SDA0915024218 Concurrence agency response With conditions

Attached to the e-mail MCU15/0085 Referral Agency Response - 44 Nandroya Rd Cooroy.

of 6

Page text shows just the words. Original shows the document exactly as it was published.

Our reference:    SDA-0915-024218
Your reference:   MCU15/0085


26 October 2015

Brett de Chastel
Chief Executive Officer
Noosa Shire Council
PO Box 141
Tewantin Qld 4565




Dear Mr de Chastel

Concurrence agency response—with conditions
Lot 2 RP193949 (44 Nandroya Road, Cooroy)
(Given under section 285 of the Sustainable Planning Act 2009)


The referral agency material for the development application described below was received by the
Department of Infrastructure, Local Government and Planning under section 272 of the
Sustainable Planning Act 2009 on 18 September 2015.

Applicant details
Applicant name:                     Allan Hugh Forge
Applicant contact details:          C/- Noosa Town Planning
                                    1/75 Main Avenue
                                    Wilston QLD 4051

Site details
Street address:                     44 Nandroya Road, Cooroy
Lot on plan:                        2 RP193949
Local government area:              Noosa Shire Council


Application details
Proposed development:               Development Permit for Material Change of Use of
                                    Premises – Transport Type 3 - Depot


Page 1
                                                                         SEQ North Region
                                                                         Level 8, Mike Ahern Building
                                                                         12 First Avenue
                                                                         PO Box 1129 Maroochydore QLD 4558
Log in to download the original file

SDA0915024218 Concurrence agency response With conditions.pdf · 365 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 5 pages

Page 2

                                                                                            SDA-0915-024218

Aspects of development and type of approval being sought
     Nature of        Approval           Brief Proposal of                          Level of
   Development          Type                Description                           Assessment
 Material Change of Development Transport Use – Type 3                          Impact
 Use                permit        Depot to be conducted within                  Assessment
                                  existing shed on the premises



Referral triggers
The development application was referred to the department under the following
provisions of the Sustainable Planning Regulation 2009:
Referral trigger                  Schedule 7, Table 3, Item 1 – State-controlled road

Conditions
Under section 287(1)(a) of the Sustainable Planning Act 2009, the conditions set out in
Attachment 1 must be attached to any development approval.

Reasons for decision to impose conditions
Under section 289(1) of the Sustainable Planning Act 2009, the department must set out the
reasons for the decision to impose conditions. These reasons are set out in Attachment 2.

Approved plans and specifications
The department requires that the following plans and specifications set out below and in
Attachment 3 must be attached to any development approval.

 Drawing/Report Title                    Prepared by          Date       Reference      Version/Issue
                                                                            no.
Aspect of development: Material change of use
Site Plan                 Fineline            2 December                Job No.         -
                          Residential Design 2014                       2014104,
                                                                        DWG No. 1 of
                                                                        6



A copy of this response has been sent to the applicant for their information.

For further information, please contact Caroline Plank, Senior Planning Officer, Regional Services
(SEQ North) on 5352 9709, or email [email protected] who will be pleased to assist.

Yours sincerely




Garth Nolan




Department of Infrastructure, Local Government and Planning                                 Page 2

Page 3

                                                                                   SDA-0915-024218

Manager

cc:       Allan Hugh Forge C/- Noosa Town Planning, [email protected]

enc:      Attachment 1—Conditions to be imposed
          Attachment 2—Reasons for decision to impose conditions
          Attachment 3—Approved Plans and Specifications




Department of Infrastructure, Local Government and Planning                        Page 3

Page 4

                                                                                          SDA-0915-024218




Our reference:      SDA-0915-024218
Your reference:     MCU15/0085


Attachment 1—Conditions to be imposed


No.        Conditions                                                            Condition timing
Material change of use
Sustainable Planning Regulation 2009, Schedule 7, Table 3, Item 1 – State-controlled road—
Pursuant to section 255D of the Sustainable Planning Act 2009, the chief executive administering
the Act nominates the Director-General of Department of Transport and Main Roads to be the
assessing authority for the development to which this development approval relates for the
administration and enforcement of any matter relating to the following condition(s):
1.         The development must be carried out generally in accordance           At all times.
           with the following plan:
                     Site Plan, Fineline Residential Design, 2 December 2014,
                      Job No. 2014104, DWG No. 1 of 6.
2.              (a) Stormwater management of the development must                (a) At all times
                    ensure no worsening or actionable nuisance to the State-     (b) At all times
                    controlled road.                                             (c) Prior to the
                (b) Any works on the land must not:                                  commencement
                        i.    create any new discharge points for stormwater         of use.
                              runoff onto the State-controlled road;
                       ii.    interfere with and/or cause damage to the
                              existing stormwater drainage on the State-
                              controlled road;
                      iii.    surcharge any existing culvert or drain on the
                              State-controlled road;
                      iv.     reduce the quality of stormwater discharge onto
                              the State-controlled road.
                (c) Registered Professional Engineer of Queensland (RPEQ)
                    certification must be provided to the Department of
                    Transport and Main Roads’ North Coast Region by email
                    [email protected] (please quote TMR14-
                    012524), confirming that the development has been
                    designed and constructed in accordance with parts (a)
                    and (b) of this condition.




Department of Infrastructure, Local Government and Planning                                 Page 4

Page 5

                                                                             SDA-0915-024218




Our reference:      SDA-0915-024218
Your reference:     MCU15/0085


Attachment 2—Reasons for decision to impose conditions

The reasons for this decision are:
    To ensure the development is carried out generally in accordance with the plans of
       development submitted with the application
    To ensure that the impacts of stormwater events associated with development are
       minimised and managed to avoid creating any adverse impacts on the state
       transport corridor.

Findings on material questions of fact:
    The development is for a Material Change of Use for a Transport Use – Type 3
      Depot, to be conducted in the existing shed on the premises.
    The subject site is described as Lot 2 RP193949 and is located at 44 Nandroya
      Road, Cooroy.
    The subject site is located adjacent to a State-controlled road, the Bruce Highway.
    The development is unlikely to increase the impervious area of the site, however
      the application does not contain information about stormwater impacts, and
      therefore there is a small risk of stormwater impacting adversely on the State-
      controlled road.
    As such, the development is to ensure no-worsening of stormwater on the State-
      controlled road.

Evidence or other material on which the findings were based:
    Application material and submitted plans and reports
    State Development Assessment Provisions version 1.6, dated 6 July 2015
    SARA DA Mapping, including Aerial Photograph, and State-controlled road
      mapping
    Sustainable Planning Act 2009 and Sustainable Planning Regulation 2009
    Transport Infrastructure Act 1994.




Department of Infrastructure, Local Government and Planning                    Page 5

Page 6

                                                              SDA-0915-024218




Our reference:      SDA-0915-024218
Your reference:     MCU15/0085


Attachment 3—Approved plans and specifications




Department of Infrastructure, Local Government and Planning    Page 6

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.