Permissible Change Decision Notice Approval or App in Part - 010.2008.00000255.002 [As Published] · 132008.255.02
2008/255
9. All hot water systems installed shall be either solar systems; electric heat pump systems; or
gas systems (LPG or natural).
10. Existing trees on the site and within road reserves are to be retained, except where required to
be removed due to building operations or the conduct of the approved use. In this regard, the
removal of vegetation shall not extend beyond 3 metres of the building footprint of the
Detached House.
11. All other vegetation shall be protected from interference resulting from clearing or construction
activities by:
11.1. Clearly marking vegetation to be retained with flagging tape;
11.2. Installing protective fencing around the drip line of the vegetation;
11.3. Stockpiling, storage and vehicle parking occurs in already cleared areas and does not
cause interference with vegetation; and
11.4. Low impact construction techniques are used around vegetation to minimise
interference with the vegetation.
12. Cleared vegetation is to be suitably processed by one of the following methods and removed
from the site: -
12.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
minimum of 10 metres between edges of heaps.
12.2. Disposal for firewood.
12.3. Disposal for landscaping purposes.
12.4. Transport to alternative site for breaking down materials provided that all necessary
permits have been obtained to allow the alternate site to be used for this purpose.
12.5. The Applicant is advised that other methods may be considered provided full details of
the method are submitted.
12.6. The applicant is advised that burning off is an unacceptable method of disposal.
13. Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
not constructed under overhead electricity transmission lines, or within any easements.
14. Sediment and erosion control measures must be in place prior to works commencing. If such
measures are not in place or are not satisfactory, ‘on the spot’ fines may be issued. Such fines
can be issued if sediments from the site are found to enter or have the potential to enter
Council’s stormwater system or natural waterways.
15. The site is to be landscaped in accordance with Council’s Policy on Landscaping Guidelines.
Landscape construction shall be implemented in accordance with the horticultural industry
best practices.
Currency
16. The Development Permit for a material change of use lapses if the use has not happened by
14 August 2012, unless an application to extend the currency is approved by Council.
5 REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:
Referral Trigger Referral Status Referral Agency Referral Address
Nil
Page 3 of 7
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Permissible Change Decision Notice Approval or App in Part - 010.2008.00000255.002 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 54 KB (small file)
- File type
No other editions are linked here.