- Place the rootball on a firmed base to achieve required FSL. Turf as specified
- Thoroughly water the root ball immediately after planting.
- Number of stakes will vary with pot size. Refer plant schedule. Topsoil
- Cultivate sides of excavated hole 50mm. - to 100mm depth
Notes: FSL
(X)
Cultivate subgrade - All timber to be CCA pressure treated to
- to 150mm depth AS1604, Hazard 5, rough sawn pine. Timber edge
Existing subgrade - All timber edges to be arissed to comply
with council standards.
- All timber ends to have one coat of Stakes
Cuprinol or equal prior to installation.
Hardwood Stake: - Stakes to be 400mm into ground at max.
25x25x90mm Place 600mm
into the ground. Do not
2 TURF PROFILE 1200mm centres, or as required to obtain
smooth curves. Top of stake to finish
Existing/compacted
/subgrade/subase
CD-200 1:5@A1, 1:10@A3
place through rootball. 20mm below top of timber edge. Where Notes:
Secure with ties by looping timber edges meet at corners provide Angle and space pavers as indicated on working drawing.
in a figure eight pattern. double stakes. If not specified space equally as shown on drawings.
Mulch: Pull away from - All fixings to be hot dipped galv.
FSL Concrete haunch to all edges.
base of plant. - Leading edge is to be free of burrs and
Ensure top of haunch is min.
Mulch splinters.
20mm below surface level.
Form an earthen basin - to 100mm depth
around base of plant. Finished mulch level.
Soil blend or site topsoil TIMBER EDGE STAKES (X) = Height above Refer to plan for type.
- to 300mm depth 38 50 finished surface level FIXINGS
typ. 100
20
50mm Bugle Headed
Topsoil blend FLUSH
Batten Screws.
Fertiliser: Do not allow
100
20mm 75mm Bugle Headed
30
Cultivated subgrade
100
contact with roots.
- to 150mm depth Batten Screws.
100mm
100mm Bugle Headed
Water retention additive 150mm Batten screws.
100x38mm Wet mortar bed 30-50mm
100mm deep compacted sub
50x50mm base: CBR 45 compacted to 95%
standard compaction.
1 140-300mm PLANTING 3 GARDEN BED PROFILE 4 EDGE TYPE 1 5 CONCRETE STEPPERS
CD-200 1:10@A1, 1:20@A3 CD-200 1:10@A1, 1:20@A3 CD-200 1:5@A1, 1:10@A3 CD-200 1:10@A1, 1:20@A3
Timber garden edge Steppers through garden
MATERIALS & FINISHES SCHEDULE
CODE / ITEM REQUIREMENTS
Notes:
- Place the rootball on a firm base.
- Thoroughly water the root ball immediately after planting. Garden Edge Type 1 100x38mm Treated pine garden edging surround with 500x38x38mm treated pine pegs at
- Cultivate sides of excavated hole 50mm deep. (EG-1) Nom.1200mm centres. Refer to detail for installation
- Do not disturb kerb, road pavement or road side drainage works.
- Tease out roots on side of rootball when planting. Paving Type (P1) Adbri Masonry 400 x 600mm concrete paver. Colour 'Zurich' to be installed as per detail. Surround
pavers with 20-40mm dia 'Roma' pebble from Doonan sand and gravel, laid 75-100mm thick.
- Ensure top of rootball is not buried; expose and set flush with finished level.
Turf Type 1 (T1) A-Grade 'Empire' Zoysia. Laid as per detail shown on CD-901
Turf Type 2 (T2) A-Grade 'Couch' Wintergreen. Laid as per detail shown on CD-901
Garden Bed Type 1 (GB1) Internal grade typical, 300mm depth amended site or imported topsoil to specification. Apply
Nutri-Tech Solutions, 'Life Force Gold' and 'Life Force Carbon' to all garden beds and water in all
plants with 'SeaChange KFF' cover with 100mm thick Organic 25mm Hoop Pine Mulch, refer to detail
CD-901
Hardwood stake: Place 600mm
into the ground. Do not place
through rootball. Secure with
ties by looping in a figure eight
pattern.
Raise plant 50mm above
finished surface level.
Mulch: Pull away from base
of plant.
Form an earthen basin
around base of plant.
Topsoil blend
min 300
Water retention additive
Fertiliser: Do not allow 1
fertiliser to come in 1
contact with roots.
width (w)
10 - 20mm Drainage gravel
2xw
6 45-200ltr PLANTING
CD-200 1:10@A1, 1:20@A3
Revision Date Amendment Drawn Checked
APPROVAL ONLY
CONSTRUCTION DETAILS NOT FOR CONSTRUCTION
A
B
C
14/02/2020
2020.02.24
2020.02.25
For Discussion
Amendment - For Tender
OPW / For Tender
AL/PS
PS
PS
CS
AL
AL
CD-200 scale as noted
24 MOORINDIL STREET, TEWANTIN
JOB NUMBER: 20024 CLIENT NAME: Thynne Property Trust
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Futher RFI -Attachment H - Concept Landscape Plans (Updated Revision F).pdfRelated documentApplication case desk ↗
About this file
- File size
- 972 KB (small file)
- File type
No other editions are linked here.