Council archive · source document
Attachment 2 - Construction and Tree Management Plan · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
4.6 PRE-CONSTRUCTION
4.1. Tree Protection Measures
A site survey and the site configuration, with an assessment of the trees have been undertaken including the
trees which require further consideration as explained under the updated Arborist Tree Retention Review by
Consult Arborist dated 24 November 2025, Version 11.
The information in this report and associated attachments form the basis of the Tree Protection Procedures and
can be used in conjunction with guidelines laid out in the Australian Standard, AS4970–2009 Protection of Trees
on Development Sites, industry best practices and experiences from the Project Arborist.
Refer to procedures in ATTACHMENT C.
4.2. Construction Contract
Construction Contract: The final approved Construction and Tree Management Plan will form part of the
Conditions of Contract between RACV and the Principal Contractor, requiring the Principal Contractor to comply
with all aspects of the Management Plan. The Principal Contractor will be supervised by RACVs Project
Manager to closely monitor and review work on site progressively throughout the contraction phase.
Contractual penalties will apply and be used where necessary to ensure compliance.
Dilapidation Report: The Principal Contractor will be required to complete a detailed dilapidation report prior to
commencing work on site to comprehensively photograph and catalogue every aspect of the site to be retained
and protected, as well as the immediate zones surrounding the site, this report will be referenced throughout the
construction phase to ensure compliance with every aspect of the Management Plan.
4.3. Collaboration and Education
A collaborative approach between all involved parties is central to the overall success of this proposed project.
Collaboration and Education of the entire project construction team prior to site commencement:
A pre-construction meeting facilitated by the Project Manager will be held with all relevant parties, including
the project arborist, project ecologist, main contractor, and architect, to discuss the project plan and identify
potential challenges. This will include a review of the conditions of approval and the expert reports to
assess existing conditions, potential hazards, and optimization opportunities, ultimately establishing safe
and efficient access routes that minimize environmental disturbance.
Regular meetings are to be facilitated by the Project Manager involving the architect, contractor, and
project arborist - these will be held to ensure all aspects of site readiness are carefully considered and
implemented with minimal impact on the retained trees.
Site Inductions:
ALL workforces on the site are to understand site priorities and be made aware of the Construction and
Tree Management Plan prior to commencing work.
All vegetation tree identification methods and examples will be explained and demonstrated to the project
construction team, ensuring specific site knowledge.
Site orientation for all personnel prior to working on the project.
This education and collaboration are to be ongoing for the duration of all works on site:
This approach will continue into the Construction and Post-Construction stages with educational briefings
to all who attend site – it will be the contractor's responsibility to ensure this is included in all site inductions.
Construction and Tree Management Plan - REV03 Page of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 2 - Construction and Tree Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 9.9 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.