65-67 Elanda Street, Sunshine Beach
Site Based Stormwater Management Plan
_____________________________________________________________________________________________
1.1 Introduction
The subject site is located within Noosa Shire Council within a developed area surrounded
by existing residential dwellings. The site can be accessed by Elanda Street to the west.
The site generally falls from west towards east of the development site. The site has a total
area of approximately 0.1020 ha. The locality of the site is shown in Figure 1.1 (highlighted
in blue hatch).
Figure 1.1 Site Location
1.2 Objectives
WC Designs has been commissioned to propose a conceptual SBSMP and undertake an
assessment of stormwater quantity impact associated with the proposed development, the
objectives of this report are list below:
• Identify the increase in stormwater runoff that will be generated by the
development (if any),
• If required, propose stormwater detention system to ensure that stormwater
discharge from the post-developed site is no more than the discharge from pre-
development scenario for all storm events up to 1% AEP.
• Nominate the location of the Lawful Point of Discharge (LPD) for the
development site.
• If required, propose stormwater treatment system to ensure the stormwater
quality.
File Name: WCD-22936 – 65-67 Elanda_SWMP.docx
Revision: A 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.