4. STORMWATER QUALITY
The following sections discuss the stormwater quality considerations for the construction
and operational phase of the development. Refer to Appendix A Proposed Development
Plans for the proposed stormwater drainage layout plan.
4. 1. C O N S T R U C T I O N P H A S E
4.1.1 Erosion and Sediment Control Measures
During construction, it is necessary to manage stormwater run-off to avoid potential
contamination of downstream waterways from sediments and other pollutants from the site.
Best practice erosion and sediment controls shall be installed to minimise the discharge of
potential contaminants from the site, in accordance with the objectives of Appendix 2 of the
SPP (DERM, July 2017) shown below in Figure 4.1.
Figure 4.1 SPP 2017 Construction Phase Stormwater Management Design Objectives
Appendix A (Proposed Development Plans) contains the site-specific erosion and sediment
control (ESC) Plan prepared for the development. The measures proposed for the site
include:
Page 11 of 33
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU21.0117 OPW21.0199-Att 5 Stormwater.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.