Council archive · source document
Concurrence Agency Response · OPW11/0144
Notice
Concurrence Agency Response, Amended Concurrence Agency Response
or Advice Agency Response
Agency Interest - General
1. All works are to be constructed in accordance with the attached approved drawings and specifications
listed in the approved plans section in the notice attached to this permit.
2. All materials and works must comply with Australian Standards.
3. An appropriate spill kit, personal protective equipment and relevant operator instructions/emergency
procedure guides for the management of fuel and chemicals associated with the operational works
stage must be kept on site.
4. Anyone working under this approval must be trained in the use of the spill kit.
5. Telephone the Department of Environment and Resource Management's (DERM) Pollution Hotline on
1300 130 372 or local office on (07) 5459 6132 immediately after becoming aware of any release of
contaminants or other breach of condition, not in accordance with the conditions of this approval.
6. The construction and installation of the works must not result in any adverse impacts on the
surrounding environment, nor cause any long-term maintenance and management implications.
7. Should the works result in adverse impacts, the permit holder is responsible for rectification works and
where necessary the removal of the works causing impacts.
8. The chief executive administering the Coastal Protection and Management Act 1995 may order the
works to be removed or modified within a reasonable time, if the works have or are likely to have a
significant effect on coastal management because the works:
(i) create a-danger to the public; or
(ii) cause erosion or land degradation; or
(iii) are unstable; or
(iv) have not been constructed according to the approved plans.
Agency Interest - Land
9. No sand is to be removed from the coastal dune system or active beach system within the erosion
prone area or coastal management district.
10. Spoil removed from within the proposed development area must be stockpiled separately upon
excavation, and reused, rather than disposed of.
11. Best practice erosion and sediment control measures must be implemented and maintained to
minimise erosion and the release of sediment.
Agency Interest - Acid Sulfate Soil
12. Acid sulfate soils must be managed such that contaminants are not directly or indirectly released to
any land or waters.
13. Should acid sulfate soils be discovered they must be treated and managed inline with the latest
edition of the Queensland EPA's 'Instructions for the Treatment and Management of Acid Sulfate
Soils' 2001.
Agency Interest - Vegetation
14. All works must be undertaken in a manner that minimises damage to the native vegetation on and
adjacent to the site.
15. There must be no death or permanent removal of marine plants, inter-tidal plants or native terrestrial
woody vegetation outside of the disturbance footprint as indicated within the attached approved plans,
as a result of these works.
Page 4 of 7. 091217 Department of Environment and Resource Management
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Concurrence Agency ResponseRelated documentApplication case desk ↗
About this file
- File size
- 3.2 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.