2022-05-16 GC Agenda - Item 7 - Attachment 2 - Noosa Oyster Ecosystem Restoration Project - Project Restoration Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn · The distance between oyster reef patches is specified in the engineered drawings for each
restoration site. The relief and profile of each patch is specified in the engineered drawings for each
restoration site.
Restoration modules
· Engineering concepts to show how oyster reef patches may be placed in association with each
other on a restoration site, while meeting specific engineering requirements.
1.9 Summary of restoration targets
An oyster ecosystem restoration site should over time demonstrate an increase in abundance and
density of rock oysters and increased diversity of epifauna comparative to the surround sediments.
Specifically, within 6-8years of oyster reef patches being deployed, a restoration site should
demonstrate:
• Density of rock oysters at restoration site average of > 200 individuals/m2
• 4+ age classes of rock oysters present at restoration site (= approx. 2 cohorts of oysters
reproductive)
➢ 5% of rock oyster population at the site is 3+ years old
• Increased density of oyster recruits with 3-4 reproductive cycles
• 5 times more epifauna on oyster habitat than on surrounding sediment10
1.10 Qualifications
All information in this submission, and attached code assessments, relating to the design, footprint
minimisation, specification, construction, movement, sinkage, stability, erosion minimisation, risks and
management and substrate rectifications relating to the restoration substrates (of rock, or rock and
shell), are made with the approval of the project’s consultant engineers, International Coastal
Management (ICM).
All information in this submission, and attached code assessments, relating to oyster ecosystem
restoration, fish habitats and marine plants in the Noosa River, have been reviewed by TNC ecologists
as well as TNC’s independent consultant ecologists, Ecological Service Professionals (ESP).
In 2020, TNC also contracted ESP to map the extend of seagrass and other marine habitats throughout
the Noosa River estuary. The results of that work are incorporated into on the restoration drawings and
advised the placement of the restoration substrates (the footprint) in each restoration site so as to
avoid impact on marine plants, or to cause only temporary impact on marine plants, as is the case at
the Tewantin restoration site.
10
McAfee et al 2020. The value and opportunity of restoring Australia's lost rock oyster reefs. Restoration
Ecology Volume 28, Issue 2 March 2020. https://doi.org/10.1111/rec.13125
14
Document Set ID: 21802641
Version: 1, Version Date: 31/01/2022
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.