Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074
Plans and drawings: the text below has words only, no drawings.
Very large file (10.9 MB): may take a few minutes to open.
ADG Consulting Pty Ltd
1 Introduction
ADG Consulting Pty Ltd (ADG) was engaged by Seymour Group to prepare a Dewatering Management
Plan (DMP) for the proposed residential apartment development within property described as Lot 0 on
BUP10936, 7 Noosa Parade, Noosa Heads, Queensland.
1.1 Proposed development
It is understood the proposed development will comprise a two‐storey building over a single‐level in‐
ground basement, extending across the 1,120 m2 site.
Based on information provided by Seymour Group, existing ground levels across the proposed basement
footprint are approximately RL 2.1 m Australian Height Datum (AHD). Excavations to facilitate the
basement construction are proposed to extend to an approximate depth of 2.8 m below existing ground
level (bgl), corresponding to an approximate elevation of RL ‐1.1 mAHD (i.e. finished basement floor level
of RL ‐0.7 mAHD; allowing for 400 mm raft slab and blinding layer). Localised deeper excavations may be
required to facilitate other structural elements (i.e. lift overrun pit, pile caps and footings), where
required.
During a geotechnical and acid sulfate soil investigation on the site in January 2025, no groundwater was
recorded in the drilling of boreholes to the depth of 4.5 mgbl (PTG Consulting, 2025). PTG noted that
groundwater levels are expected to fluctuate in response to variations in rainfall and are likely to rise
close to the ground surface during periods of heavy or prolonged rainfall. No further recent data has been
supplied for review in preparing this DMP, however based on ADG’s experience on nearby sites in the
locality in recent years, it is anticipated that groundwater should be expected at or around 0.5 m AHD +/‐
0.5 m, depending on tidal and seasonal rainfall conditions. Dewatering will therefore be necessary to
allow the basement and other structural elements to be constructed in dry conditions.
1.2 Relevant guidelines
The DMP was prepared with reference to the following documents:
Australian and New Zealand Guidelines for Fresh and Marine Water Quality 2018. Australian and
New Zealand Governments and Australian state and territory governments, Canberra ACT, Australia
(ANZG, 2018), which supersedes Australian and New Zealand Guidelines for Fresh and Marine Water
Quality, Australian and New Zealand Environment and Conservation Council and Agriculture and
Resource Management Council of Australia and New Zealand (ANZECC/ARMCANZ). 2000.
Environmental Protection (Water & Wetland Biodiversity) Policy 2019. Queensland Government.
2019.
Guidelines for Managing Risks in Recreational Water. Australian Government, National Health and
Medical Research Council (NHMRC). 2008.
Monitoring and Sampling Manual 2018, Version 2 June 2018. Department of Environment and
Science (DES). 2018.
Noosa River environmental values and water quality objectives. Department of Environment and
Science (DES). 2022.
National Environment Protection (Assessment of Site Contamination) Measure 1999, (as amended
May 2013). National Environment Protection Council (NEPC). 2013.
Queensland Water Quality Guidelines 2009, Version 3. The Department of Environment and
Heritage Protection (DEHP). 2013.
ADG1777.25 Dewatering Management Plan_Rev0_01.05.25 Page 1
Document Set ID: 23735664
Version: 1, Version Date: 12/05/2025
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074Related documentApplication case desk ↗
Reference Document - Dewatering Management Plan (For Stamping) MCU25/0053 & OPW25/0074Related documentApplication case desk ↗
About this file
- File size
- 10.9 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.