2005-16644 SRA - Response with conditions

Attached to the e-mail SARA Referral agency response – with conditions - MCU20/0037.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

RA6-N




SARA reference:        2005-16644 SRA
Council reference:     MCU20/0037
Applicant reference:   J000856



19 May 2020

Chief Executive Officer
Noosa Shire Council
PO Box 141
Tewantin Qld 4565
[email protected]

Attention:       Patrick Murphy


Dear Mr Murphy


SARA response—11 Margit Crescent, Sunrise Beach
(Referral agency response given under section 56 of the Planning Act 2016)

The development application described below was confirmed as properly referred by the Department of
State Development, Manufacturing, Infrastructure and Planning on 7 May 2020.


Response
Outcome:                            Referral agency response – with conditions.
Date of response:                   19 May 2020
Conditions:                         The conditions in Attachment 1 must be attached to any
                                    development approval.
Advice:                             Advice to the applicant is in Attachment 2.
Reasons:                            The reasons for the referral agency response are in Attachment 3.


Development details

Description:                        Development permit          Material change of use for a duplex

SARA role:                         Referral Agency
SARA trigger:                      Schedule 10, Part 4, Division 3, Subdivision 1, Table 1 (Planning
                                   Regulation 2017)

                                   Development application for a material change of use in an area of
                                   substantial unexploded ordnance potential

                                                                             South East Queensland (North) regional
                                                                             office
                                                                             Mike Ahern Building, Level 3, 12 First
                                                                             Avenue, Maroochydore
 Page 1 of 6                                                                 PO Box 1129, Maroochydore QLD 4558
Log in to download the original file

2005-16644 SRA - Response with conditions.pdf · 258 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 5 pages

Page 2

                                                                                            2005-16644 SRA




SARA reference:                        2005-16644 SRA
Assessment Manager:                    Noosa Shire Council
Street address:                        11 Margit Crescent, Sunrise Beach
Real property description:             Lot 135 on RP132135
Applicant name:                        Lucy Jane Cottee and Christopher Graham Ferraro
Applicant contact details:              C/- Property Projects Australia
                                        PO Box 1264
                                        New Farm, QLD 4005
                                        [email protected]


Representations
An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment Rules)
Copies of the relevant provisions are in Attachment 4.

A copy of this response has been sent to the applicant for their information.

For further information please contact Ruth Creffield, A/Senior Planning Officer, on 5352 9775 or via
email [email protected] who will be pleased to assist.

Yours sincerely




Garth Nolan
Manager (Planning)




 Department of State Development, Manufacturing, Infrastructure and Planning                    Page 2 of 6

Page 3

                                                                                                    2005-16644 SRA




Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application)


                                                                                                   Condition
 No.    Conditions
                                                                                                   timing
 Material change of use
 Schedule 10, Part 4, Division 3, Subdivision 1, Table 1 - The chief executive administering the Planning
 Act 2016 nominates the Director-General of the Department of State Development, Manufacturing,
 Infrastructure and Planning to be the enforcement authority for the development to which this
 development approval relates for the administration and enforcement of any matter relating to the
 following condition:
 1.     Provide written confirmation to the Department of State Development,                       Prior to the
        Manufacturing, Infrastructure and Planning by an approved contractor on the                commencement
        Australian Government, Department of Defence, Unexploded Ordnance (UXO)                    of works.
        Panel that the subject site has been remediated and cleared of Unexploded
        Ordnances.

        The Unexploded Ordnance (UXO) Panel is found online at:
        http://www.defence.gov.au/estatemanagement/support/dehp/WhoToEngage.asp




 Department of State Development, Manufacturing, Infrastructure and Planning                            Page 3 of 6

Page 4

                                                                                                2005-16644 SRA




Attachment 2—Advice to the applicant

General advice
1.       Terms and phrases used in this document are defined in the Planning Act 2016 its regulation or
         the State Development Assessment Provisions (SDAP) v2.6. If a word remains undefined it has
         its ordinary meaning.
2.       Provide the owner, occupier and any person employed to work on the subject site the following
         information:
                  (a) Residual UXO may still exist following remediation and all work should proceed with
                      due caution.
                  (b) The procedure to be followed by any person finding an object suspected of being
                      explosive ordnance or component thereof:
                        i.    advise the police immediately
                        ii.   do not disturb the object
                       iii.   take action, where appropriate, to prevent it being disturbed by another
                              person
                       iv.    note its approximate dimensions and general appearance
                        v.    note the route to its location.

                   Applicants wanting to find out more details of area management advice (AMA), current
                    UXO investigations and remedial search contractors, may use the following websites:
                    Department of Environment and Science - https://www.des.qld.gov.au/
                   Commonwealth Department of Defence - http://www.defence.gov.au/uxo/




Department of State Development, Manufacturing, Infrastructure and Planning                        Page 4 of 6

Page 5

                                                                                          2005-16644 SRA




Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)


The reasons for the department’s decision are:
 The proposed development is for a development permit for a material change of use for a duplex.
 The subject site is located in an area with substantial unexploded ordnance potential.
 SARA assessed the development application against State code 13: Unexploded Ordnance of the
   State Development Assessment Provisions (SDAP), version 2.6, and determined that with conditions,
   the development achieves compliance with the performance outcomes of the State code.

Material used in the assessment of the application:

      The development application material and submitted plans
      Planning Act 2016
      Planning Regulation 2017
      The State Development Assessment Provisions (version 2.6), as published by the department
      The Development Assessment Rules
      SARA DA Mapping system




    Department of State Development, Manufacturing, Infrastructure and Planning              Page 5 of 6

Page 6

                                                                               2005-16644 SRA




Attachment 4—Change representation provisions
(page left intentionally blank)




 Department of State Development, Manufacturing, Infrastructure and Planning      Page 6 of 6

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.