Updated EMP Stage 2_Grasstree Court April 2023
2023 Ecological Management Plan – Grasstree Court – Lot 9
Planting density/arrangement will consider the location of existing/retained trees with an approximate density of 300
trees per hectare (i.e. 600 tree over 1.8ha).
Two Glossy Black-cockatoo nest boxes have been installed in large bloodwood trees as part of Stage 1 rehabilitation.
Where available 14, tree trunks are to be salvaged from the project site and placed on the rehabilitation area to create
habitat.
4.5 Irrigation and Watering
A watering system has been installed on the receiver site for Stage 1. The watering system consists of tanks installed
in the eastern part of the site (secure compound) with six irrigation lines extending through the southern and
southwestern part of the Stage 1 rehabilitation area. Recycled water is pumped into the tanks for use as irrigation.
The Stage 2 irrigation system will be extended where appropriate and as agreed between Council and the project.
Final alignment of any new infrastructure will be decided on ground based on local conditions once works have been
completed. This system will allow watering to be done on an as needed basis over the 5-year maintenance period.
The Receiving/Rehabilitation Site set-out is provided 15 in FIGURE B4.
14 Noted that the project site does not support a large tree/canopy community.
15 The Set-out figure has been updated subsequent to the approved EMPs and following discussions with Council in order to
address rehabilitation site context and conditions.
29
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Updated EMP Stage 2_Grasstree Court April 2023.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.