Approved Decision Notice - MCU26 0040, OPW26 0066 & RAL26 0013 (As Published)
2025-68 I Landscape Schedule – sheet no. 31, prepared by 26.05.26
Building Coast Green
Currency Period
2. The Currency Period for this development approval lapses if the development has not
substantially started by 6 August 2031, unless an application to extend the currency period
is approved by Council.
SITE SPECIFIC CONDITIONS
Amended Plans
3. Submit a “Signage & Linemarking Plan” that includes directional signage, linemarking and
details of a traffic management system pursuant to Conditions 3 and 5 of this Decision Notice.
The additional plan must be prepared by a suitably qualified person (RPEQ) and be
submitted and approved by Council prior to the pre-start meeting.
Erosion and Sediment Control Plans
4. Submit a site-specific Erosion and Sediment Control Plan in accordance with the
International Erosion Control Association’s (IECA) Best Practice Erosion and Sediment
Control and prepared by a suitably qualified person (RPEQ and/or CPESC). The Plan must
be submitted prior to the commencement of works.
5. Prior to the commencement of bulk earthworks:
a. a hold-point inspection is required with a Council delegate to review that the erosion
and sediment controls on-site generally reflect the Erosion and Sediment Control Plan.
b. certification from a suitably qualified person (RPEQ and/or CPESC) must be submitted
to Council certifying that the erosion and sediment controls on site have been installed
in accordance with the Plan and IECA’s Best Practice Erosion and Sediment Control.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
6. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
pre-start meeting must include the relevant parties for the following aspects of the works:
a. civil engineering works;
b. landscape works;
c. erosion and sediment control works; and
d. other relevant parties.
A proxy may be nominated for any party unable to attend the meeting. Council must be
notified of any proxies prior to the pre-start meeting.
7. Submit a copy of the approved plans that are issued “For Construction” and duly signed by
the consultant Registered Professional Engineer of Queensland (RPEQ). Plans must be
submitted and approved by Council prior to the pre-start meeting.
8. Submit certificates demonstrating currency of public liability insurance and works insurance
covering the works. Certificates must be submitted to Council prior to the pre-start meeting.
9. Submit a condition report documenting any existing defects in the road reserve or
infrastructure, including photographs of the site frontage. The report must be submitted to
Council prior to the pre-start meeting.
Page 12 of 27
Document Set ID: 25048906
Version: 6, Version Date: 13/08/2026
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.