MCU21.0117 OPW21.0199-Att 5 Stormwater · MCU21/0117
stormwater into the legal point of discharge on Pearl Street at a maximum rate of
64L/s from the development.
By implementing the proposed stormwater treatments, the development will reduce
the quantity of stormwater pollutants by more than 90% of gross pollutants, 80% of
total suspended solids, 60% total phosphorous and 45% total nitrogen, exceeding
the pollutant reduction targets required for the site.
• By implementing the proposed stormwater solution, it is considered that stormwater
layout proposed will minimise any adverse impacts to the downstream environment
and neighbouring properties arising from the stormwater run-off while also meeting
the stormwater quality targets required for the development.
Page 21 of 33
P +61 7 5211 1003 A 37 Mary St, Noosaville Qld 4566 E [email protected] recorconsulting.com
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
MCU21.0117 OPW21.0199-Att 5 Stormwater.pdfRelated documentApplication case desk ↗
About this file
- File size
- 5.1 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.