FINANCIAL PERFORMANCE REPORT - NOVEMBER 2025 · Attachment 4 - Financial Analytics 30 November 2025
Capital Revenue
On Track
Watch Benchmark % Complete 41.67%
For the Year Ending 30 June 2026 $'000 $'000 % $'000 %
As 30 November 2025 Actual Budget Actuals to Annual Actuals to
YTD YTD Budget Budget Annual Budget
YTD
Capital cash contributions and infrastructure charges 1,873 1,293 144.81% 1,293 144.81%
Contributed assets 0 0 0.00% 1,500 0.00%
Capital grants and subsidies 5,618 3,077 182.59% 48,334 11.62%
Other capital revenue 0 0 0.00% 0 0.00%
Total Capital Revenue 7,491 4,370 171.41% 51,128 14.65%
Capital Expenditure
On Track
Watch Benchmark % Complete 41.67%
For the Year Ending 30 June 2026 $'000 $'000 % $'000 %
As 30 November 2025 Actual Budget Actuals to Annual Actuals to
YTD YTD Budget Budget Annual Budget
YTD
Plant & Equipment 118 726 16.21% 2,842 4.14%
Council Owned Freehold Land 1,551 2,945 52.66% 6,093 25.46%
Buildings 685 1,551 44.17% 5,917 11.58%
Other Structures 1,941 7,396 26.25% 22,476 8.64%
Roads, Bridges & Footpaths 4,718 17,702 26.65% 46,598 10.13%
Stormwater 148 977 15.16% 4,625 3.20%
Fleet 1,217 2,977 40.87% 4,524 26.90%
Intangibles 0 0 0.00% 0 0.00%
Contributed Assets 0 0 0.00% 1,500 0.00%
Debt Redemption 614 614 100.00% 1,227 50.04%
Other Capital Expenses 4,649 0 0.00% 0 0.00%
Total Capital Expenditure 15,641 34,887 44.83% 95,801 16.33%