Original source · versioned page text
Attachment 4 - Site Investigation and Slab Report
NOTES
1. CONCRETE CLASS
CONCRETE TO BE CLASS N25 FOR SLABS & CLASS N20
FOR FOOTINGS & PIERS. 80 SLUMP. 20 NOM. AGGREGATE
2. CONCRETE COMPACTION
ALL CONCRETE TO BE MECHANICALLY VIBRATED FOR
COMPACTION IN TRENCHES OR FORMWORK.
3. SITE SOIL CONDITIONS
IF SOIL OR SITE CONDITIONS VARY FROM THOSE
INDICATED IN THE SITE INVESTIGATION REPORT THEN
THE FOOTING AND SLAB DESIGN SHOULD BE VERIFIED
WITH E.B.LS.
4, SCALED DIMENSIONS
DO NOT SCALE THIS DRAWING FOR SET OUT. REFER TO
DIMENSIONED WORKING DRAWINGS.
5. TERMITE MANAGEMENT.
PROVIDE TERMITE MANAGEMENT SYSTEM TO REDUCE
LIKELIHOOD OF TERMITE INFESTATION & TO DETER
CONCEALED ENTRY.
|
j | TIMBER
IN HIGH MOISTURE SITES, | | FRAME
COAT EDGE WITH XYPEX
.. CONCENTRATE WHERE |.
CONCRETE IN CONTACT | |
LAP VAPOUR BARRIER
WITH SOIL OR EXTEND
VAPOUR BARRIER 10 {| 200mm MIN. & FULLY TAPE
FIGURE 5.2 OF AS2870 |
6. FILL COMPACTION
COMPACT FILL UNDER SLAB TO 65% SAND DENSITY
INDEX OR 98% STANDARD COMPACTION. USE ONLY CLEAN
SOIL - FREE OF ORGANIC OR COMPRESSIBLE MATTER.
7. ARTICULATION JOINTS
ARTICULATION JOINTS TO BE CONSTRUCTED IN ACCORDANCE
WITH “CONCRETE INFORMATION" FROM THE CEMENT AND
CONCRETE ASSOCIATION OF AUSTRALIA - TECHNICAL NOTE 61.
8. LOAD BEARING
LOAD BEARING WALLS SHOULD BE SUPPORTED BY SLAB
THICKENINGS. WHERE THIS DOES NOT OCCUR, VERIFY THE
DESIGN WITH E.B).S.
9. SITE INSPECTIONS
THE FOOTING & SLAB PREPARATIONS SHOULD BE VERIFIED
BY INSPECTIONS DURING CONSTRUCTION. WHERE PREPARATION
VARIES FROM THE DESIGN THEN ADEQUACY SHOULD BE
VERIFIED WITH E.B.1.S
10, HOT WEATHER CONDITIONS
DURING HOT OR WINDY CONDITIONS
ADDITIONAL PRECAUTIONS SHOULD BE TAKEN
TO CONTROL EVAPORATION, TO REDUCE THE RISK
OF PREHARDENING CRACKING IN CONCRETE,
THIS MAY TAKE THE FORM OF A SPRAY ON ANTI -
EVAPORATIVE AGENT AND ESTABLISHING A
TEMPORARY WIND BREAK
11, BLOCK WORK REINFORCING
VERTICAL STARTER BARS ARE TO BE PROVIDED TO COINCIDE
WITH THE LOCATIONS SPECIFIED BY THE DESIGNER. THESE ARE
GENERALLY AT ALL CORNERS, EITHER SIDE OF OPENINGS
AND AT 1200 MAX CENTERS AND ARE TO BE CAST INTO
THE FOOTING AND/OR SLAB
12, PLUMBING (STORMWATER & SEWER)
FOR “M, H1, H2 & E" CLASS SITES, PROVIDE ROTATION BENDS &
TELESCOPIC JOINS TO ACCOMODATE MOVEMENT OF SOIL
WITHOUT SEPARATION OF PIPEWORK. PIPEWORK FITTINGS SIMILAR
TO “STORMPLASTICS" (WITH RECOMMENDED PRACTICE) IS
RECOMMENDED. WHERE LARGE RUNS OF PIPE, SOFT SOILS OR
UNCOMPACTED FILL LOCATED UNDER SLAB, PROVIDE SUPPORT
FIXING TO SUSPEND FROM MAIN SLAB
13, REFERENCED DOCUMENTS
THESE DRAWINGS SHALL BE READ IN CONJUNCTION WITH
REPORT No. 210417-SI/FD BY EBIS
COMPLIANCE WITH DESIGN
FOR COMPLIANCE WITH OUR DESIGN, THE FOLLOWING
MINIMUM STANDARD FOR PIER/PAD FOOTING CONSTRUCTION
IS REQUIRED:
BASE OF PIERS ARE TO BE OF AT LEAST THE SPECIFIED DIAMETER
LOOSE SOIL IS TO BE FULLY REMOVED TO EXPOSE THE SPECIFIED
FOUNDING SOILS;
WHERE COMPLETE REMOVAL OF SOILS IS UNACHIEVABLE, THEN
DEPTH OF THE FILL SHOULD BE LIMITED TO NO MORE THAN 50mm
AND COMPACTED TO ACHIEVE AN ALLOWABLE BEARING CAPACITY
OF 200kPa
AS A GUIDELINE ONLY
FOR SAND:
A70 x 35 STUD SHALL NOT PENETRATE MORE
THAN 20mm USING GREAT EFFORT
FOR CLAY:
A N12 ROD SHALL NOT PENETRATE MORE
THAN 50mm USING GREAT EFFORT
THICKEN SLAB LOCALLY & PLACE
EXTRA SQUARE SL82 SLABMESH
(1200 x 1200) OVER EACH SLAB
PIER. 30 TOP COVER
I" N12 STARTER BARS
| At 1000 CTS OR
| RIO STARTER BARS
|
j
AT 600 CTS
AS PER CLAUSE 5.3.3.4
3-L11TM TOP & BTM TIED AS2870
WITH R6 LIGS AT 900 CTS
OR EQUIVALENT CAGE
[ FOUND P2 PIERS
350
FOOTING & SLAB DETAIL
TERMINATE VAPOUR BARRIER
MIN. 400mm INTO FOOTING
oo oo
3-L1 Tw200 § a ===
ee ee ee >
350
THICKENING BEAM DETAIL
_ a — FOUND P3 PIERS
(a) OF ~ : | | AS SPECIFIED : Te
"TO NCC/AS2870 Te
. 1000 ~~" 1 TONCC/AS2870
SL82 SLABMESH. 30 TOP/40 BTM COVER | \ SL82 SLABMESH. 30 TOP/40 BTM COVER | | , 5t82 SLABMESH. 40 BTM COVER \ {|
E = 100 > = 100 | ; ==. = 100 125
pa a Tee ee ——— =
be VAPOUR BARRIER | t r __ -_ Lo VAPOUR BARRIER | a ~ eee ieee eae — VAPOUR BARRIER. |
a TO NCC/AS2870 —L
FOUND P4 PIERS.
: ASSPECIFIED”
350 TO
SLAB THICKENING DETAIL
FOR TENDER/APPROVAL 02.03.2022
Engineering & Building Investigation Services —
Unit 1/4 Textile Ave, Warana
PO Box 973 Buddina 4575
Proposed New Residence
EBIS
T: (07) 5436 9199 F: (07) 5436 9198 E: [email protected]
Client: C & H Fraser
at Lot 21 (No. 16) Pines Road, Cooroy
FOOTING & SLAB DETAILS
Drawing No. A3-210417-FD2
Scale: 1:20
February 2022
Checked tod
Drawn: SLS
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.