2021-02-04 Special Meeting Agenda

of 11

Page text shows just the words. Original shows the document exactly as it was published.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

                       AGENDA



              Special Meeting


           Thursday, 4 February 2021

                  commencing at 9.30am
          Council Chambers, 9 Pelican Street, Tewantin



Crs Clare Stewart (Chair), Karen Finzel, Joe Jurisevic, Amelia Lorentson,
Brian Stockwell, Tom Wegener, Frank Wilkie



                    “Noosa Shire – different by nature”
Log in to download the original file

2021-02-04 Special Meeting Agenda(PDF, 271KB).pdf · 278 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 10 sections

Section 2

SPECIAL MEETING AGENDA                                  4 FEBRUARY 2021


TABLE OF CONTENTS

ITEM                                                              PAGE


ATTENDANCE & APOLOGIES                                                 -

REPORTS                                                               3

1      2021/22 NOOSA COUNCIL BUDGET – SCENE SETTING                   3

2      1920T138 DESIGN, CONSTRUCT AND MAINTAIN HINTERLAND ADVENTURE
       PLAYGROUND CONTRACT AWARD                                      5

MEETING CLOSURE                                                        -




                                                            Page 2 of 11

Section 3

SPECIAL MEETING AGENDA                                                         4 FEBRUARY 2021


REPORTS


1      2021/22 NOOSA COUNCIL BUDGET – SCENE SETTING

Author           Director Corporate Services, Michael Shave
                 Corporate Services Department

Index            ECM/ 69.05 – Corporate Services

Attachments      Nil



EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Director Corporate Services to the Special Meeting dated 4
February 2021 and note the presentations provided at the meeting by the Chief Executive Officer
and Director Corporate Services that set the scene for the beginning of the 2021/22 Council budget
process.


REPORT
Under sections 104 and 107A of the Local Government Act 2009 and section 170 of the Local
Government Regulation 2012, Council is required to adopt, for each financial year, after 31 May
before the financial year and before 1 August in the financial year, a budget and revenue statement.

Council’s budget process runs from November through to June each year and is a significant
annual project for Council, requiring considerable organisational and Councillor input to ensure
that budget decisions align with Corporate Plan objectives, Operational Plan targets and Financial
Sustainability Policy requirements.

As part of the annual budget process the Chief Executive Officer and key staff provide a scene
setting overview for Councillors that provides context for future important budget decision making.
Given the implications of COVID-19 on Council’s 2020/21 budget and potential implications for the
2021/22 budget, and as part of Council’s commencement of its 2021/22 budget engagement
process, the scene setting presentation will be considered as part of the Special Meeting and live
streamed for resident and ratepayer benefit.

Previous Council Consideration
Nil.

Finance
Nil.




                                                                                      Page 3 of 11

Section 4

SPECIAL MEETING AGENDA                                                            4 FEBRUARY 2021


Risks & Opportunities
Risks

Reputational – Council has progressed down the path of consultation on future Council budgets.
Community trust will likely be eroded should Council determine to abandon future budget
consultation.

Priorities – Engagement processes with the community can achieve sub optimal outcomes and
priority misalignment should wide engagement not occur as intended.

Opportunities

A budget consultation process is an opportunity to understand the spending priorities of our
community and ensures that effective engagement continues to retain community confidence in
Council processes and decision making.


Consultation
External Consultation - Community & Stakeholder
Nil.

Internal Consultation
Chief Executive Officer.

Departments/Sections Consulted:

 X     Chief Executive Officer    Community Services                      X   Corporate Services
       Executive Officer          Director                                X   Director
       Executive Support          Community Development                       Financial Services
                                  Community Facilities                        ICT
                                  Libraries & Galleries                       Procurement & Fleet
                                  Local Laws                                  Property
                                  Waste & Environmental Health                Revenue Services

       Executive Services         Environment & Sustainable Development       Infrastructure Services
       Director                   Director                                    Director
       Community Engagement       Building & Plumbing Services                Asset Management
       Customer Service           Development Assessment                      Buildings and Facilities
       Governance                 Economic Development                        Civil Operations
       People and Culture         Environmental Services                      Disaster Management
                                  Strategic Land Use Planning                 Infrastructure Planning,
                                                                              Design and Delivery




                                                                                           Page 4 of 11

Section 5

SPECIAL MEETING AGENDA                                                         4 FEBRUARY 2021


2    1920T138 DESIGN, CONSTRUCT AND MAINTAIN HINTERLAND ADVENTURE
     PLAYGROUND CONTRACT AWARD

Author            Project Officer, Paul Brennan
                  Infrastructure Services Department

Index             ECM / Projects & Contracts (T1) / 1920T138 Design, Construct and Maintain
                  Hinterland Adventure Playground Contract Award / Council Reports
                  ECM / Subject / Contracting / Parks & Reserves

Attachments       Nil


EXECUTIVE SUMMARY
Not applicable.

RECOMMENDATION
That Council note the report by the Project Officer to the Special Meeting dated 4 February 2021
and award a tender for the Design, Construction and Maintenance of the Hinterland Adventure
Playground to Aspect Contractors for the lump sum price of $3,761,256.59 excluding GST.



REPORT
1.   Tender Background and Procurement Process adopted for Project Delivery of the
     Hinterland Adventure Playground
The project scope, design and operational costs for the Hinterland Adventure Playground were all
assessed as high-risk from the perspective of receiving pricing from suitably experienced
contractors that would meet the available budget, as well as defining reasonable ongoing costs for
maintaining the site once it is opened (refer discussion in previous Council Report from August
2019). Project staff, in conjunction with Procurement staff and Council-appointed legal consultants,
subsequently developed a procurement model for the project delivery which sought to minimise
Council’s financial risk and provide maximum flexibility when finalising costs and contract
negotiation.

The following process was adopted:
Step 1.     Request for Expression of Interest (EOI) in accordance with the Local Government Act
            2009 via the Vendorpanel Marketplace system from the marketplace for the project
            delivery (approved by Council in August 2019);
Step 2.     Develop a select tender list of appropriately qualified tenderers following the EOI
            evaluation;
Step 3.     Request for Design Construction Maintenance (DCM) Tender in accordance with the
            Local Government Act 2009 via the Vendorpanel Marketplace system from the select
            list of tenderers;
Step 4.     Select a preferred contractor following the Tender assessment;
Step 5.     Award an Early Contractor Involvement (ECI) contract with preferred DCM contractor
            to finalise scope and price;
Step 6.     Accept final scope and price and closeout the ECI contract;
Step 7.     Council awards DCM Tender to preferred contractor based on final scope and price
            (this report).


                                                                                      Page 5 of 11

Section 6

SPECIAL MEETING AGENDA                                                           4 FEBRUARY 2021


2.    Early Contractor Involvement (ECI) process
Whilst the above process is broadly familiar under current Council procurement procedures, the
ECI process is relatively new. It was added as an additional step for contractually allowing formal
negotiations to occur with a preferred tenderer, in the event the initial pricing exceeded the budget.
The process adopts an open-book approach, with all elements of the design, scope and pricing up
for review. The intent is to seek, prior to awarding the construction contract, a level of contractor
involvement such that they work closely with Council and the lead design consultants in order to
finalise a scope of works that suits the available budget, still meets Council’s intentions for the
project, and leverages the preferred contractor’s expertise and experience on projects of this
nature. There is an added advantage in building an ongoing relationship with the contractor and
agreeing on key elements for the project delivery prior to construction award, helping to promote a
deeper understanding of the delivery requirements from all contractual parties.

It is important to note that no commitment is made on either party for awarding the subsequent
construction contract, and that the process may end at any stage without prejudice and cost or
damages claims if negotiations cannot be finalised. Also, by adding responsibility for design
completion into the follow-up contract, it commits the contractor into documenting the final scope
of works for the revised price.

3.    Select Design, Construction and Maintenance (DCM) Tender
A select list of six (6) tenderers were invited to submit tenders for the DCM, following an Expression
of Interest process that received nine (9) submissions. The invitation to tender was released via
VendorPanel on 21 February 2020. The tender closed on 15 April 2020 which was an extension to
the original closing date - this was granted by Council following feedback that tenderers were
struggling to compile timely submissions due to operational impacts from the initial lockdown of
COVID-19. Three (3) conforming tenders were received.

The tender evaluation panel undertook an assessment of the tender submissions from the following
respondents, which are listed in alphabetical order:
1)    Aspect Contractors;
2)    Naturform Pty Ltd;
3)    Eureka Landscapes Pty Ltd.

The tenders were evaluated using the following criteria:
•     Design and Construct Capabilities and Experience;
•     Stakeholder Engagement;
•     Quality Management Systems;
•     Workplace Health and Safety Systems;
•     Local Economy, and;
•     Price.

The three selected DCM tender prices initially submitted were $5,349,313.11 (Aspect Contractors),
$6,004,397.38 (Naturform Pty Ltd) and $6,516,795.26 (Eureka Landscapes Pty Ltd) excluding
GST.




                                                                                        Page 6 of 11

Section 7

SPECIAL MEETING AGENDA                                                           4 FEBRUARY 2021


4.    Design, Construction and Maintenance (DCM) Tender Assessment and Early
      Contractor Involvement (ECI) Award
The tender evaluation team finalised their tender evaluations using the above criteria and following
further clarifications with Aspect Contractors, they were subsequently awarded an ECI contract to
review the scope and pricing. The tender submission from Aspect Contractors was the most
favourable as they have significant previous experience with construction of similar projects, a
strong track record with Council, are highly capable, and have the necessary resources to meet
Council’s program to complete these works by December 2021. Encouragingly, they also have
experience with the ECI process, having undertaken the same process on similar projects.

The ECI process was undertaken with Aspect Contractors from July 2020 through to December,
with Aspect Contractors submitting a final price of $3,761,256.59 excluding GST. Council considers
this price offers the best value for money against the revised scope of works.

5.    Development Applications and Approval Conditions
Council approved Development Applications (DAs) for the playground site (MCU20/0013) and
adjacent Lower Mill area carpark (MCU20/0012) at its Special Meeting on 27 January 2021. A
number of conditions were imposed on the approvals which project staff are working through, in
order to assess the impact of these on the current scope and budget along with the appropriate
actions that will need to be taken in finalising the construction scope of works and associated costs.
It should be assumed a number of elements will require some additional funding that has yet to be
identified.

6.    Programme and Next Steps
Pending Council approval, Aspect Contractors have indicatively proposed a construction schedule
that completes the site by December 2021, inclusive of initial design activities, wet weather
allowances, and lead times for supply of certain items and defects rectification. There is a targeted
commencement of works in March-April 2021 with practical completion to be achieved at the
beginning of December 2021. It should be noted that this schedule is yet to be finalised and is
subject to a number of factors, including design finalisation, final assessment on the development
application approval conditions, grant-funding requirements and materials/stock availability (refer
Risks and Opportunities below).

7.    Construction Management and Inspections
Under the Design-Construct delivery model, Council will maintain the overall project management
role. This will be supported by Council’s Contracts and Project Superintendent. Specialist
architectural and engineering consultants, appointed by the contractor, will progressively inspect
the works to ensure project objectives and approval conditions are met. In addition some specific
plumbing elements will be inspected by Council staff as part of the regulatory approvals process
required under the Plumbing Act.


Previous Council Consideration
Ordinary Meeting Minutes, 15 August 2019, Item 8, Page 15
That Council note the report by the Project Officer to the General Committee Meeting dated 12
August 2019 regarding the proposed Hinterland Playground at Cooroy and:
A.    Note the general project update; and
B.    Note the specific updates to the capital and operating cost estimates.
C.    Make the Cooroy Hinterland Playground Economic and Financial Analysis available to the
      public on Council’s website.



                                                                                        Page 7 of 11

Section 8

SPECIAL MEETING AGENDA                                                                4 FEBRUARY 2021


Ordinary Meeting Minutes, 15 August 2019, Item 9, Page 15
That Council note the report by the Project Officer to the General Committee Meeting dated 12
August 2019 and authorise staff to call for Expressions of Interest for the Design, Construction and
Maintenance of the Cooroy Hinterland Playground.
Special Meeting Minutes, 27 January 2021, Item 2, Page 2
That Council note the report by the Coordinator Planning to the Special Meeting dated 27 January
2021 regarding Application No. MCU20/0012 for a Development Permit for Material Change of Use
- Transport - Type 2 Car Park situated at 4-8 Lower Mill Road, Cooroy and MCU20/0013 for a
Development Permit for Material Change of Use – Open Space Type 1 Sport and Recreation
(Playground) at 1, 3 and 9 Maple Street, Cooroy and:
A.      Approve Applications MCU20/0012 and MCU20/0013 in accordance with the conditions
        contained in the Special Meeting Minutes dated 27 January 2021.
B.      Note the report is provided in accordance with Section 63(5) of the Planning Act 2016.
Finance
A BR2 budget of $739,554.00 excluding GST has been allocated for the 2020/21 financial year,
with the balance of funds to be allocated in 2021/22 under the 10-year Capital Works Program.
Note that this does not include funding for delivering the Maple Street car-parking and pedestrian
street improvements – this is funded as a separate project in the current capital works program
(refer discussion below).
 Item                           Cost ex GST         Comments
 Design + Construction            $3,761,256.59     Based on outcomes from Early Contractor Involvement
 Contract with Maintenance                          process
 provisions
 Contingency (10%)                $ 376,126.00      This level of contingency is appropriate for the type of
                                                    construction and covers unforeseen issues onsite and
                                                    during the delivery of the contract
 QLeave (0.575%)                  $     29,900.00   Based on full project estimated cost for playground
                                                    ($5.2M) – refer Council Report August 2019
                      TOTAL       $4,167,282.59

The contingency noted above is for the construction contract only and does not cover the potential
additional costs discussed in Section 5 above or in ‘Risks and Opportunities’ below.
Total project costs have continued to be refined since the last Update Report issued to Council in
August 2019. The latest estimate is as follows:
 ESTIMATE                                    Cost ex GST        Comments
 DCM Contract                                  $4,167,282.59    As above
 Maple Street Carpark and Raised               $ 517,647.00     Latest Estimate January 2021
 Crossing costs
 Costs to June 2020                            $ 637,000.00     Costs related to Planning, Design,
                                                                Approvals and Procurement in years
                                                                2015-2020
 Other identified remaining costs for          $ 656,976.45     Refer discussion below
 additional works
            TOTAL PROJECT ESTIMATE             $5,978,906.00
 Revenue LGGSP Grant-funding                   $2,788,770.60    To be expended by December 2021
               TOTAL COSTS COUNCIL             $3,190,135.40


                                                                                              Page 8 of 11

Section 9

SPECIAL MEETING AGENDA                                                         4 FEBRUARY 2021


The related project Cooroy Maple Street carpark and raised pedestrian crossing will be the subject
of a separate tender report to Council shortly. The current estimate for this project, inclusive of
services relocation and installation, and contingencies, is $517,647.00 excluding GST.
Identified remaining cost estimates for additional works and unforeseen items include the following:
•    Purchase of Road Reserve land from State Government at playground site
•    Additional requirements as a result of the DA approval conditions – mainly associated with
     flood management and environmental improvements, along with some site-specific signage,
•    Services relocations (water mains),
•    Early tree and plants procurement,
•    Allowance for temporary shade structures after research and feedback into recent
     playground constructions in SE Qld (these are to remain in place until the tree canopy
     matures), and
•    Contaminated Land management.


Risks & Opportunities
Finance risks include:
•    Cost of construction exceeding budget. The ECI process has alleviated the majority of
     concerns that future construction costs may exceed the budget allocation. Nevertheless, this
     will be carefully managed throughout the construction period by utilising the Project Control
     Group and Budget approval processes. Opportunities for additional funding through other
     upcoming grant-funding rounds are also being investigated by project staff and
     representatives from Finance.
•    Development Application (DA) approval conditions. The conditions included in the DA
     approval will impose a number of additional costs to the project that were not originally
     foreseen. Some anticipated items were allowed for in the most current scope of works but a
     few remain to be determined. The budget will continue to be finalised in the coming weeks
     as each condition is assessed and quantified.
•    Client request for scope changes. This will be mitigated through Project Control Group
     management and limitation of client requested scope variations.
•    Latent conditions. Typically a geotechnical risk, extensive previous investigations have
     mitigated much of this risk. There is some residual risk associated with unforeseen
     conditions, given the industrial history of the site and potential hidden defects that will be
     carefully monitored.
•    Variation risks. This has been partly mitigated through the lump sum construction
     procurement method with further mitigation through using an ECI process and post-tender
     clarifications, tying Aspect Contractors firmly into the scope of works.
•    Contingency amount being insufficient. This risk has to an extent been mitigated through the
     ECI process, along with the risk profile adopted for this type of project informing an
     appropriate allocation of contingency level.

Time risks include:
•    Wet weather delays. Construction during the typically dry season aims to mitigate this. Some
     wet-weather day allocations have been built into the programme, given the current La Nina
     weather pattern.
•    Delays in obtaining final approvals. These have been built into the pre-construction program.
•    Delays from equipment suppliers. Some equipment is required to be sourced from interstate
     and possibly overseas and may experience delays. The contractor has factored this into their
     construction program.



                                                                                      Page 9 of 11

Section 10

SPECIAL MEETING AGENDA                                                           4 FEBRUARY 2021


•     Grant-funding mandated schedule. The current Local Government and Grants Subsidies
      Program (LGGSP) requires construction completion by end-of-December 2021. Whilst this
      has been factored into the current construction schedule, the programme will be monitored
      to ensure compliance is maintained, with any potential requests for variation to the schedule
      identified well in advance.

Safety Risks;
•    Aspect Contractors will be appointed as the Principal Contractor and responsible for
     Workplace Health and Safety of the construction site. Prior to construction commencing,
     workplace health and safety and pedestrian and traffic management plans will be required
     to be submitted to Council for approval. Council will undertake regular audits on contractor
     compliance with these approved plans throughout construction.

Scope and Quality Risk;
•    The risk of meeting project objectives will be managed through Council staff reviews
     supported by specialist consultants who developed the performance specifications.
•    Quality requirements. Given the high quality expectations for much of the finished play-
     spaces and outdoor areas, a dedicated Council project officer will be assigned to monitor
     and direct the contractor specifically on issues of quality and compliance.
•    Public Art. The rationalisation of the delivery cost and scope of works that occurred during
     the ECI process resulted in reducing or removing a number of non-essential design elements
     that were included in the original scope of works. However, budget allocations for
     incorporating art into the site was defunded, which may not suit the vision for the site given
     the ‘iconic’ nature of the brief. Whilst the overall project design remains reasonably intact, it
     is hoped an alternative source of funding may reinstate many of these elements prior to
     construction completion, with artwork a priority if this occurs.

Resource Risk;
•   Aspect Contractors have nominated a highly capable team for this project limiting the
    resourcing risks to this project. The addition of external architectural and engineering
    consultants, mitigates the resourcing risk from Council.
•   Council are currently resourcing additional staff to the Infrastructure Planning, Design and
    Delivery section which will help ensure sufficient project management time and attention is
    given to the project in the 2020/21 and 2021/22 financial years.

Consultation
External Consultation - Community & Stakeholder
External Reference Group:
•    Cooroy Futures Group
•    Cooroy Area Resident’s Association

Internal Consultation
Chief Executive Officer, Community Services, Corporate Services, Environment & Sustainable
Development, and Infrastructure Services.




                                                                                      Page 10 of 11

Section 11

SPECIAL MEETING AGENDA                                                             4 FEBRUARY 2021


Departments/Sections Consulted:

 X   Chief Executive Officer   X   Community Services                      X   Corporate Services
     Executive Officer             Director                                X   Director
     Executive Support             Community Development                   X   Financial Services
                                   Community Facilities                        ICT
                                   Libraries & Galleries                   X   Procurement & Fleet
                                   Local Laws                              X   Property
                                   Waste & Environmental Health                Revenue Services

     Executive Services        X   Environment & Sustainable Development   X   Infrastructure Services
     Director                      Director                                X   Director
     Community Engagement      X   Building & Plumbing Services                Asset Management
     Customer Service          X   Development Assessment                  X   Buildings and Facilities
     Governance                    Economic Development                        Civil Operations
     People and Culture        X   Environmental Services                      Disaster Management
                                   Strategic Land Use Planning             X   Infrastructure Planning,
                                                                               Design and Delivery




                                                                                          Page 11 of 11

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.