Council archive · source document
SUPERSEDED Decision Notice - 010.2007.00001841.001 [As Published] · 132007.1841
- 12 -
All contributions must be paid prior to the issue of a Development Permit for Operational
Works.
Alternatively a trading bank guarantee shall be submitted to Council plus 20%. Should
the contributions not be paid at the due time, Council shall call upon the trading bank
guarantee in full.
Processing of bonds for security where specific Council approval has been given for the
bonding of contributions will incur an administration fee in accordance with Council’s
Land Development Commercial & Regulatory Fees at the time of lodgement.
In the event that the Development Permit for Material Change of Use of Premises
lapses or is cancelled, the trading bank guarantee will be returned.
General
77. A suitably qualified Registered Professional Engineer shall prepare engineering
drawings and specifications for all engineering works that will become Council
infrastructure, which shall be submitted in conjunction with an application for a
Development Permit for Operational Works. To avoid conflict with underground pipes or
services, all existing and proposed services required by the development shall be
shown on the plans.
78. Any alteration of any public utility or other facilities necessitated by the development of
the land or associated construction works external to the site shall be at no cost to
Council.
79. The transportation of all materials to and from the site shall be undertaken in a manner
such that no particle matter escapes onto a public road. All vehicles carrying materials
either to or from the site shall be covered to prevent materials including dust being
windblown from the vehicle.
Environmental Health
80. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial
and Industrial Premises”, including an external imperviously paved area correctly sized
for all refuse and recycling containers and suitably screened from public places and
neighbouring properties. A bin wash area is required with a cold-water tap, hose and
drain outlet connected to sewer, via a bucket trap. The drain outlet is to be designed to
prevent storm water entry to the sewerage system and this can be achieved with a nib
wall 50mm high and up to 700mm x 700mm wide (max 0.5m²), or alternatively the
waste area can be roofed, or any other design approved by Council.
81. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
82. The development must allow refuse-loading areas to be located off street. All vehicles
associated with the collection of waste/recyclables, shall enter and leave the site in a
forward direction.
83. Noise emission from mechanical equipment (air conditioners, refrigeration equipment or
pool pumps etc) shall comply with the following requirements:
The equipment shall be installed and located in a manner that prevents excessive noise
in accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement
Notices (on-the-spot fines) may apply for offences.
A person must not use equipment on any day if it makes or causes noise to be made –
Page 12 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED Decision Notice - 010.2007.00001841.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 94 KB (small file)
- File type
No other editions are linked here.