ORDINARY MEETING MINUTES 18 DECEMBER 2014
ENGINEERING
Earthworks
4. All earthworks must be in compliance with the relevant codes and policies of
The Noosa Plan (particularly the Earthworks Code) and undertaken in
accordance with a Development Permit for Operational Works. The application
for operational works for earthworks shall also include the details of any
associated drainage works (eg swales, scour protection, stormwater pipes
work).
5. Suitable construction management measures must be put in place prior to the
commencement of development works on this site and for all stages of works,
the measures must address in particular:
a. Traffic management during all aspects of the construction phase
including:
i. Temporary signage and traffic control measures in accordance with
Manual of Uniform Traffic Control Devices (MUTCD) to provide
warning to drivers and road users of any safety hazard or changes
to traffic conditions due to the proposed works.
ii. Details on the location of imported fill sources, the haulage route,
type of vehicle to be utilised during filling operations and frequency
of usage.
NOTE: any damage to the existing road system as a result of
haulage operations must be fully repaired at the applicant’s
expense
b. Effective procedures and measures to protect the Riparian Buffer and
existing natural flora and fauna.
c. Effective procedures and measures to minimise adverse environmental
impact on other properties and roads users including noise and dust
emission.
d. Establishment of a communication protocol with the adjoining owners and
any other affected parties to advise of construction times, impacts on
traffic and services and any other relevant issues.
Stormwater Drainage
6. Stormwater runoff from the development areas must be disposed off in a
controlled manner on site without causing erosion or adverse impacts on the
environment and/or the existing drainage conditions on other properties (eg by
concentrating or diverting additional flows and/or causing additional ponding on
other properties) .
7. The development works must include stormwater management and treatments
measures/devices that:
a. Are designed in accordance with the current version of the Deemed to
Comply Solutions by Water By Design; or
b. Are designed to treat stormwater to achieve 80% Reduction in Total
Suspended Solids, 60% Reduction in Total Phosphorous and 45%
Reduction in Total Nitrogen prior to discharge from the site compared to if
there was no water pollutant mitigation incorporated into the design.
A Development Permit for Operational Works for stormwater management shall
be required.
This is not an official copy of Council’s Minutes
Page 46 of 58
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.