Updated EMP Stage 2_Grasstree Court April 2023

of 47

Page text read automatically using OCR, there may be inaccuracies

2023 Ecological Management Plan – Grasstree Court – Lot 9



Step      Action
  1       Clear entire offset site. Mulch, strip and stockpile all top layers and weed material.
  2       Install main infrastructure e.g. haul/access roads, irrigation water line from treatment plant, water tanks.
  3       Install exclusion fencing around weed area.
          Provide weed treatment to entire receiver site after clearing, i.e. spray all weeds as they germinate for four
  4
          weeks prior to seed soil being moved to site.
  5       Site soil from Lot 6 transported and installed into the southern part of the rehabilitation site (0.8ha).
  6       Treatment to T1 (e.g. coir logs) and soil (0.3ha).
          Plant she-oak tubes and other trees. Planting included in T1 and T2 areas and incorporates both Stage 1 and
  7
          Stage 2 planting targets.
  8       Planting of grass trees into T2 area by Council.
  9       Install monitoring points.
 10       Ongoing weed management.

Practical completion for On-Maintenance Stage 1 has been achieved as follows:

Criteria                       Target                        Achieved
                               Fencing installed where
                                                             Installed around stage 2 area - rehabilitation area
Fencing                        needed – part safety
                                                             demarcated but unfenced to allow fauna movement
                               part fauna management
                               Landform stable &             Landform stabilised with coir logs (T1), mulch (T2), earthen
Weeds & Erosion
                               generally weed free           bund and erosion fencing in east
Soil translocation             0.8ha                         0.5ha in T2 south, 0.3ha in north (original T2 area)*
She-oak planting               200x                          670
Eucalypt (& allied)
                               50x                           50
species planting
Glossy black-cockatoo
                               2x (where possible)           2 x nest boxes installed August 2021
nest boxes
                                                             Irrigation system is connected to a fixed water supply
                                                             (recycled water supplied from the nearby treatment plant)
Irrigation system              To be installed
                                                             with 2 x water tanks and pump system. Necessary approvals
                                                             in place and signage “non-potable” installed.
      * areas approximate.

In addition to the above, the T1 area has been rehabilitated. This rehabilitation has been brought forward (i.e.
exchanged for part T2) with some 3000m2 treated for weeds and approximately 1500m2 (open dune) stabilised with
the use of coir logs, natural vegetation material and the planting of 350 plants (as tube stock) from nine species. It is
relevant to note:

      •    The she-oak planting has exceeded (by >200) the requirement for the project (i.e. stage 1 and stage 2 offset
           ratio target).
      •    The 350 native species incorporated into the T1 area is above any requirements for Stage 1 or Stage 2
           planting.

2.1.2 Additional Works and Fencing
The project has successfully achieved the required planting target for both Stage 1 and Stage 2. Additional planting of
600 trees is proposed (refer Section 4.4).

Parts of the rehabilitation area for Stage 2 will be capped in accordance with the design and specification provided by
Noosa Shire Council (refer APPENDIX B1) – refer Section 4.3.

The Madeira vine area was fenced (exclusion fencing) for future treatment 10 and will remain fenced until the area is
deemed secure by the contractors (e.g. buried beneath the GCL liner) which is to be vegetated as per this EMP.

Responsibility for existing fencing on the rehab site will transfer to Blue Care/Lendlease from 1 June 2023 and will be
removed as soon as planting is complete, and all works machinery have demobilised offsite.

10 It is noted that Council have mulched the weed stockpiles in this area in September 2022. Left untreated this area remains a

weed source and risk for the successful rehabilitation of the balance land.
                                                                                                                            24

Log in to download the original (Updated EMP Stage 2_Grasstree Court April 2023.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.