TPC 1354 - Change to Existing Approval Decision(SPA) [As Published] · 51981.3457.03

of 7

Text shows just the words. Original shows the document exactly as it was published.

                                            Officer:          Glen Conforti
                                            Direct Telephone: (07) 5449 5379
                                            Response Address: Locked Bag 72
                                                              Sunshine Coast Mail Centre QLD 4560
                                            Email:            [email protected]
                                            Our Reference:    TPC 1354
                                            Your Reference:
15 June 2010


Mr & Mrs L Cranley & Mr I Mundy
PO Box 73
NOOSA HEADS QLD 4567



Dear Sir / Madam
Re:   Application for a Change to Development Approval situated at 17 Ferguson Street,
      Sunshine Beach described as Lots 1 & 2 BUP 5732

I refer to your request to make a change to the above development approval. On 10 June 2010
Council decided to: -
A.    Approve the change with the following additional conditions:
Planning Assessment
1.    Development undertaken in accordance with this approval must generally comply with the
      approved plans of development. The approved plans are listed in the following table and may
      be amended by these conditions.

        Plan No.        Plan / Document Name                                    Date
        WD01            Site Plan – Soul Space                                  7 March 2010
        WD02            Level 1 Plan– Soul Space                                7 March 2010
        WD03            Level 2 Plan– Soul Space                                7 March 2010
        WD04            Roof Plan– Soul Space                                   7 March 2010
        WD05            Elevations – Soul Space                                 7 March 2010
        WD06            Elevations– Soul Space                                  7 March 2010
        WD07            Sections– Soul Space                                    7 March 2010
        WD08            Sections– Soul Space                                    7 March 2010
        WD09            Sections– Soul Space                                    7 March 2010

2.    The development must be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting nuisance or other emissions.

3.    Existing trees on the site and within road reserves shall be retained, except where required to
      be removed due to building operations or the conduct of the approved use. In this regard the
      street tree in the road reserve shall be retained.
4.    A landscape plan prepared by a suitably qualified person in accordance with Council’s Policy
      on Landscaping Plants and Guidelines PSP 3 shall be submitted to Planning Assessment –
      Tewantin Office prior to the issue of a Development Permit for Building Works. The landscape


                                                                                            Page 1 of 7
Full text of the other 6 pages

Page 2

      plans shall be to the satisfaction of the Planning Assessment Coordinator. The landscaping
      plan shall include:-

      4.1.   Dense plantings to the new garden areas located to the front entries of the duplex
             dwelling.
      4.2.   Dense plantings to the garden area between the visitor parking space and the front
             boundary.
      4.3.   Dense plantings to the garden area near the bin enclosure
      4.4.   Around the pool, no more than 30% of the landscaped area shall be a mixture of plants
             of local origin and exotic plant species, provided none of the plant species are
             undesirable plants identified in Councils Landscaping Plants and Guidelines PSP3.
      4.5.   A minimum of one 45 litre native street tree shall be established within the road reserve
             and include the following species:
       SMALL STREET TREES IN COASTAL AREAS UNDER POWER LINES
        Acronychia imperforata                        Fraser Island apple
        Alectryon coriaceus                           Beach birds eye
        Acmena hemilampra                             Broad leafed lilly pilly
        Banksia aemula                                Wallum banksia
        Banksia integrifolia
        Casuarina glauca                              Swamp sheaok
        Elaeocarpus reticulatus                       Blue berry ash
        Eucalyptus bancrofftii                        Tumbledown gum
        Grevillea banksii                             Red flowering silky oak
        Petalostigma pubescens                        Quinine berry

5.    Cleared vegetation is to be suitably processed by one of the following methods and removed
      from the site:
      5.1.   Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
             loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
             minimum of 10 metres between edges of heaps.
      5.2.   Disposal for firewood.
      5.3.   Disposal for landscaping purposes.
6.    The applicant is advised that burning off is an unacceptable method of disposal.
7.    Security in the form of a cash bond or trading bank guarantee to the sum of $3000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for building works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
8.    The building height shall not exceed 8.0 metres above the natural ground level, finished
      ground level and 2 storeys.
9.    Any deck or balcony areas are not to be fully enclosed with shutters, glass panelling or the
      like, thus remaining as open structures.
10.   All fencing shall be setback at least 1m from the front property boundary, with at least half the
      fencing setback 2m. The area of land between the front fence and the front boundary shall be
      densely landscaped to screen any fencing from the street.
                                                                                         Page 2 of 7

Page 3

Further Permits Required
11.   Prior to the commencement of development, the following Development Permits must be
      obtained:-
           Development Permit for Building Works.

Operational Works Assessment Branch
12.   A vehicular access driveway to serve the development must be constructed from the Ferguson
      Street frontage of the site with a maximum width of 5.5m.
13.   The driveway must be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
      movements along the footpath without any step or level difference. Should any driveways be
      constructed to grades that do not comply with AS/NZS 2890.1-2004, Council will require that
      the driveway be removed and reconstructed to levels that do comply.
      Please note, a step between the driveway and the footpath must be avoided, as it is preferred
      to have the footpath continue at a constant grade to minimise the potential for pedestrians to
      trip or fall.
14.   To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath,
      the driveway and any associated fencing or vegetation near the driveway must comply with
      the minimum sight line requirements as defined in AS 2890.1, section 3.2.4. The applicant
      must demonstrate compliance by illustrating these sight lines on the plans submitted for
      Building Works approval.
15.   All vehicles must enter and leave the site in a forward direction.
16.   A Road/Footpath Permit (copy enclosed) must be completed and submitted for the
      construction of the access driveway in accordance with Council’s Local Law No.8. If approval
      is given the driveway must be constructed in accordance with Council’s standard drawings,
      which will be provided at time of approval.
17.   Carparking must be provided within the site as shown on drawing number WD02 plot dated 11
      March 2010 by Soul Space, except as modified herein.
18.   The carparking area must be designed to comply with the provisions of AS/NZS 2890.1-2004
      for user class 1A with allowance for vehicles to enter and leave the site in a forward gear and
      with a minimum head clearance (headroom) at any point of 2.2m.
19.   The proposed turning area must be clearly sign posted to indicate that the area is a “Turning
      Area Only” and that “No Parking is Permitted”.
20.   All car parking must be kept, maintained and line-marked in a condition fit for use.
21.   Roof runoff from any dwelling must be directed to a rainwater storage system or tank that is
      installed to ensure water from the rainwater storage system or tank is used for external uses
      (such as watering gardens, irrigation, ornamental ponds, water features, topping-up swimming
      pools, outdoor cleaning, etc) and for internal (ground floor) use in washing machine cold taps
      and toilet cisterns. All rainwater tanks are to be designed and installed in accordance with the
      Queensland Development Code (QDC) current at the time of building approval, and must be
      part of the plumbing application for approval. The location and capacity of the tanks must be
      clearly shown on the plans submitted for Building Works approval and any overflow must be
      directed to the road frontage.
22.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      must be collected and discharged so there is no net increase in stormwater runoff from the
      site. Stormwater drainage permitted to drain from the site must be discharged to Council’s
      existing kerb & channel street drainage system in Ferguson Street.
23.   All site stormwater drainage must be by means of a gravity system.


                                                                                        Page 3 of 7

Page 4

24.   Earthworks required on site must be carried out in accordance with Council’s Planning
      Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional
      ponding of water on any adjoining lands or the blockage of, or interference with, any natural
      overland flows.
25.   Earthworks carried out on site must not affect the structural integrity of any of the existing
      fences and/or structures and/or services and/or lands that border the development site.
      Fences that are affected must be replaced prior to the Building Certifier issuing the Certificate
      of Classification.
26.   Any person acting on this permit must prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard, a plan detailing the methods of controlling erosion and sediment in accordance
      with the Healthy Waterways document and fact sheet series titled “Controlling Stormwater
      Pollution on your Building Site dated 2006” are required to be submitted with the application
      for a Building Works Permit.
27.   Any damage caused to any public utility during the course of construction must be repaired to
      Council’s standards and at no cost to Council.
28.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site must be at no cost to Council.
29.   The transportation of all materials to and from the site must be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site must be covered to prevent materials including dust being windblown from the
      vehicle.
30.   The applicant must pay contributions towards trunk infrastructure in accordance with the
      following Planning Scheme Policies and Council Policies:
      (a)   Planning Scheme Policy 12 – Public Open Space Contributions;
      (b)   Planning Scheme Policy 13 – Contributions in Lieu of Off Street Parking;
      (c)   Planning Scheme Policy 16 – Sewerage Headworks Contributions;
      (d)   Planning Scheme Policy 17 – Water Supply Headworks Contributions;
      (e)   Planning Scheme Policy 20 – Pathway Trunk Network Contributions;
      (f)   Council Policy – Rural Roadworks Contributions;
      (g)   Council Policy – Master Drainage Contributions.
      For material change of use of premises approvals the contributions must be paid prior to the
      commencement of use, for reconfiguring a lot approval contributions must be paid prior to
      Council approval of the plan of subdivision.
      The actual amount of the contribution must be calculated and paid in accordance with the
      Planning Scheme Policies and variations due to indexation current at the time of payment.

Sunshine Coast Water
31.   Reticulated water supply and sewerage must be provided to the development.
32.   Construction activities must not impede the access of Sunshine Coast Water or Fire Brigade
      personnel to vital infrastructure (eg. valves, fire hydrants and sewer access chambers).
33.   The fire-fighting demand on Council’s water supply system from the development must not
      exceed 15 litres per second.
34.   Separate 25mm PE water services must be installed to a common lot boundary with
      independent meters installed outside the boundary of the lot in accordance with Sunshine
      Coast water standard drawing SCW 361. Meters must be “Elster” PSM 50100/39 (dual check).
                                                                                        Page 4 of 7

Page 5

35.    Buildings and other structures must maintain a minimum clearance of 1.5 metres from Council
       sewer mains, and 1.0 metre from sewer inspection openings.
36.    Storm water retention systems must maintain a minimum clearance of 1.5 metres from Council
       water supply and sewerage infrastructure.
37.    Landscape planting within 1.5 metres of Council sewerage infrastructure and 1.0 metre of
       Council water infrastructure must be Council approved varieties and low growing when
       mature.
38.    Construction works undertaken in the vicinity of Council water supply or sewerage
       infrastructure must not adversely affect the integrity of the infrastructure. All costs associated
       with repair, replacement or alteration of infrastructure must be met by the applicant.

Additional Advice Conditions
1.     Parts of the proposed works are located within the Common property of BUP 5732.It is
       recommended the owners revise the BUP when the works have been completed.
2.     Connection to Council live water mains and the Council live sewer system must be undertaken
       by Council at the applicants cost.
3.     Water meters must be located on alternative boundaries to power boxes.

B.     Advise applicants of Council’s Decision.

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Sustainable Planning Act 2009 is also attached.

Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

Yours faithfully,




Glen Conforti
PLANNING TECHNICAL OFFICER




                                                                                          Page 5 of 7

Page 6

                                                                                                 2010/712



                                                    Appeal Rights
                                                 SUNSTAINABLE PLANNING ACT         2009    &    SUSTAINABLE
                                                 PLANNING REGULATION 2009



                                                                   (b) any provision of the approval including—
The following is an extract from the Sustainable                      (i)    a condition of, or lack of condition for,
Planning Act 2009 (Chapter 6).                                               the approval; or
MATERIAL CHANGE OF USE, RECONFIGURING A                               (ii)   the length of a period mentioned in
LOT & OPERATIONAL WORKS                                                      section 341 for the approval.
Division 8 - Appeals to court relating to development       (3)    However, a submitter may not appeal if the
applications                                                       submitter—
461    Appeals by applicants                                       (a) withdraws the submission before the
                                                                      application is decided; or
(1)     An applicant for a development application
        may appeal to the court against any of the                 (b) has given the assessment manager a
        following-                                                    notice under section 339(1)(b)(ii).
        (a) the refusal, or the refusal in part, of a       (4)    The appeal must be started within 20 business
            development application;                               days (the submitter’s appeal period) after the
                                                                   decision notice or negotiated decision notice is
        (b) any condition of a development approval,
                                                                   given to the submitter.
            another matter stated in a development
            approval and the identification or inclusion    463   Additional and extended appeal rights for
            of a code under section 242                           submitters   for  particular development
                                                                  applications
        (c) the decision to give a preliminary approval
            when a development permit was applied           (1)    This section applies to a development
            for;                                                   application to which chapter 9, part 7
                                                                   applies.
        (d) the length of a period mentioned in section
            341;;                                           (2)    A submitter of a properly made submission for
                                                                   the application may appeal to the court about a
        (e) a deemed refusal of the development                    referral agency’s response made by a
            application.                                           prescribed concurrence agency for the
(2)     An appeal under subsection (1)(a), (b), (c) or             application.
        (d) must be started within 20 business days         (3)    However, the submitter may only appeal
        (the applicant’s appeal period) after—                     against a referral agency’s response to the
        (a) if a decision notice or negotiated decision            extent it relates to—
            notice is given—the day the decision notice            (a) if the prescribed concurrence agency is the
            or negotiated decision notice is given to the             chief    executive       (environment)—
            applicant; or                                             development for an aquacultural ERA; or
        (b) otherwise—the day a decision notice was                (b) if the prescribed concurrence agency is the
            required to be given to the applicant.                    chief executive (fisheries)—development
(3)     An appeal under subsection (1)(e) may be                      that is—
        started at any time after the last day a decision             (i)    a material change of use of premises
        on the matter should have been made.                                 for aquaculture; or
462    Appeals by submitters - general                                (ii)   operational work that is the removal,
                                                                             damage or destruction of a marine
(1)     A submitter for a development application may                        plant
        appeal to the court only against-
                                                            (4)    Despite section 462(1), the submitter may
        (a) the part of the approval relating to the               appeal against the following matters for the
            assessment manager’s decision about any                application even if the matters relate to code
            part of the application requiring impact               assessment—
            assessment under section 314; or
                                                                   (a) a decision about a matter mentioned in
        (b) the part of the approval relating to the                  section 462(2) if it is a decision of the chief
            assessment manager’s        decision under                executive (fisheries);
            section 327.
                                                                   (b) a referral agency’s response mentioned in
(2)     To the extent an appeal may be made under                     subsection (2).
        subsection (1), the appeal may be against 1 or
        more of the following—
        (a) the giving of a development approval;

                                                                                                 Page 6 of 7

Page 7

                                                                                             2010/712

464   Appeals by advice agency submitters                 (3)    Also, a person who has made a request under
                                                                 section 369 may appeal to the court against a
(1)    Subsection (2) applies if an advice agency, in            deemed refusal of the request.
       its response for an application, told the
       assessment manager to treat the response as        (4)    An appeal under subsection (3) may be started
       a properly made submission.                               at any time after the last day the decision on
                                                                 the matter should have been made.
(2)    The advice agency may, within the limits of its
       jurisdiction, appeal to the court about—           467    Appeals about changing or cancelling
                                                                 conditions   imposed    by   assessment
       (a) any part of the approval relating to the              manager or concurrence agency
           assessment manager’s decision about any
           part of the application requiring impact       (1)    A person to whom a notice under section
           assessment under section 314; or                      378(9)(b) giving a decision to change or cancel
                                                                 a condition of a development approval has
       (b) any part of the approval relating to the              been given may appeal to the court against the
           assessment     manager’s   decision under             decision in the notice.
           section 327
                                                          (2)    The appeal must be started within 20 business
(3)    The appeal must be started within 20 business             days after the day the notice of the decision is
       days after the day the decision notice or                 given to the person.
       negotiated decision notice is given to the
       advice agency as a submitter.                      For Building Works Only
(4)    However, if the advice agency has given the        532   Appeals by applicants
       assessment manager a notice under section          (1)    If—
       339(1)(b)(ii), the advice agency may not
       appeal the decision.                                      (a) a person has been given, or is entitled to
                                                                       be given—
465    Appeals about decisions           relating   to
                                                                       (i)     an information notice under the
       extensions for approvals
                                                                               Building Act about a decision
(1)    For a development approval given for a                                  other than a decision under that
       development application, a person to whom a                             Act made by the Queensland
       notice is given under section 389, other than a                         Building Services Authority; or
       notice for a decision under section 386(2), may                 (ii)    an information notice under the
       appeal to the court against the decision in the                         Plumbing and Drainage Act
       notice.                                                                 2002 about a decision under
                                                                               part 4 or 5 of that Act; or
(2)    The appeal must be started within 20 business
       days after the day the notice of the decision is          (b) a person—
       given to the person.
                                                                       (i)     was an applicant for a building
(3)    Also, a person who has made a request under                             development approval; and r
       section 383 may appeal to the court against a                   (ii)    is dissatisfied with a decision
       deemed refusal of the request                                           under the Building Act by a
(4)    An appeal under subsection (3) may be started                           building certifier or referral
       at any time after the last day the decision on                          agency about inspection of
       the matter should have been made.                                       building work the subject of the
                                                                               approval; the person may appeal
466    Appeals about decisions           relating   to                         against the decision to a building
       permissible changes)                                                    and development committee.
(1)    For a development approval given for a             (2)    An appeal under subsection (1) must be
       development application, the following persons            started within 20 business days after the day
       may appeal to the court against a decision on             the person is given notice of the decision.
       a request to make a permissible change to the
                                                          (3)    If—
       approval—
                                                                 (a) under the Building Act, a person makes
       (a) if the responsible entity for making the                  an application other than a building
           change is the assessment manager for the                  development application to a local
           application—                                              government; and
           (i)    the person who made the request; or            (b) the period required under that Act for the
           (ii)   an entity that gave a notice under                 local government to decide the application
                  section 373 or a pre-request                       (the decision period) has passed; and
                  response notice about the request              (c) the local government has not decided the
       (b) if the responsible entity for making the                  application; the person may appeal to a
           change is a concurrence agency for the                    building and development committee
           application—the person who made the                       against the lack of the decision and for the
           request..                                                 committee to decide the application as if it
                                                                     were the local government.
(2)    The appeal must be started within 20 business
       days after the day the person is given notice of   (4)    An appeal under subsection (3) must be
       the decision on the request under section 376.            started within 20 business days after the end of
                                                                 the decision period.


                                                                                             Page 7 of 7

Used in these records

About this file

File size
56 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

TPC 1354 - Change to Existing Approval Decision(SPA) [As Published].pdf · 56 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.