Golden Gully Thoroughbreds, 48 Princess Street Cooran Supporting Document for the Operational Works Permit

As part of our Operational Works application, I have provided an overview of the controls that we have currently in place for the topsoil that has been placed on our property at 48 Princess St Cooran. The topsoil material in question has been stored at the address mentioned above from the Six Mile Bridge development project for CMC. The topsoil material will be returned to site as part of the final landscaping works required as part of the project. The topsoil material will be stored at the address mentioned above for 6 months and the relocation of the material will commence in July or August 2023.
As part of this document, we have broken it down into 2 sections.
Onsite Top Soil Stabilisation and Protection
Removal of Top Soil from 48 Princess St to the Six Mile Creek Bridge Project Site

Onsite Top Soil Stabilisation and Protection
A list of controls that have been undertaken to stabilise the soil to avoid any erosion of the soil into any waterways. The list of controls were discussed onsite with Noosa Council representatives on 20th March 2023, and the list of controls mentioned were all completed within a week of Noosa Council’s site visit. All controls have been outlined by the RPEQ Certified ESCP engineer in a ESCP plan and has been submitted as part of this application.
Golden Gully Thoroughbreds, Simon Adams and CMC to apply for an Operational Works permit. CMC to engage a RPEQ certified ESCP Engineer to complete an ESCP plan and complete the Operational Works application.
Golden Gully and Simon Adams to move the leading edge of the top soil pile so a second silt fence barrier can be installed. Simon to ensure the angle on the leading edge is no greater than 1 is to 3.
Golden Gully and Simon Adams to instruct CMC to build a 2nd silt fence 1.3-1.5m inside the existing silt fence. Simon Adams to oversee this project.
Golden Gully and Simon Adams to seed and maintain the area between the 2 silt fences.
As per the ESCP plan a bund is to be built in front of the top soil material. This works will be completed by Monday 15th May 2023.
Simon Adams to take photos and short videos of the area of concern each month or after a weather event. This has completed monthly and sent to Noosa Council Representatives.

Removal of Topsoil from 48 Princess St to the Six Mile Creek Bridge Project Site
The topsoil material is only being stored on site as a temporary measure, until it will be returned to CMC’s Six Mile Bridge project. Before any of the material is relocated from 48 Princess St to the project site, the following measure must be in place-
A site meeting to be a meeting held with all stake holders. The stake holders will be Simon Adams, Noosa Council and CMC. This meeting will be used to discuss truck movements, neighbourhood awareness, road maintenance, and project overview. Completed before removing topsoil.
CMC will install Rumble grid to install at the front gate of the property at 48 Princess St to ensure all loose material is not taken on to the main roads.
All neighbours will be informed of all relocation works, including time frames, number of trucks and frequency of each run by means of a letterbox drop, with opportunity to voice concerns provided. Concerns raised and complaints will be recorded and relayed to the Council.
No trucks will run before 8am or after 4.30pm.
Relocation works will be limited to 3 trucks on a round trip on each day of topsoil relocation works.
A CMC water truck will water the gravel road at the front of the property at 48 Princess St at least 4 times per day whilst the topsoil material is being relocated back to site.
A dilapidation report will be conducted to record the current condition of the haul route from the property to site.
CMC will repair any damage created on Princess St (gravel road) through topsoil relocation works.
The rumble grid and remaining erosion and sediment control measures will be removed and the disturbed are revegetated.

This document will be included as part of our Operational works permit, along with the RPEQ Certified ESCP plan and Monthly Update Documents. Further information available on request.
Log in to download the original file

Additional Information for Operational Works Application 05.05.2023.docx · 17 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.