Delegated Report - Code - Planning MCU26 0040, OPW26 0066 & RAL26 0013 (As Published)
39. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or
machinery. It is essential to implement appropriate approved erosion and sediment control
measures throughout the site during all phases of construction including vehicle shakedown
pad/grid (or similar) at the access to the construction site. Where sediments or other
contaminants are deposited on a road, they must be removed so as not to enter Council’s
drainage system or waterways.
Damage to Services and Assets
40. Any damage caused to existing services and assets as a result of the development works
must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets
must first be referred to the relevant service authority for approval.
PRIOR TO THE COMMENCEMENT OF THE USE
Certification/Supervision
41. Upon completion of the work a certificate must be issued by an RPEQ certifying that the
works have been constructed in accordance with the Operational Works permit.
42. A final inspection and approval of the new driveway and completed reinstatement works by
Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the
inspection.
43. Prior to commencement of use, for each stage, the following (prepared by respective
qualified persons* and certifying compliance with approvals) must be submitted to Council:
a. Landscaping certification confirming all works have been constructed in accordance
with conditions of approval.
b. AS2303:2018 certification for all street trees.
*(Refer to Advisory Note)
5. REFERENCE DOCUMENTS
Plan No. Rev. Plan/Document Name Date
2576-SBSMP-01 2.0 Site-Based Stormwater Management Plan 8 April 2026
prepared by Barlow Shelley
2576-SWMP-01 2.0 Waste Management Plan prepared by Barlow April 2026
Shelley
6. REFERRAL AGENCIES
The referral agencies applicable to this application are:
Referral Status Referral Agency and Referral Trigger Response
Address
Advice Agency Energy Queensland Schedule 10, Part 9, The agency provided its
Limited Level 6, 420 Division 2, Table 1, Item 1 response on 27 March
Flinders Street (10.9.2.1.1) – 2026 (Reference No.
Townsville QLD 4810 Reconfiguring a lot ECM 39501951-
subject to an easement 40677416). A copy of
Page 28 of 33
Document Set ID: 25021329
Version: 9, Version Date: 12/08/2026