Delegated Report - Code - Planning OPW22 0303 [As published] · OPW22/0303
22196449 1 Tree Management Plan by Consult 21 November 2023
Arborist
CURRENCY PERIOD
2. The Currency Period for this development approval lapses if the development has not
substantially started by 26 April 2025, unless an application to extend the currency period is
approved by Council.
Site Specific Conditions
3. The required stormwater storage tanks must be clearly shown on the hydraulic drawings
approved through the building permit.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
4. Submit amended plans to Council as described in the List of plans requiring amendments.
Plans must be submitted and approved prior to the pre-start meeting.
5. Tree protection fencing must be installed under the supervision of the qualified person*.
(Refer to Advisory Note)
6. All necessary approvals from external service providers (eg Unitywater) and external parties
on which the development works are proposed have been obtained and a copy supplied to
Council.
7. A condition report of the Council drainage system within the frontages of the site must be
completed for agreement at the prestart meeting.
8. A condition report including photographs of the frontage of the site must be completed and
submitted to Council at the prestart meeting / prior to any works commencing.
9. Certificates demonstrating currency of public liability insurance and works insurance covering
the works must be submitted to Council prior to the prestart meeting.
10. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. Civil engineering works;
b. Arboreal works.
c. Fauna management works.
d. Landscape works.
e. Erosion and sediment control works;
f. Other relevant parties
11. A Construction Management Plan must be submitted to Council at least 5 business days
prior to the pre-start meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
Control Devices (MUTCD) detailing all temporary signage and traffic control
measures prior to construction.
ii. Maintenance of safe vehicle and pedestrian access across the frontage of the
site both during daily construction and after daily construction has ceased
iii. Proposed fencing to the site during the construction phase of the development
iv. Adequate parking arrangements for construction workers
Page 6 of 18
Document Set ID: 22338918
Version: 6, Version Date: 21/04/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Delegated Report - Code - Planning OPW22 0303 [As published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 353 KB (small file)
- File type
No other editions are linked here.