Attachment 2 - 1856-Stormwater Rev. F
The original of this document is very large (11.4 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Original PDF page 30, section 1. The text section number identifies this passage in the reader.
CHASE OUTLET TO IL2.4 IN EXISTING
GULLY & PROVIDE ROCK & PRESS
ROCK INTO INVERT OF DRAIN WITH
EXCAVATOR BUCKET. PLACE PROVIDE FILL OVER NEW NATURAL SURFACE
GEOTEXTILE OVER THE ROCK & PIN AS DN900 SW PIPE AS
DIRECTED BY SUPERINTENDENT REQUIRED
PROVIDE DN900 HEADWALL
SINGLE CELL
CE
RFA
H SU
FINIS
PROVIDE FILL OVER NEW
DN900 SW PIPE AS
REQUIRED 1
NATURAL SURFACE FLOW
19
IL2.5
D50=200mm NEW DN900 RCP SW AT 0.12%
2.7mm
DATUM RL5.0
PROVIDE CHILD PROOF
SAFTEY GRILL WITH
HORIZONTAL SPACING
NOT EXCEEDING 150mm
STORMWATER SYSTEM 19 - SECTION M
SCALE 1:10 (A3)
W M
R CP S SW30
00
1 DN9
NEW
19
ENERGY DISSIPATER CALCULATION
M
SW30 OUTLET VELOCITY = 1.0m/s
PIPE SIZE = DN900 RCP
L = 3D [D50 = 200mm]
2.7m ENERGY DISSIPATOR LENGTH = 3D x 0.900 = 2.7m
CHASE OUTLET TO IL2.4 IN EXISTING
GULLY & PROVIDE ROCK & PRESS
ROCK INTO INVERT OF DRAIN WITH 5
EXCAVATOR BUCKET. PLACE 1
GEOTEXTILE OVER THE ROCK & PIN AS
DIRECTED BY SUPERINTENDENT
2.85m
NEW DN900 RCP SW AT 0.12%
STORMWATER SYSTEM 19 - ENERGY DISSIPATER DETAIL
STORMWATER SYSTEM 19 - DETAIL PLAN SCALE 1:10 (A3)
SCALE 1:250 (A3)
PROJECT: JOB NUMBER
REV DATE DESCRIPTION BY CHKD DRAWN
I GDETAL
IS SCALE APPROVED PROPOSED SUBDIVISION 1856
A 13-09-19 FOR APPROVAL MM CL AT NOOSA CIVIC, WALTER HAY DRIVE
B 24-08-20 REVISED STORMWATER ALIGNMENT MM CL DATUM AHD SHEET: 30 OF 30
0 2.5 5 7.5 10 12.5m FOR STOCKWELL PTY LTD
C
D
21-09-20
16/10/20
REVISED FOR NOOSA COUNCIL DRAFT CONDITIONS
REVISED AS PER COUNCIL RFI [29/09/20]
MM
MM
CL
CL
DESIGN MM ................. DRAWING NUMBER REV
DRAWING TITLE:
DRAWN MM Director: CAMERON LANDRETH
E 26-11-20 REVISED AS PER COUNCIL RFI [5-11-20] MM CL SCALE 1:250 A3 p 07 5443 8285 ABN 89 215 591 077
DESIGN CHECK (RPEQ 19358) e [email protected] w www.barlowshelley.com.au
STORMWATER OUTLET DETAIL PLAN SW30 E
CL
This drawing is not to be copied or amended without written permission from a PO Box 899, Maroochydore,4558 SHEET 4 OF 4 [STRUCTURE 1/19]
DATE 13-09-19 Barlow Shelley Consulting Engineers
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.