RESPONSE TO FURTHER ADVICE - ADG1808.25 Dewatering Management Plan_Rev0_07.05.25 · MCU25/0054
Plans and drawings: the text below has words only, no drawings.
ADG Consulting Pty Ltd
1 Introduction
ADG Consulting Pty Ltd (ADG) was engaged by Ross Palazzesi care of SCG Consulting Engineers to prepare
a Dewatering Management Plan (DMP) for the proposed residential duplex development within property
described as Lot 3 on RP3813, situated at 20 William Street, Noosaville, Queensland.
1.1 Proposed development
It is understood the proposed development will comprise of a three‐storey residential duplex building
over a single level in‐ground basement car park with car turntable.
Based on information provided by SCG Consulting Engineers, existing ground levels across the proposed
basement footprint are approximately RL 1.35 m Australian Height Datum (AHD). Excavations to facilitate
the basement construction are proposed to extend to an approximate depth of 2.05 m below existing
ground level (bgl), corresponding to an approximate elevation of ‐0.7 mAHD (allowing for up to 325 mm
raft slab and 75 mm blinding layer for basement finished floor level of ‐0.3 mAHD). Localised deeper
excavations will be required to facilitate other structural elements (i.e. car turntable, pile caps and
footings), where required.
During a geotechnical and acid sulfate soil investigation on the site in March 2025, no groundwater was
recorded in the drilling of boreholes to depths of up to 3.0 mbgl (PTG Consulting, 2025). However, ADG
notes that groundwater levels can be perched and fluctuate seasonally and during heavy rainfall events.
Due to the site’s close proximity to the tidal Noosa River and the permeable nature of the silty sand soils
encountered, this increases the likelihood of groundwater fluctuations. In addition, ADGs recent previous
experience in the locality has generally identified standing groundwater at or around RL 0.5 to 1.0 mAHD,
and given the sandy subsurface profile and proximity to the tidal canal network associated with Noosa
Inlet these relative groundwater levels should be expected, with higher levels during or following periods
of intense or extended rainfall. Dewatering will therefore be necessary to allow the basement and other
structural elements to be constructed in dry conditions.
1.2 Relevant guidelines
The DMP was prepared with reference to the following documents:
Australian and New Zealand Guidelines for Fresh and Marine Water Quality 2018. Australian and
New Zealand Governments and Australian state and territory governments, Canberra ACT, Australia
(ANZG, 2018), which supersedes Australian and New Zealand Guidelines for Fresh and Marine Water
Quality, Australian and New Zealand Environment and Conservation Council and Agriculture and
Resource Management Council of Australia and New Zealand (ANZECC/ARMCANZ). 2000.
Environmental Protection (Water & Wetland Biodiversity) Policy 2019. Queensland Government.
2019.
Guidelines for Managing Risks in Recreational Water. Australian Government, National Health and
Medical Research Council (NHMRC). 2008.
Monitoring and Sampling Manual 2018, Version 2 June 2018. Department of Environment and
Science (DES). 2018.
Noosa River environmental values and water quality objectives. Department of Environment and
Science (DES). 2022.
National Environment Protection (Assessment of Site Contamination) Measure 1999, (as amended
May 2013). National Environment Protection Council (NEPC). 2013.
Queensland Water Quality Guidelines 2009, Version 3. The Department of Environment and
Heritage Protection (DEHP). 2013.
ADG1808.25 Dewatering Management Plan_Rev0_07.05.25 Page 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
RESPONSE TO FURTHER ADVICE - ADG1808.25 Dewatering Management Plan_Rev0_07.05.25.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.5 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.