Council archive · source document
Further Advice Response 17-07-25 22BRT0122_LT01_3 · OPW25/0042
MOVEMENT SUMMARY
Site: 101 [Weyba Road_Mary Street - Exiting 2022 PM Peak
(Weekday) (Site Folder: Site 4)]
Output produced by SIDRA INTERSECTION Version: 9.1.3.210
New Site
Site Category: (None)
Roundabout
Vehicle Movement Performance
Mov Turn Mov Demand Arrival Deg. Aver. Level of 95% Back Of Prop. Eff. Aver. Aver.
ID Class Flows Flows Satn Delay Service Queue Que Stop No. of Speed
[ Total HV ] [ Total HV ] [ Veh. Dist ] Rate Cycles
veh/h % veh/h % v/c sec veh m km/h
South: Reed Street
1 L2 All MCs 297 0.0 297 0.0 0.419 9.0 LOS A 3.3 23.4 0.91 0.76 0.93 51.4
2 T1 All MCs 266 0.0 266 0.0 0.549 9.1 LOS A 6.0 42.0 0.98 0.80 1.11 49.4
3b R3 All MCs 268 0.0 268 0.0 0.549 16.5 LOS B 6.0 42.0 0.98 0.80 1.11 48.6
3u U All MCs 2 0.0 2 0.0 0.549 17.7 LOS B 6.0 42.0 0.98 0.80 1.11 48.6
Approach 834 0.0 834 0.0 0.549 11.5 LOS B 6.0 42.0 0.96 0.78 1.05 49.8
SouthEast: Weyba Road
21b L3 All MCs 347 0.0 347 0.0 0.206 3.1 LOS A 0.0 0.0 0.00 0.44 0.00 56.0
21a L1 All MCs 491 0.0 491 0.0 0.526 6.6 LOS A 5.1 35.8 0.88 0.71 0.93 52.1
23a R1 All MCs 107 0.0 107 0.0 0.526 11.8 LOS B 5.1 35.8 0.88 0.71 0.93 51.2
23u U All MCs 4 0.0 4 0.0 0.526 15.6 LOS B 5.1 35.8 0.88 0.71 0.93 51.2
Approach 949 0.0 949 0.0 0.526 5.9 LOS A 5.1 35.8 0.56 0.61 0.59 53.3
North: Weyba Road
7a L1 All MCs 99 0.0 99 0.0 0.237 12.6 LOS B 1.5 10.4 0.87 0.79 0.87 50.8
8 T1 All MCs 245 0.0 245 0.0 0.648 16.1 LOS B 7.5 52.5 1.00 1.00 1.40 46.1
9 R2 All MCs 158 0.0 158 0.0 0.648 22.2 LOS C 7.5 52.5 1.00 1.00 1.40 45.4
9u U All MCs 9 0.0 9 0.0 0.648 24.7 LOS C 7.5 52.5 1.00 1.00 1.40 45.4
Approach 512 0.0 512 0.0 0.648 17.5 LOS B 7.5 52.5 0.98 0.96 1.30 46.7
West: Mary Street
10 L2 All MCs 206 0.0 206 0.0 0.259 7.1 LOS A 1.9 13.1 0.80 0.68 0.80 52.7
12a R1 All MCs 487 0.0 487 0.0 0.656 14.1 LOS B 8.4 59.0 0.98 0.84 1.19 47.8
12 R2 All MCs 201 0.0 201 0.0 0.656 15.4 LOS B 8.4 59.0 0.98 0.84 1.19 47.8
12u U All MCs 26 0.0 26 0.0 0.656 17.8 LOS B 8.4 59.0 0.98 0.84 1.19 47.8
Approach 921 0.0 921 0.0 0.656 12.9 LOS B 8.4 59.0 0.94 0.80 1.11 48.8
All Vehicles 3216 0.0 3216 0.0 0.656 11.2 LOS B 8.4 59.0 0.84 0.77 0.97 49.9
Site Level of Service (LOS) Method: Delay (SIDRA). Site LOS Method is specified in the Parameter Settings dialog (Options tab).
Roundabout LOS Method: SIDRA Roundabout LOS.
Vehicle movement LOS values are based on average delay per movement.
Intersection and Approach LOS values are based on average delay for all vehicle movements.
Roundabout Capacity Model: SIDRA Standard.
Delay Model: SIDRA Standard (Control Delay: Geometric Delay is included).
Queue Model: SIDRA queue estimation methods are used for Back of Queue and Queue at Start of Gap.
Gap-Acceptance Capacity Formula: SIDRA Standard (Akçelik M3D).
HV (%) values are calculated for All Movement Classes of All Heavy Vehicle Model Designation.
Arrival Flows used in performance calculations are adjusted to include any Initial Queued Demand and Upstream Capacity
Constraint effects.
SIDRA INTERSECTION 9.1 | Copyright © 2000-2023 Akcelik and Associates Pty Ltd | sidrasolutions.com
Organisation: TTM CONSULTING PTY LTD | Licence: NETWORK / Enterprise Level 5 | Processed: Tuesday, 15 July 2025 3:40:18 PM
Project: C:\Users\Ashley.Schalken\OneDrive - Colliers International\2022 Synergy Projects - 22BRT0122 3 – 7 Serenity Close, Noosa Heads –
Proposed Hotel resort\6 - Analysis\1_SIDRA\22BRT0122_02_OPW.sip9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Further Advice Response 17-07-25 22BRT0122_LT01_3.pdfRelated documentApplication case desk ↗
About this file
- File size
- 2.3 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.