2019-12-16 GC Agenda - Item 5 - Attachment 1 - Noosa Spit Shoreline Erosion Management Plan-Part 1

of 109

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.5 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Noosa Spit SEMP Final Report                                                                             62
Shoreline Erosion Mitigation Options




4       Shoreline Erosion Mitigation Options
4.1     Introduction
        An initial rapid assessment of shoreline erosion management options was completed to inform the
        Noosa Spit SEMP. This work followed:

        • Conceptual options proposed by Council’s Project Control Group (PCG) (refer Attachment 1); and

        • A meeting with Sel Sultmann from the Department of Environment and Science (DES) held on
          Friday 2 August 2019. The conceptual options proposed by the PCG were discussed in the
          context of gaining approval for the proposed works.

        The shortlisted options were then considered in detail following a Multi-Criteria Analysis process and
        further engagement with the PCG. Where appropriate, The Model has been used to test the
        effectiveness of the shortlisted options.

        This Chapter presents the analysis of shoreline erosion managements options and justification for
        the preferred strategy.

4.2     Overview of Generic Options
        Management options presented here focus on reducing the rate of shoreline erosion at Dog Beach
        and to avoid a breakthrough of the Noosa Spit which provides sheltering to existing development.

        Coastal management options broadly fall within the categories of avoid, accommodate, accept for
        future development; and protect, accommodate, retreat for existing assets and development.

        For future development, the management approaches are:

        • Avoid the risk, by not permitting vulnerable developments in high risk areas (over the design life
          of the development);

        • Accommodate the risk by including provisions that reduce consequence of impacts (foundations,
          floor levels, etc.); and

        • Accept the risk where appropriate to the level of risk over the design life of the development.

        Planned development should generally adopt these principles to avoid creating new coastal
        management issues for Council.

        Existing assets and development are harder to manage as the value (e.g. open space) or built
        assets (e.g. urban area) are already in place, as is the case for the Noosa Spit and adjacent areas it
        protects. Options for management of existing assets include the following approaches:

        • Protect existing assets on the ground, whether important habitat, open space or development.
          Protection can be in the form of a hard structure or soft engineering measure, and can have offsite
          impacts;

        • Retreat is the ‘no defence’ approach that aims to preserve beach amenity by allowing natural
          recession of the shoreline. Retreat can involve relocating or sacrificing the asset when impacts
          occur; and




G:\Admin\B23636.g.mpb.NoosaSpit_SEMP\R.B23636.001.02.SEMP_final.docx
Log in to download the original file

2019-12-16 GC Agenda - Item 5 - Attachment 1 - Noosa Spit Shoreline Erosion Management Plan-Part 1(PDF, 18MB).pdf · 18.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.