201026 16 Grant Street, Noosa TP Report
Attached to the e-mail Operational Works Application - 16 Grant Street Noosa Heads.
treatment during the construction capture in accordance with Appendix
phase. 2, Table A of the Queensland State
Planning Policy and International
Erosion Control Association Best
Practice Erosion and Sediment
Control (BPESC) 2008;
AND
S1.2 S1.2 Complies
Construction works are designed and Sediment barriers will be provided
managed to restrict the extent of throughout and downslope of
clearing and soil exposure to that disturbed areas to prevent
necessary for access, and safe sediment washing into gutters,
construction; drains and watercourses either on
AND or off the site.
S1.3 S1.3 Complies
Clean stormwater is diverted or Clean stormwater will be diverted
managed around or through the site or managed appropriately in
without increasing the concentration accordance with the relevant
of total suspended solids or other provisions.
contaminants in the flow and without
causing erosion (onsite or offsite);
AND
S1.4 S1.4 Complies
Cleared areas are effectively Cleared areas are effectively
stabilised prior to rainfall if works are stabilised prior to rainfall if works
delayed or works are not intended to are delayed or works are not
occur immediately; intended to occur immediately
AND
S1.6 S1.6 Complies
For buildings – The proposal at hand involves
a) upstream runoff must be diverted appropriate measures to ensure
around the construction site; and no sediment is discharged in
b) sediment barriers are provided compliance with the relevant
downslope of disturbed areas to provisions.
prevent sediment washing into
gutters, drains and watercourses
either on or off the site; and
c) exposed soil and construction
access must be managed in
accordance with International
Erosion Control Association Best
Practice Erosion and Sediment
Control (BPESC) 2008; and
d) temporary or permanent
downpipes are connected to the
stormwater system before laying
the roof; or
e) e) localised erosion is avoided by
directing flow from downpipes
over non-erosive areas.
Works in a watercourse
O2 S2.1 S2.1 Complies
Construction activities within Work within waterways must be The proposal will be undertaken
watercourses are planned to undertaken in accordance with Best in accordance with Best Practice
prevent erosion, construction Practice Erosion and Sediment Erosion and Sediment Control.
failure and associated Control, Appendix I – Instream
sedimentation. works, Sections 14 and 16
International Erosion Control
12
Operational Work (Development Permit)
16 Grant Street, Noosa
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (201026 16 Grant Street, Noosa TP Report.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.