2022-05-16 GC Agenda - Item 7 - Attachment 2 - Noosa Oyster Ecosystem Restoration Project - Project Restoration Plan

of 75

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
                    Public access:     A dual carriage way with a minimum of 8m width will be maintained to allow
                                       access to the boat ramp along Hilton Esplanade.

                                       A dual public boat launch area 12m wide will be maintained along the
                                       shoreline. Note that the formal dual boat ramp at Tewantin is 10m wide.

                                       Adequate vessel reversing area will be maintained between site areas A and B.

                                       Access to Hilton Esplanade from Hilton Terrace via the pathway leading from
                                       Hilton Terrace will be maintained.

                                       Commercial operators wishing to use the ramp may negotiate temporary
                                       access to the shoreline directly with the project’s construction contractor.

                    Public safety:     Load out site areas A and B will be fenced using commercial fencing as will a
                                       2.5m corridor joining areas A and B.

                                       Signage will be used on the fencing to inform the public about the site, its
                                       purpose and cautions.

                                       The barge will only come ashore within site area A.

                                       The construction company will use standard traffic control methods to ensure
                                       the public is separated from truck movements at the end of Hilton Esplanade
                                       and operations between site area A and B.

                    Public             A public notification regarding the works will be printed in the Noosa News
                    notifications      two weeks prior to commencement of activities.

                                       An announcement will be made in the Noosa Council’s circular.

                                       Relevant authorities will be notified of works prior to commencement.

                                       Public notification signage will be posted at the site and will include a QR code
                                       which connects to online information about the construction process:
                                       Timeframe, purpose, activities, further information.

                                       Tourism facilities adjacent to the site will be specifically notified and met with
                                       to explain the work schedule.

                    Noise              Truck movements and barge loading will take place between 7am and 6pm
                    management:        weekdays, and between 8am and 5pm on weekends.

                    Environmental      Trees will be protected from harm from machinery and fencing. Fencing will
                    management:        be placed at a distance from the tree line and visible tree roots will be
                                       avoided.

                                       The site will be kept clear of debris/refuse.

                                       The site will be rehabilitated to its pre-use condition or better.




                                                                                                                            59




Document Set ID: 21802641
Version: 1, Version Date: 31/01/2022
Log in to download the original file

2022-05-16 GC Agenda - Item 7 - Attachment 2 - Noosa Oyster Ecosystem Restoration Project - Project Restoration Plan(PDF, 7MB).pdf · 7.0 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.