Noosa Shire Council 2019 - 20 Annual Report
Corporate Plan - Theme 2: The Noosa Community • Construction on Stage 3 of the Rufous Street Peregian development commenced with the new
carpark completed in time for Christmas. While the collapse of the primary contractor caused a
Key achievements as we work towards our long term goal include: delay, Council remained committed to the project and completed the detailed design of the new
community house in preparation for a new tender for construction in mid-2020.
Specific Operational Plan Priorities
• The redevelopment of the Noosa North Shore Beach Campground was completed providing
• Council continued implementation of Council’s Social Strategy including the Cultural Plan, Sport additional powered and unpowered sites, improved toilet amenities and a new camp kitchen.
and Active Recreation Plan and Health and Wellbeing Plan. Council completed a review of the • Council completed replacement of the old Noosa Botanic Gardens Shade House built in the 1980s
Cultural Plan’s 2019 Action Plan, which demonstrated 85% of the actions were completed or with a new $400,000 Shade Garden jointly funded by Council and Seqwater. The shade garden is
well underway. Council also endorsed a 2020/21 Action Plan to progress implementation of the home to a large variety of shade-loving rare and exotic plants.
Cultural Plan.
Other Initiatives to enable Council to achieve its goal for this theme
• Council supported residents through the 2019 bushfires in Peregian, Cooroibah and Noosa North
Shore. This included running evacuation centres (up to six at one stage), providing emergency
relief and supporting the community with clean-up and recovery afterwards including maintaining
Recovery Hubs at Peregian and Noosaville.
• Council supported the community through the 2020 Coronavirus Covid -19 pandemic. Key
measures included increasing health and hygiene measures in public spaces, providing Covid-
safe information and advice to businesses and community organisations and supporting social
service organisations with the delivery of emergency relief such as food supply, clothing, funding,
accommodation, hygiene products, free flu vaccinations, laundry facilities and hot showers.
• Over 65,000 people engaged in arts and cultural activities through Floating Land 2019. The festival
included 21 projects and 38 associated events outside of non-traditional venues, with several
community collaboration activities that included First Nations’ artists.
• Council continues to collaborate and partner with Kabi Kabi Traditional Custodians on a range of
initiatives. A highlight included working with members of the Kabi Kabi Crowe family to produce
two short films; Place of Crowes and Tewantin’s Oyster Feasts. The films are available online and
were distributed to all local schools. They are regularly viewed and utilised in local education
programs.
• Regional sporting events were supported through Council’s community development team
including hosting the Pakistan and West Indies Women T20 World Cup cricket teams for warm-up
games, training and community engagement activities.
• The Seniors Health and Wellbeing Program (Ageing Well Noosa) commenced across the Shire. The
• A major refurbishment of the Noosa Aquatic Centre was completed following a short closure.
program provides low-cost exercise classes for seniors to improve balance, strength and mobility
The refurbishment included replacing the roof, timber decking and completing major pool
and provide opportunities for older people to meet new people.
maintenance such as tiling and re-grouting.
• Children from prep to year 6 participated in Council’s Walking Wheeling Wednesdays program
• Council adopted a Community Health and Wellbeing Plan and 12-month implementation plan.
which promotes walking and riding to school. The initiative helps keep kids active, while reducing
• The first stage of the pre-feasibility study for a Regional Art Gallery was completed. This
traffic congestion.
stage reviewed the existing Galleries’ strengths and weaknesses and engaged a consultant to
• Digital education opportunities were provided to increase critical skills such as the Library and
investigate the needs, opportunities and priorities of a possible new Gallery. This study will be
Digital Hubs ‘Fly for Good’ program which provided local high school girls learning in drone use
complete by early 2021.
and application to solve critical problems
• Council has investigated contemporary options for outreach library services to replace the
• A motion led by Noosa Council in tandem with Cherbourg Aboriginal Shire Council at the Local
existing Mobile Library which is reaching the end of useful life. It is expected that the new service
Government Association of Queensland (LGAQ ) annual conference helped gain the support of
model will be fully implemented by late 2021.
Queensland local governments to endorse the Uluru Statement from the Heart and advocate for
• Master Plans for the Noosa District Sports Complex and the Cooroy Sports Complex were
the constitutional recognition of First Nations peoples.
adopted by Council and implementation plans commenced including the preliminary civil works
• Council continues to support and focus on recognising the important work of volunteers in our
design for the Noosa District Sports Complex.
community. A ‘volunteer recognition’ event was hosted by Council and a promotional video was
developed for our Noosa service clubs.
Page 20 Page 21
Preview the original
The page text is free to read. Previews and downloads of original files need an account.
Log in to previewLog in to download the original (Annual Report 2019-20(PDF, 7MB).pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.