2019-12-16 GC Agenda - Item 5 - Attachment 1 - Noosa Spit Shoreline Erosion Management Plan-Part 1

of 109

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (18.5 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
 Noosa Spit SEMP Final Report                                                                                83
 Shoreline Erosion Mitigation Options




4.3.3    Option 2: extension of the existing groyne at Dog Beach
         Figure 4-8 illustrates the model representation of the extension to the existing groyne. Key features
         of the option include:

         • The crest elevation of the groyne is 1 m above AHD (not overtopped under normal tidal conditions)

         • The extension is similar in length to the existing geofabric sand container groyne (effectively
           doubling the length of the existing structure).

         The impacts to peak tidal current figures show:

         • A moderate reduction (~0.2 to 0.4 m/s) in peak flood current magnitude at the Dog Beach channel
           and shoreline.

         • Increases to flood tide at the head of the proposed extension, effectively transferring the scour
           currently observed at the existing structure. There is also a minor increase in peak flood current
           magnitude through the central channel adjacent to the groyne structure.

         • The peak ebb tide impacts are like Option 1a and 1b, with a significant reduction in magnitude at
           the Dog Beach channel and shoreline. An increase in ebb tide current magnitude through the
           central channel is also observed.

         • The groyne extension option is considered ‘permanent’ and would be developed with a goal to
           minimise ongoing maintenance requirements. The design would need to account for local scour
           potential at the structure.

         The whole of life cost estimate for this option is $1.8M with annualised costs around $90,000/year.
         This estimate is based on the cost for similar works in 2012 (i.e. the existing training wall) with
         adjustments for inflation. This includes beach nourishment as part of the capital costs. It is noted that
         the extended structure is not expected to stabilise the entire length of shoreline and therefore
         additional management actions and costs may be required toward the eastern extent of the Dog
         Beach shoreline.

         The potential for impact to environmental values is primarily related to the construction phase. There
         would also be a notable impact to visual amenity.

         The social benefits are primarily related to stabilising a longer section of shoreline and providing a
         width of beach for recreational opportunities.

         The risks to Council are generally low to medium and manageable. The exception being pedestrian
         slip hazard at the crest of the structure and the submerged hazard which could result in injury when
         swimming (diving) or boating near the structure. Similar risks are associated with the existing
         structure, so the training wall extension does not represent a significant change in risk profile. Full
         details of the risk assessment results are provided in Appendix D.




 G:\Admin\B23636.g.mpb.NoosaSpit_SEMP\R.B23636.001.02.SEMP_final.docx
Log in to download the original file

2019-12-16 GC Agenda - Item 5 - Attachment 1 - Noosa Spit Shoreline Erosion Management Plan-Part 1(PDF, 18MB).pdf · 18.5 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.