Appendix C - Engineering

of 27

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Original PDF page 3, section 1. The text section number identifies this passage in the reader.

                                                    GENERAL NOTES                                                                         ANDSTOCKPILE ON SITE OR REMOVE FROM SITE AS DIRECTED.                                                                       STRUCTURAL FILL.                                                                                REQUIREMENTS OF THE GEOTECHNICAL ENGINEER AS OUTLINED IN THE
                                                                                                                                      19. DRAWINGS TO BE READ IN CONJUNCTION WITH ARCHITECT, SURVEYOR,                                                         3.     UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR                                        GEOTECHNICAL INVESTIGATION REPORT BY TECTONIC. TEMPORARY
                                                    1.   ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN.                       HYDRAULICS, ETC. CONSULTANT AND CONTRACTOR DRAWINGS.                                                                        SOFT MATERIALS ENCOUNTERED SHOULD BE REMOVED DURING                                             UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE FORMED
                                                                                                                                                                                                                                                                      SUBGRADE PREPARATION FOR BULK EARTHWORKS. ALL UNSUITABLE                                        AT 1V:2H, AND IN MEDIUM DENSE SAND AT 1V:1H FOR BATTERS UP TO
                                                    2.   ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE                         20. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT                                                                         MATERIAL TO BE REMOVED FROM SITE AT CONTRACTORS EXPENSE.                                        3M IN HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY THE
                                                         CONTRACTOR. CONTRACTOR TO ALLOW FOR ALL MEANS NECESSARY                          AUTHORITY: ROAD OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN                                                                                                                                                                  GEOTECHNICAL ENGINEER.
                                                         TO ACCURATELY SETOUT THE WORKS.                                                  FOR ALL WORKS WITHIN COUNCIL ROAD RESERVES. CONTRACTOR TO                                                            4.     COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES
                                                                                                                                          ALLOW FOR ALL COSTS ASSOCIATED WITH IMPLEMENTATION OF THE                                                                   SUBSTANTIAL VOLUMES OF WATER COMBINED WITH VIBRATORY                                         21. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE
                                                    3.   ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT                           TMP.                                                                                                                        COMPACTION EQUIPMENT. CARE MUST BE TAKEN TO ENSURE THERE                                         ACHIEVED, TEMPORARY SHORING WILL BE REQUIRED UNDER THE
                                                         SPECIFICATIONS AND WHERE FURTHER DETAILS ARE REQUIRED THE                                                                                                                                                    ARE NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE                                         ADVICE OF A SPECIALIST SHORING CONTRACTOR.
                                                         CONTRACTOR SHALL REFER TO NOOSA SHIRE COUNCIL DEVELOPMENT                    21. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL                                                                      COMPACTED IN ACCORDANCE WITH GEOTECHNICAL REPORT AND
                                                         GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES, ASSOCIATED                         AUTHORITY APPROVALS RECEIVED FOR THE PROJECT AND IN                                                                         AS1289.                                                                                      22. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE
                                                         STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.                                      ACCORDANCE WITH OPW APPROVALS BY COUNCIL.                                                                                                                                                                                    SPECIFIC DESIGN TO PREVENT UNDERMINING WHICH SHOULD BE
                                                                                                                                                                                                                                                               5.     A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE                                           CARRIED OUT BY A SUITABLY QUALIFIED AND EXPERIENCED RPEQ
                                                    4.   SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED                           22. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE                                                                   REQUIRED ON SOIL SUBGRADES ALONG HAUL ROADS AND LAYDOWN                                          STRUCTURAL ENGINEER.
                                                         OUTSIDE OF THE TOLERANCES SPECIFIED WITHIN THE PROJECT                           BOUNDARY WITHOUT FORMAL APPROVAL BY THE OWNER/CUSTODIAN                                                                     AREAS TO IMPROVE TRAFFICABILITY. SPECIFIC PLATFORM DESIGN
                                                         SPECIFICATION AND LOCAL AUTHORITY REQUIREMENTS, THE                              OF THAT LAND INCLUDING BUT NOT LIMITED TO PRIVATE PROPERTY,                                                                 WOULD BE REQUIRED PRIOR TO MOBILISATION AND TRAFFICKING OF                                   23. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT
                                                         CONTRACTOR WILL RECTIFY AT THEIR COST INCLUSIVE OF ANY                           ROAD RESERVE, PARKS/OPENSPACE, EASEMENTS.                                                                                   ANY HEAVY MOBILE PLANT ON THE SITE.                                                              ANY CONSTRUCTED CUT/FILL BATTERS AND RETAINING STRUCTURES
                                                         ADDITIONAL COSTS INCURRED BY RECOR.                                                                                                                                                                                                                                                                           ON THE SITE HAVE ACHIEVED ADEQUATE STABILITY WITH A LONG-TERM
                                                                                                                                      23. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION                                                            6.     IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND                                             FACTOR OF SAFETY AGAINST GEOTECHNICAL FAILURES TO THEIR
                                                    5.   EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND                       DRAWINGS AND APPROVALS ON SITE AT ALL TIMES.                                                                                COMPACTED WHERE UNSUITABLE NATURAL MATERIALS ARE LOCATED                                         SATISFACTION.
                                                         AS SUCH THEIR ACCURACY CANNOT BE GUARANTEED. NO                                                                                                                                                              AND AS OTHERWISE NECESSARY TO OBTAIN SUBGRADE/PLATFORM
                                                         RESPONSIBILITY IS TAKEN BY RECOR OR THE PRINCIPAL FOR THE                                                                                                                                                    LEVEL. IMPORTED GENERAL FILL MATERIAL SHALL BE CLEAN GRADED                                  24. EARTHWORKS LEVELS SHOWN ARE FINISHED SURFACE LEVELS
                                                                                                                                      24. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN
                                                         ACCURACY AND COMPLETENESS OF THIS INFORMATION. IT IS THE                                                                                                                                                     MATERIAL FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM                                         INCLUSIVE OF TOPSOIL LAYER. REFER TO STRUCTURAL ENGINEERING
                                                                                                                                          ACCORDANCE WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN
                                                         RESPONSIBILITY OF THE CONTRACTOR TO ACCURATELY ESTABLISH                                                                                                                                                     PARTICLE SIZE OF 100MM AND CAPABLE OF BEING COMPACTED INTO                                       DRAWINGS FOR BUILDING SLAB THICKNESSES AND HYDRAULIC
                                                                                                                                          AND CONSTRUCTION CODE (2013).
                                                         THE LOCATION AND LEVEL OF ALL EXISTING SERVICES PRIOR THE                                                                                                                                                    COHERENT FILLING TO THE SPECIFIED STANDARD. THE MATERIAL                                         DRAWINGS FOR SUB-FLOOR DRAINAGE FOR DETERMINATION OF
                                                         COMMENCEMENT OF ANY WORKS. ANY DISCREPANCIES SHALL BE                                                                                                                                                        SHALL HAVE A MAXIMUM PLASTICITY INDEX OF 15%, A SHRINK-SWELL                                     REQUIRED BULK EARTHWORKS SURFACE.
                                                         REPORTED TO THE SUPERINTENDENT. CONTRACTOR TO LOCATE AND                     STANDARD SIGNS AND LINE MARKING NOTES                                                                                           INDEX OF LESS THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
                                                         PROTECT SERVICES AS REQUIRED DURING PROPOSED WORKS.                          1. GENERAL                                                                                                                                                                                                                   25. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE
                                                                                                                                        a. ALL SIGNS AND PAVEMENT MARKING IS TO BE IN ACCORDANCE WITH                                                          7.     ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE                                      GEOTECHNICAL ENGINEERS REQUIREMENTS. CONTRACTOR TO ALLOW
                                                    6.   THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND                        THE QUEENSLAND TRANSPORT MANUAL OF UNIFORM TRAFFIC                                                                         CONTENT FOR STANDARD COMPACTION.                                                                 FOR THE IMPORT AND REMOVAL OF ALL NECESSARY MATERIAL TO
                                                         SURVEY ALL CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS                         CONTROL DEVICES (CURRENT EDITION).                                                                                                                                                                                          UNDERTAKE THE PRELOADING OPERATIONS.
                                                         SHOWN ON THE DRAWINGS INCLUDING ANY POTENTIAL EXISTING                                                                                                                                                8.     ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE
                                                                                                                                      2. SIGNS
                                                         SERVICES CLASHES PRIOR TO COMMENCEMENT OF CIVIL WORKS.                                                                                                                                                       PROPERTY BOUNDARY OF THE SUBJECT SITE, INCLUDING REAR OF
                                                                                                                                        a. ALL SIGNS TO BE REFLECTORISED CLASS 1 TO AS1906.1:2007 UNLESS                                                                                                                                                           26. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
                                                         CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO                                                                                                                                                        RETAINING WALL DRAINAGE INFRASTRUCTURE FOR RETAINING WALLS
                                                         RECOR AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL                        NOTED OTHERWISE.
                                                                                                                                                                                                                                                                      IN CUT. RETAINING WALLS ARE TO BE PREPARED IN ACCORDANCE WITH
                                                         WORKS.                                                                         b. SIGNS ARE TO BE INSTALLED WITH THE FOLLOWING CLEARANCES TO                                                                 STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE
                                                                                                                                           EDGE OF SIGN: LOCATION CLEARANCE NO KERB 600 BEHIND GUIDE                                                                  WITH CONSTRUCTION REQUIREMENTS OF GEOTECHNICAL REPORT.                                       INSPECTIONS:
                                                    7.   ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS                       POSTS BARRIER KERB 300 FROM FACE MOUNTABLE KERB 500 FROM                                                                                                                                                                THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS
                                                         SHALL BE RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS,                             FACE OF KERB.                                                                                                       9.     REFER   ARCHITECT/LANDSCAPE     ARCHITECT    DRAWINGS                          FOR           BEFORE ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR
                                                         FOOTPATHS, CONCRETE AREAS, GRAVEL AREAS, GRASSED AREAS AND                                                                                                                                                   CONFIRMATION OF RETAINING WALL COLOUR AND FINISH.                                            IS TO PROVIDE A MINIMUM OF 72 HOURS NOTICE TO RECOR FOR REQUIRED
                                                         ROAD PAVEMENTS.                                                                c. PARKING CONTROL SIGNS TO BE MOUNTED TO FACE APPROACHING
                                                                                                                                                                                                                                                                                                                                                                   INSPECTIONS. SHOULD THE CONTRACTOR FAIL TO REQUEST AN
                                                                                                                                           TRAFFIC AT 45° TO KERB OR CARRIAGEWAY EDGE. ALL OTHER SIGNS TO                                                                                                                                                          INSPECTION, THE CONTRACTOR WILL BE RESPONSIBLE FOR ALL COSTS TO
                                                                                                                                                                                                                                                              10. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 2'
                                                    8.   CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO                       BE TURNED AWAY BY 5° FROM THE NORMAL TO APPROACHING                                                                                                                                                                     ALLOW FOR THE WORKS TO BE INSPECTED TO THE SATISFACTION OF
                                                                                                                                                                                                                                                                  SOIL ENGINEERING SUPERVISION IN ACCORDANCE WITH APPENDIX B OF
                                                         AUTHORITY/COUNCIL'S   INFRASTRUCTURE.  SUCH     REPAIR   OR                       HEADLIGHT.                                                                                                             AS 3798. THE NOMINATED GEOTECHNICAL TESTING AUTHORITY SHALL                                      RECOR. ANY INSPECTIONS THAT FAIL ARE TO BE RE-INSPECTED WITH ALL
                                                         REINSTATEMENT TO BE CARRIED OUT IMMEDIATELY TO THE                           3. SIGN SUPPORTS                                                                                                            PROVIDE    CERTIFICATION  THAT    ALL GENERAL    EARTHWORKS                                      REINSPECTION COSTS TO BE PAID BY THE CONTRACTOR.
                                                         SATISFACTION   OF    INFRASTRUCTURE    OWNER/MANAGER       /                   a. SLEEVED SIGNS SUPPORTS ARE TO BE PROVIDED IN ALL AREAS                                                                 OPERATIONS HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE
                                                         AUTHORITY/COUNCIL.                                                                                                                                                                                       DRAWINGS AND SPECIFICATIONS AND THE CONTROLLED FILL IS                                            a. PRESTART
                                                                                                                                           WHERE THEY ARE IN A PAVED SURFACE.
                                                                                                                                      4. LINEMARKING                                                                                                              SUITABLE FOR PURPOSE TO THE REQUIRED BEARING CAPACITY UNDER
                                                    9.   CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL                       a. REDUNDANT LINEMARKING IS TO BE GROUND OFF.                                                                             THE PLATFORM/STRUCTURES AS SPECIFIED BY THE GEOTECHNICAL                                          b. EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF
                                                         WORKPLACE HEALTH AND SAFETY REQUIREMENTS.                                                                                                                                                                REPORT.                                                                                              SEDIMENT AND EROSION CONTROL MEASURES UNSUITABLE GROUND
                                                                                                                                        b. THERMOPLASTIC LINEMARKING TO BE USED FOR ALL CONCRETE.
                                                    10. WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN                                                                                                                                               11. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED
                                                                                                                                                                                                                                                                                                                                                                    c. SIDE AND CUT OFF DRAINS
                                                        CLOSE PROXIMITY TO NEIGHBOURING LOT BOUNDARIES OR                             JOINTING NOTES                                                                                                              TO 98% STANDARD MAXIMUM DRY DENSITY OR A DRY DENSITY INDEX
                                                        INFRASTRUCTURE, CONTRACTOR TO ALLOW IN SCOPE OF WORKS TO                                                                                                                                                  OF AT LEAST 75% IN ACCORDANCE WITH THE GEOTECHNICAL REPORT
                                                        PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY OF                     1.   ALL JOINTING AND CONCRETE TO BE IN ACCORDANCE WITH THE                                                                 IN LAYERS OF 250MM LOOSE THICKNESS (PRIOR TO COMPACTION).                                         d. STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL
                                                        EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE                       REQUIREMENTS OF AS3727.1:2016.
                                                        USE OF LOW VIBRATION EQUIPMENT, TRENCH SHORING ETC AS                         2.   SAW CUT JOINTS MUST BE:
                                                                                                                                                                                                                                                              12. COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO                                          e. STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT
                                                        REQUIRED.                                                                      a. BETWEEN 1 AND 1 OF CONCRETE PAVEMENT DEPTHS.                                                                            TESTS PER VERTICAL LIFT WHERE STRUCTURAL FILL HEIGHTS EXCEED
                                                                                                                                                   4       3                                                                                                      300MM IN ACCORDANCE WITH AS3798. CONTRACTOR TO UNDERTAKE
                                                                                                                                                                                                                                                                                                                                                                    f. STORMWATER STRUCTURE BASE SLABS
                                                    11. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON                       b. CLEARED OF ANY DEBRIS FROM THE CUTTING METHOD.                                                                          ALL EARTHWORKS TESTING IN ACCORDANCE WITH GEOTECHNICAL
                                                        THESE DRAWINGS, THE CONTRACTOR IS TO NOTIFY RECOR AND                                                                                                                                                     ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.
                                                                                                                                        c. PERFORMED WITHIN 6 TO 12 HOURS OF FINISHING CONCRETE POURS.                                                                                                                                                              g. SEWER RETICULATION
                                                        RECEIVE WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
                                                                                                                                      3. DOWELL BARS MUST BE INSTALLED EXACTLY 90° TO THE FACE OF JOINT
                                                                                                                                                                                                                                                              13. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN
                                                    12. CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL                              TO ALLOW EXPANSION AND CONTRACTION MOVEMENTS.
                                                                                                                                                                                                                                                                  ACCORDANCE WITH LANDSCAPE DRAWINGS.                                                               h. WATER RETICULATION
                                                        CONSTRUCTED WORKS IN ACCORDANCE WITH LOCAL GOVERNMENT                         4. JOINTING LAYOUT TO BE CONFIRMED BY SUPERINTENDANT PRIOR TO
                                                        REQUIREMENTS.  UNLESS   OTHERWISE    ADVISED   BY RECOR                            CONSTRUCTION COMMENCING. LAYOUT SHOULD AVOID ACUTE ANGLES
                                                                                                                                           IN THE CONCRETE SLAB AND AVOID MISMATCHED JOINTS.                                                                  14. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS.                                               i. PAVEMENT SUBGRADE
                                                        CONTRACTOR TO NOTE COUNCILS ADAC REQUIREMENTS.
                                                                                                                                      5. JOINT SEALANTS WHERE USED MUST ADHERE TO SIDE OF JOINT FACES
                                                                                                                                           ONLY AND SHALL NOT EXTEND ABOVE SIDES OF JOINTS ONTO THE SLAB                                                      15. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED                                           j. PAVEMENT REINFORCING
                                                    13. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH
                                                                                                                                           SURFACE.                                                                                                               MANAGEMENT PLANS.
                                                        RELEVANT APPROVALS.
                                                                                                                                      6. DOWEL BARS ARE TO BE
                                                                                                                                        a. FOR 100MM THICK SLAB, 12MM Ø OF LENGTH 300MM AND SPACED AT                                                         16. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES                                            k. PAVEMENT PRIOR TO SEALING (PRESEAL)
                                                    14. CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL,
                                                                                                                                           400MM CENTRES                                                                                                          ARE INSTALLED INCLUDING BUT NOT LIMITED TO SHAKE DOWNS, SILT
                                                        LANDSCAPE AND OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL
                                                                                                                                       b. FOR 125MM THICK SLAB, 16MM Ø OF LENGTH 350MM AND SPACED AT                                                              FENCE ETC IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL                                         l. RETAINING WALL FOOTING REINFORCING
                                                        CONSTRUCTION.
                                                                                                                                                                                                                                                                  PLAN
                                                                                                                                           300MM CENTRES
                                                    15. CONTRACTOR TO ORGANISE ALL DEMOLITION             PERMITS     PRIOR             c. FOR 150MM THICK SLAB, 20MM Ø OF LENGTH 400MM AND SPACED AT                                                                                                                                                               m. RETAINING WALL BLOCKWORK PRIOR TO CORE FILL
                                                                                                                                                                                                                                                              17. ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL
                                                        DEMOLITION WORKS COMMENCING ON SITE.                                               300MM CENTRES                                                                                                          BATTERS OR RETAINING WALLS (TEMPORARY OR PERMANENT) AS PER
                                                                                                                                                                                                                                                                  RELEVANT AUSTRALIAN STANDARDS AND LEGISLATION.                                                    n. STEEL REINFORCEMENT OF CONCRETE STRUCTURES
                                                    16. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES,
                                                        ROADS AND SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM                      EARTHWORKS NOTES                                                                                                        18. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON                                            o. PRACTICAL COMPLETION
                                                        SITE U.N.O.
                                                                                                                                      1.   FOR DETAILED GEOTECHNICAL INFORMATION, REFER GEOTECHNICAL                                                              UNPAVED ROADS, ACCESS TRACKS AND STOCKPILES AT A SUFFICIENT
                                                                                                                                           INVESTIGATION REPORT BY GEOTECHNICAL ENGINEER. IT IS                                                                   LEVEL TO SUPPRESS DUST GENERATION. ADDITIONALLY CONTRACTORS                                       p. ON MAINTENANCE
                                                    17. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING                                                                                                                                                 ARE TO COVER OR ENCLOSE STOCKPILES WHERE REASONABLY
                                                                                                                                           RECOMMENDED    THAT  THE    GEOTECHNICAL  CONSULTANT   BE
                                                        PROPERTIES AND COUNCIL ROADS AND VERGES PRIOR TO                                                                                                                                                          PRACTICAL TO RESTRICT DUST MOVEMENT.
                                                                                                                                           CONTACTED TO CONFIRM THE SOIL CONDITIONS PRIOR TO
                                                        COMMENCEMENT OF ANY WORKS ON SITE.                                                                                                                                                                                                                                                                          q. OFF MAINTENANCE
                                                                                                                                           EARTHWORKS COMMENCING.
                                                                                                                                                                                                                                                              19. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON
                                                    18. CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS                                                                                                                                                    THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE                                       r. ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER
                                                                                                                                      2.   GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF
                                                        IDENTIFIED IN THE APPROVED VEGETATION MANAGEMENT PLAN.                                                                                                                                                    WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.                                                        DEVELOPMENT APPROVAL)
                                                                                                                                           100MM OVER THE EXTENT OF THE WORKS UNLESS DIRECTED
                                                        CONTRACTOR TO ENSURE ALL TREE ROOTS AND STUMPS ARE
                                                                                                                                           OTHERWISE AND STOCKPILED WHERE REQUIRED FOR FILL OF
                                                        COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.
                                                                                                                                           LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT BE USED IN                                                            20. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE                                       s. ANY OTHER INSPECTION AS REQUIRED BY UNITY WATER AND WHERE
                                                        CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION
                                                                                                                                                                                                                                                                                                                                                                       RELEVANT TO THEIR CERTIFICATION SCHEME




                                                                                                                          ENERGY SERVICE PROVIDERS                                                                  TELECOMMUNICATIONS
                                                                                                                                                                                                                     SERVICE PROVIDERS                                                                                                            elstra                                         Manual of Uniform Traffic Control Devices
                                 BEFORE YOU DIG              SERVICE LOCATIONS                                              AGL                                                                                                                                                                                                                        AUSTRALIA
                                                                                                                                                  ERGON.                                                                                                                                                                                                                                                                                            60
                                                                                                                                                  ENERGY
                                                                                                                                                                  energex                                      ' yes'                        Telstra
                                                                                                                                                                                                                                                                                                                               WARNING: OPTIC FIBRE
                                                           IT IS THE RESPONSIBILITY OF THE PRINCIPAL                                                                                                                                                                                visionstream                                                                                                                                                    km/h


                                                          CONTRACTOR TO CONTACT ALL RELEVANT                                       origin                                                                            OPTUS
                                                          SERVICE AUTHORITIES TO VERIFY THE                            NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM                                NOTE: SERVICE LOCATIONS ARE APPROXIMATE ONLY FROM                                                                       EXTREME CARE TO BE TAKEN WHILE EXCAVATING IN THE
                                                                                                                                                                                                                                                                                                                                                                                                   NOTE: ALL SIGNS & LINE MARKING TO BE IN
                                                          LOCATION OF ALL EXISTING SERVICES PRIOR                            PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED                                   PROVIDERS PLANS. LOCATIONS ARE TO BE CONFIRMED                                                                    VICINITY OF OPTIC FIBRE CABLES. LOCATIONS ARE TO                         ACCORDANCE WITH THE MANUAL OF
                                                                                                                             PRIOR TO START OF CONSTRUCTION. PHONE DBYD                                       PRIOR TO START OF CONSTRUCTION. PHONE DBYD
                                                          TO THE START OF CONSTRUCTION                                       SERVICE LOCATIONS ON 1100 FOR DETAILS.                                           SERVICE LOCATIONS ON 1100 FOR DETAILS.
                                                                                                                                                                                                                                                                                                                                BE CONFIRMED PRIOR TO START OF CONSTRUCTION.                             UNIFORM TRAFFIC CONTROL DEVICES.



                                                                               North Point   Approved                                                                                                                                                                                                                 Project Address                                              Title
                                                                                             BEN PARRY
                                                                                             RPEQ 28084                                                                                                                                                                                                               53-55 DONNELLA ST                                            GENERAL NOTES
                                                                                                                                                                                                                                                                                                                      TEWANTIN QLD 4565
                                                                                             For and on behalf of RECOR Pty Ltd.                                                                                                                                                                                      LOT 4 T16337 & LOT 5 RP73672
                                                                                             Scale                                                                                                     ENGINEERING + PROJECT MANAGEMENT                                                                               Client Details                                               PROJECT NAME:                                   Project Number          Sheet Size
                                                                                                                                                                                                       SUNSHINE COAST | BRISBANE | SYDNEY
 B    23/06/23   OPW ISSUE                                     HL     BP                                                                                                                              www.recorconsulting.com | ABN 89 647 469 707                                                                    BLACKWOOD ASSETS                                             PROPOSED                                        20210038                  A1
 A    05/05/23   MCU ISSUE                                    JAC     BRP
                                                                                                                        AS SHOWN                                   COPYRIGHT © This drawing is subject to copyright in accordance with the agreement between RECOR Pty Ltd and RECOR's client. This                                                                                RESIDENTIAL DUPLEX                              Drawing Number           Revision

                                                                                                                                                                                                                                                                                                                                                                                                                                   002                        B
                                                                                                                                                                 drawing shall only be used for this specific project. This drawing shall not be used for construction until marked as 'Issued For Construction' in

Rev   Date                   Revision Description           Drawn Check                                           DO NOT SCALE, IF IN DOUBT ASK                                                                                the revision description.
Log in to download the original file

Appendix C - Engineering.pdf · 3.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.