Environmental Protection Act 1994
Chapter 4A Great Barrier Reef protection measures
Part 3 Environmental risk management plans
[s 97]
(3) An ERMP need not be called an environmental risk
management plan.
Example for section 96—
A person carrying out an agricultural ERA will comply with the ERMP
content requirements if—
(a) for good business practice, the person prepares a document called a
‘farm management system’ that includes an environmental
management component; and
(b) the component consists of a land management agreement under the
Land Act 1994 and other documents; and
(c) the agreement and the other documents, when read together,
comply with the ERMP content requirements, but they are not
identified as an ERMP; and
(d) the person submits the component for accreditation as an ERMP.
Division 3 Accreditation of ERMPs
97 Application of div 3
This division applies if a person has submitted an ERMP to
the administering authority for accreditation, whether or not
the person was required to do so under section 92.
98 Request for further information
The administering authority may, by written notice, ask the
person to give the authority further information or documents
about the ERMP content requirements by the reasonable date
stated in the notice.
99 Deciding whether to accredit
(1) The administering authority must decide to accredit or refuse
to accredit the ERMP—
(a) if additional information is not required—within 60
business days after receiving the ERMP; or
Current as at 20 February 2014 Page 95
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.