ORDINARY MEETING MINUTES 18 DECEMBER 2014
Preparation of a Preliminary Construction Management Plan
6. A preliminary Construction Management Plan must be submitted with the
Operational Works application and must address the following:
a. traffic management during all aspects of the construction phase including:
i. a Traffic Management Control Plan in accordance with the Manual
of Uniform Traffic Control Devices (MUTCD) detailing all temporary
signage and traffic control measures prior to construction
ii. maintenance of safe pedestrian access for the areas affected by the
works during and after daily construction has ceased
iii. proposed fencing to the site during the construction phase of the
development
iv. approval of the Traffic Management Control Plan by the Department
of Transport and Main Roads (DTMR) for any works on State
controlled roads
v. provision for worker car parking
b. maintenance and protection of water quality and existing drainage lines
through the construction site, through the implementation of appropriate
erosion and sediment control measures
c. works programme identifying key components of the works and their
respective durations
d. establishment of a communication protocol with the general public,
adjoining owners, emergency services and local businesses to advise of
agreed construction times, impacts on traffic, services and other relevant
issues
e. identification of complaint management procedures including:
i. contact details for the on-site manager
ii. dispute resolution procedures
f. details on the location of external fill sites/sources, the haulage route,
type of vehicle to be utilised during filling operations and frequency of
usage. NB any damage to the existing road system as a result of
haulage operations shall be fully repaired at the applicant’s expense
g. it is acknowledged that the preliminary Construction Management Plan
will be a draft document requiring finalisation upon appointment of the
Principal Contractor employed to construct the works and a final
document will be required to be submitted at the Pre-Start Meeting for the
project.
UNITYWATER
7. Connection to the Unitywater live water supply and live sewerage system must
be undertaken by Unitywater at the applicant’s cost.
B. Include the following property notes:
REC13/0146 – Stormwater Treatment Device
The following notation applies to approved lots 26, 27 and 28:
“A private stormwater treatment device is located within this allotment and the owner
is responsible for any maintenance”
“This property contains a stormwater treatment device protected by a covenant, and
a maintenance handbook is available under separate application which outlines the
maintenance requirements.”
This is not an official copy of Council’s Minutes
Page 13 of 58