                                       Charges Resolution (No.8) 2024



12.2    Application of section

        Section 12 applies where:

                 (a)      the development to which the trunk infrastructure relates has been
                          lawfully completed;

                 (b)      the trunk infrastructure is planned under this document to service the
                          development of other premises and has been completed and handed
                          over to Council;

                 (c)      the amount of the value of an infrastructure offset has not been fully
                          offset against a levied infrastructure charge to which the trunk
                          infrastructure relates.

12.3    Payment of a refund

        (1)      A refund will be paid by Council (as applicable) to the applicant in accordance
                 with the following:
                 (a)      the refund will not exceed the value of the unused infrastructure offset
                          and is not subject to indexation;
                 (b)      The amounts and timing of refund payments will be made as follows:
                          (i)     for refund amounts up to $150,000, the payment will occur in the
                                  December quarter in the financial year following completion of the
                                  works and “off-maintenance” handover of the trunk infrastructure to
                                  Council; and
                          (ii)    for remaining refund balance amounts over $150,000 up to
                                  $500,000 the payment will occur in the December quarter in the
                                  second financial year following completion of the works and “off-
                                  maintenance” handover of the trunk infrastructure to Council; and
                          (iii)   for any remaining refund balance amounts over $500,000, the
                                  payment will occur in the December quarter in the third financial
                                  year following completion of the works and “off-maintenance”
                                  handover of the trunk infrastructure to Council.

  13.         CONVERSION APPLICATIONS

13.1    Purpose

        Section 13 states the Council’s criteria for consideration and assessment of applications
        to convert non-trunk infrastructure to trunk infrastructure. This section is to be also read in
        conjunction with the “Minister’s Guidelines and Rules”.

13.2    Application of section

        (1)       This section applies if:
                  (a)     a condition of a development approval requires non-trunk infrastructure
                          to be provided; and
                  (b)     the construction of the non-trunk infrastructure has not started.



                                  Council Resolution effective 15 August 2024
Log in to download the original file

ATTACHMENT 2 - NSC CHARGES RESOLUTION (No.8) 2024.pdf · 1.5 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.