               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                  Senior Development Engineer, Daniel Epps
                                       Development Assessment



                    APPLICATION DETAILS

                    Application No.                OPW26/0100

                    Applicant                      John Holland Group Pty Ltd

                    Proposal                       Operational Works - Earthworks

                    Properly Made Date             20 July 2026

                    Information Request Date       Not Applicable

                    Information Response Date      Not Applicable

                    Decision Due Date              14 September 2026

                    Report Reviewed &              Will Lowe – 24 July 2026
                    Finalised By


                    PROPERTY DETAILS

                    Property Address               271 Lake Macdonald Dr Lake Macdonald Qld 4563

                    RP Description                 Lot 2 SP 108094

                    Land Area                      141400.00 m²

                    Existing Use of Land           Cultivation (Type 2) & Industrial Business (Type 2) – Rural


                    STATUTORY DETAILS

                    SEQRP Designation              Regional Landscape and Rural Production Area

                    Zone                           Rural

                    Precinct                       Not applicable

                    Local Plan Area                Not applicable

                    Overlays                       Biodiversity, Waterways and Wetlands Overlay, Bushfire Hazard
                                                   Overlay, Flood Hazard Overlay, Landslide Hazard Overlay,

                    Assessment Type                Code

               1.      PROPOSAL
               The application seeks approval for Operational Works - Earthworks.
               The locality and proposal plan are included below.



Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026
Log in to download the original file

Delegated Report - Code - Planning OPW26 0100 (As Published).pdf · 2.6 MB (large file)

The download may take up to a minute.

Full text of the other 10 pages

Page 2

                                       Figure 1 – Locality




                                       Figure 2 – Site Plan

                                                              Page 2 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 3

               2.     SITE DETAILS
               2.1. Site History
               There is no higher order approval requiring these works.
               The works are necessary to satisfy the (State) Coordinator-General’s Change Report –
               Construction and associated Traffic Management Plan for the upgrade works to Lake MacDonald.
               2.2. Site Description
               The site is currently used by Wimmers. The site is approximately 14 hectares and incudes a
               mapped waterway either side of the existing built area. The built area generally grades towards
               the western waterway. The site takes access from Lake MacDonald drive from three different
               vehicle crossovers which are separated by their use (i.e., service vehicles, passenger vehicles,
               etc).
               2.3. Surrounding Land Uses
               The surrounding land is primarily used as rural / rural residential living. The adjoining rear lot
               includes an agricultural use (cultivation).
               3.     ASSESSMENT
               3.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (20 March 2026).
               3.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •      Works Codes – Earthworks
               •      Overlay Code – Biodiversity, Waterways and Wetlands Overlay
               The application has been found to generally comply with all applicable statutory instruments. The
               pertinent issues arising out of the assessment are discussed below:
               The applicant is seeking approval to undertake earthworks on the subject site to facilitate a
               temporary carpark and site laydown for the ongoing state project at Lake MacDonald. It is proposed
               that the temporary carpark and laydown be utilised by the applicant for 36 months (until May 2029).
               The works includes minor earthworks to achieve suitable finished levels (including topsoil
               stripping), placement and compaction of road base, delineation of temporary carparks, long-term
               erosion and sediment controls, drainage and rehabilitation of the site.
               SEQWater have undertaken a Revised Universal Soil Loss Equation (RUSLE) to determine the
               erosion risk for the site and the level of controls required in accordance with IECA’s Best Practice
               Erosion and Sediment Control. The calculation includes a conservative soil erodibility and rainfall
               erosivity factor to arrive at a predicted soil loss per hectare per year of 132, placing the site in a
               very low risk category. For the catchment area (the works area), the standard recommends the
               site be provided with Type 2 controls. This is generally satisfied in Section 5 of SEQ Water’s
               Planning Assessment through a series of sediment fences, rock check dams, a rock mattress and
               a rock outlet structure.
               The works do not propose to remove any vegetation or create any new vehicle access to Lake
               MacDonald drive.
               The proposed earthworks will not require 36 months to complete. However, Council recognises
               that:

                                                                                                       Page 3 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 4

               •       regular and ongoing maintenance works will be required after the initial works described
                       above to ensure the temporary carpark and laydown continues to function safely and
                       efficiently (i.e., fill of potholes, re-grading of carparking, etc) without causing an ongoing
                       erosion and sediment nuisance; and
               •       the works area may not be able to reasonably achieve ‘long-term’ stabilisation expected
                       upon the complete of the immediate earthworks because the area will be frequently
                       trafficked.
               It is recommended that any future permit have a sunset clause for the works to achieve ‘long-
               term’ stabilisation by May 2029 (i.e., cease works by May 2029) to ensure the works area does
               not present as an on-going erosion and sediment control nuisance. It is also recommended that
               regular inspections of the site’s erosion and sediment controls are imposed to ensure that the
               maintenance works can be undertaken without causing nuisance.

               Environment

               A portion of the proposed car park and laydown area is located within a mapped Riparian
               Protection Area. The image below demonstrates that the existing shared driveway access and
               surrounding gravel areas associated with the Wimmers building are unsealed and currently do
               not incorporate erosion and sediment control measures.

               The proposed works will formalise these areas and incorporate gravel resurfacing, erosion and
               sediment controls, turf-lined swales, rock check structures and a rock mattress. Collectively,
               these measures are expected to significantly improve site stormwater management and reduce
               the risk of sediment discharge to downstream waterways. In addition to the proposed erosion and
               sediment controls a condition requiring the permanent stabilisation of the area around the rock
               mattress and outlet with 100 Lomandra longifolia has been required.




               Engineering recommends that the proposal satisfies the relevant provisions of The Noosa Plan
               2020 and recommends the following conditions.




                                                                                                         Page 4 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 5

               4.      CONSULTATION
               4.1. Referral Agencies
               Not Applicable
               4.2. Internal Council Referrals
               The application was forwarded to the following internal Council officers for review and/or comment:
               •       Coordinator of Engineering and Environment, Development Assessment
               5.      CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW26/0100 for Operational Works - Earthworks situated at 271
               Lake Macdonald Dr Lake Macdonald Qld 4563 and described as Lot 2 SP 108094, it is
               recommended the application be approved in accordance with the following details for the Decision
               Notice:
               1.      APPLICATION DETAILS

                   Application No:                  OPW26/0100

                   Street address:                  271 Lake Macdonald Dr Lake Macdonald Qld 4563

                   Real property description:       Lot 2 SP 108094

                   Planning Scheme:                 Noosa Plan 2020 (20 March 2026)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works - Earthworks
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.     Plan/Document Name                         Date

                          D26/127335            -        Figure 3: Indicative carpark layout        20 July 2026
                                                         Prepared by SEQwater
                                                         Amended by Council




                                                                                                      Page 5 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 6

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 24 July 2028, unless an application to extend the currency period is
                      approved by Council.
               SITE SPECIFIC CONDITIONS
               3.     All site surfaces must be effectively stabilised using methods which have achieved effective
                      short-term stabilisation and will continue achieve effective stabilisation in the medium- to
                      long-term. Stabilisation must be established, inspected and accepted by a Council delegate
                      no later than 31 May 2029 unless otherwise agreed to in writing by Council.
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               4.     All necessary approvals from external service providers and external parties on which the
                      development works are proposed have been obtained and a copy supplied to Council.
               5.     A condition report including photographs of the frontage of the site and the mapped waterway
                      to the west of the works site must be completed and submitted to Council prior to the prestart
                      meeting.
               6.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Erosion and sediment control works; and
                      c.      Other relevant parties.
               7.     Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               8.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               DURING CONSTRUCTION
                      Engineering
               9.     The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               10.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               11.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      c.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.


                                                                                                      Page 6 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 7

                      Landscape
               12.    Outlet structures discharging stormwater into the riparian protection area from the rock
                      mattress must be permanently stabilised through the planting of a minimum 100 Lomandra
                      longifolia.
                      Pavement Design and Construction
               13.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               14.    Safe pedestrian and vehicle access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               15.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               16.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Earthworks and Retaining Walls
               17.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development.
               18.    All earthworks and associated batters/retaining structures, both above and below ground
                      level, both temporary and permanent, must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
               19.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;
                      c.      1 in 3 for planted areas; and
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               20.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               21.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g. by blocking or interfering with natural overland flows).
               22.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Erosion and Sediment Control
               23.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination.




                                                                                                      Page 7 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 8

               24.    At the time of the prestart meeting, all erosion and sediment controls must be in place in
                      accordance with an erosion and sediment control plan prepared by a suitably qualified person
                      (RPEQ or CPESC). If such measures are not in place or are not satisfactory, “on the spot”
                      fines may be issued. Such fines can be issued if sediments from the site are found to enter
                      or have the potential to enter Council’s stormwater system, natural waterways, any
                      downstream stormwater filtration system or adversely impacting on other properties.
                      The sediment and erosion control design and measures have NOT been approved, it is the
                      site's Supervising Engineer who is responsible for ensuring that the sediment and erosion
                      control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;
                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               25.    The erosion and sediment control measures must be designed, installed and maintained in
                      accordance with the supervising engineer’s instructions and the current best practice
                      standards. A copy of the latest erosion and sediment control plan, prepared and endorsed
                      by a suitably qualified person (RPEQ/CPESC), must be made available to Council within 5
                      business of request.
                      (*) Refer to Advisory Note
               26.    All erosion and sediment controls must be inspected to ensure the controls are not being
                      bypassed. Inspections must occur and be electronically recorded:
                      a.      at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      within 24 hours of expected rain; or
                      c.      within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
               27.    Earthworks and the implementation of erosion and sediment controls are undertaken in ways
                      which ensure flooding characteristics (including stormwater quantity characteristics) external
                      to the development site are not worsened during construction for all events up to and
                      including the 1% AEP (1 in 100 year ARI) event.
               28.    The developer must ensure non-essential exposure of soil is prevented by restricting the
                      extent of disturbance and minimising the duration of soil exposure to adverse weather
                      conditions and effectively turf, cover or stabilise any disturbed area without delay and prior
                      to rainfall occurring.
               29.    The developer must ensure sediment does not leave the site or enter onto adjoining
                      properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
                      machinery. It is essential to implement appropriate approved erosion and sediment control
                      measures throughout the site during all phases of construction including vehicle shakedown
                      pad/grid (or similar) at the access to the construction site. Where sediments or other
                      contaminants are deposited on a road, they must be removed so as not to enter Council’s
                      drainage system or waterways.
                      Damage to Services and Assets
               30.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:


                                                                                                          Page 8 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 9

                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION AND ESTABLISHMENT OF THE CARPARK AND LAYDOWN
                      Certification
               31.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               32.    A final inspection of the completed works (i.e., establishment of the carparking and laydown
                      areas) by Council’s Inspector is required prior to the commencement of use. Please contact
                      Council on 5329 6500 to arrange for the inspection.
               5.     REFERENCE DOCUMENTS

               Not applicable.
               6.     REFERRAL AGENCIES

               Not applicable.
               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                      the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               2.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               3.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
                      Prestart, On and Off Maintenance Inspections Request
               4.     Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               5.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.




                      Environmental Advisory Notes

                                                                                                      Page 9 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 10

               6.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               7.     Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               8.     Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               9.     As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Road Reserve Permit
               10.    This development permit provides the applicant with written authority to undertake the
                      prescribed works. Any additional activities that are undertaken inside Council’s road reserve
                      for the purpose of acting on this development permit may require a Road Reserve Permit.
                      These additional activities may include, but are not limited to, hoarding, pedestrian
                      diversions, laneway closures, etc. To apply for a Road Reserve Permit, or for more
                      information, Contact Council’s Road Reserve Officer at [email protected] Act 2014 – Fire Ant Control
               11.    Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
                      individuals and businesses are responsible for ensuring that they follow the movement
                      controls for specific organic materials to help prevent the spread of fire ants within South
                      East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
                      ant biosecurity zone may need a biosecurity instrument permit. More information is available
                      on https://www.fireants.org.au/treat/business-andindustry/movement-controls.
               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.

                                                                                                       Page 10 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

Page 11

               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                    Page 11 of 11

Document Set ID: 25007092
Version: 4, Version Date: 24/07/2026

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.