MCU21.0192 -Applicant's Response to Council's IR
oriented to capture the prevailing winds and address the natural topography of the site.
Information Required by Council
4. Provide a preliminary Stormwater Management Plan (SWMP), prepared by a Registered Professional
Engineer of Queensland (RPEQ), demonstrating that the proposed development will not cause a worsening
of stormwater conditions by adversely altering stormwater drainage characteristics external to the site,
including, but not limited to:
4.1. additional ponding on neighbouring properties or on road reserve;
4.2. increased runoff onto neighbouring properties or road reserve;
4.3. redirect overland flows.
Applicant’s Response
Refer to the Preliminary Stormwater Management Plan prepared by AAA Design & Development enclosed
within Attachment 3. The preliminary plan includes the QUDM Catchment Calculation.
Information Required by Council
5. Provide a preliminary earthworks plan for the proposed development, prepared by a RPEQ, including, but
not limited to: extents; volumes; existing and finished levels; cross sections; batters and retaining structures;
stabilisation methods proposed, etc.
Applicant’s Response
Refer to the Preliminary Earthworks Plan prepared by AAA Design & Development enclosed within Attachment
4.
Information Required by Council
6. Provide amended plans demonstrating compliance with the requirements of AS/NZS 2890.1:2004. The plans
must be prepared by a qualified person and demonstrating the headroom measured as shown on “FIGURE
5.3 – CRITICAL HEADROOM MEASUREMENT AT A GRADE CHANGE” of AS/NZS 2890.1:2004
PO Box 1818 07 5474 3873
Noosa Heads [email protected]
QLD 4567 rgstrategic.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.