Attachment 2 - Construction and Tree Management Plan · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
3.6 MANAGEMENT PLAN STRUCTURE
This Construction and Tree Management Plan outlines a comprehensive approach to the construction and development
of the proposed RACV project, prioritizing the preservation of the site's natural environment, minimizing ecological impact
and protecting individual trees of value as required by the development approval.
The report is a collaborative effort between Aspect Architects & Project Managers and Consult Arborist, incorporating
expertise from various disciplines, including ecology, arboriculture, construction management, and engineering.
Gondwana Ecology Group have provided a review from an ecological perspective, and MRP Hydraulic and Fire services
Consultants have provided information on the proposed construction methodology for the provision of water, sewer and
fire services.
Key strategies include careful site planning, staged construction, specialised construction techniques and the
implementation of stringent environmental protection measures. By staging the construction into three phases, and
facilitating the use of smaller, less disruptive construction equipment and construction works, the overall impact on the
site will be reduced considerably. In addition, this staged process with smaller construction areas and specialised building
techniques allows for better onsite environmental controls.
The project works have been separated into (1) PRE-CONSTRCTION, (2) CONSTRUCTION, and (3) POST
CONSTRUCTION. A series of ONGOING TASKS (i.e. to ensure compliance and tree protection) occurs throughout all
three stages.
PRE-CONSTRUCTION
Tree Protection Measures
Construction Contract
Collaboration and Education
Site Readiness
Site Set-up and Preparation
CONSTRUCTION
Overall Project Construction Sequencing/Stage of Works
Cabin Construction Methodology
POST- CONSTRUCTION
Site Demobilisation
Rehabilitation and Landscaping
Post Construction Arborist Report
Hand-Over Documentation
The ONGOING TASKS include:
Collaboration
Construction and Tree Management Plan - REV03 Page 8 of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2 - Construction and Tree Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.