SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 8 OCTOBER 2019
Safety Risks Mitigation
This is a medium to low risk project due to the Ri-con Contractors Pty Ltd Contractors have
working at heights up to 8 mtrs above ground, extensive experience at this scale and type of
with relatively flat topography and adequate space project and would be appointed as the Principal
for normal construction activities Contractor responsible for all Workplace Health
and Safety of the site. Prior to construction
commencing, work place health and safety and
pedestrian and traffic management plans will be
required to be submitted to Council for review.
Regular audits on contractor compliance with
these approved plans will be undertaken by
Council throughout construction.
Preschool, and community Traffic and pedestrians Specific requirements for contractor to manage
must share Rufous street with construction safety of pedestrians and traffic are included in the
vehicles and machinery operating and accessing contract conditions. Regular audits on contractor
the work site. compliance with these approved plans will be
undertaken by Council throughout construction.
Environmental Harm Risks Mitigation
There is risk that the car park works impact The alignment of the car park was developed to
vegetation by machinery coming into contact reduce the risk of vegetation impacts by aligning
above and below ground. the southern edge clear of the tree line.
A hold point will be established prior to excavation
and a risk based approach for construction
methodology to ensure impacts are minimised.
Scope And Quality Risks Mitigation
Risk of not meeting project objectives To be managed through Council staff reviews
supported by specialist consultants who developed
the original design and specifications.
Public Disruption And Council Reputation Mitigation
Risks
Access during construction, there will be disruption Specific requirements for contractor to manage
to the public as a result of the works. There is a safety of pedestrians and traffic are included in the
risk that the proposed pedestrian and traffic contract conditions. Regular audits on contractor
management plans do not provide an acceptable compliance with these approved plans will be
level of service during the construction period undertaken by Council throughout construction.
There will be regular contact with adjacent tenants
to review for impacts as well as weekly review of
systems in place and seek opportunities to
improve wherever possible.
There is risk that notification is insufficiently in Council is regularly updating the project news on
advance of the works due to the probity nature of the Council web site. Council community
tender processes and the short period from award development team will Liaise with Community
to commencement. organisations throughout the project.
Noise may be a cause of disruption due to noise Specific requirements for contractor to manage
from plant and equipment. safety of pedestrians and traffic are included in the
contract conditions. Regular audits on contractor
compliance with these approved plans will be
undertaken by Council throughout construction.
This will be minimised wherever possible through
having as much of the materials cut to size and
preassembly prior to arriving on site.
Page 44 of 69
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.