Council archive · source document
Decision Notice - 010.2007.00002031.002 [As Published] · 142007.2031.02
Form 6 - Decision Notice
INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION
File No: 2007/2031 Date of Decision: 12 December 2007
1. APPLICANT DETAILS
Name: Henjo Investments Pty Ltd & Karen McDonagh Investments Pty Ltd
Postal address: CARE Tod Noosa Pty Ltd
PO Box 233
NOOSA HEADS QLD 4567
Phone no: 5449 9600 Fax no: 5449 9494
2. PROPERTY DESCRIPTION
Street address: 28 Headland Drive NOOSAVILLE, 26 Headland Drive NOOSAVILLE
Real property LOT: 1 RP: 137140, LOT: 2 RP: 137140
description:
3. OWNER DETAILS
Name: Henjo Investments Pty Ltd & Karen McDonagh Investments Pty Ltd
Postal address: PO Box 1665
BONDI JUNCTION NSW 1355
4. REFERRAL AGENCIES
Referral Agency Address Basis
NIL
5. APPLICATION TYPE
Development Development Details Preliminary Development
Approval Permit
Operational Works In accordance with Engineering No Yes
drawings Nos.
07562-1A dated September 2007 by
TOD Noosa
07562-2A dated September 2007 by
TOD Noosa
07562-4A dated September 2007 by
TOD Noosa
or as modified herein.
6. DECISION DETAILS
Council decided to approve this application on 12 December 2007, subject to conditions.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 8 pages
Page 2
NOOSA COUNCIL IDAS Development Application Decision Notice 2 of 9 7. APPLICABLE CODES The developer must comply with the following codes for self-assessable development related to the development approved under this Development Permit:- N/A. 8. CONDITIONS The approval is subject to conditions. Noosa Council’s conditions are attached. 9. FURTHER DEVELOPMENT PERMITS REQUIRED Type of Development Permit required Subject of the required Development Permit N/A 10. RIGHTS OF APPEAL Rights of appeal in relation to this application are attached. 11. ASSESSMENT MANAGER Name: Noosa Council Signature: Date: NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 3
NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 9
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
1. The development shall be carried out in accordance with Engineering drawings Nos.
07562-1A dated September 2007 by TOD Noosa
07562-2A dated September 2007 by TOD Noosa
07562-4A dated September 2007 by TOD Noosa
or as modified herein.
2. The Traffic Management Plan described in condition 20 of the Decision Notice File No: 2006/2241 dated
19 March 2007 shall be submitted to and approved by Council prior to the pre start meeting.
3. Suitable sediment control devices ("in pit” pollution control devices) shall be temporarily installed into the
first existing external downstream stormwater structure. In this regard the “filter tube” indicated on drawing
No: 07562-4A dated September 2007 by TOD Noosa shall be deleted and replaced with “in pit” devices.
These devices are to be checked and cleaned on a regular basis and specifically after each rain event.
These devices are to remain in place during the civil works and construction phases of the development.
The location and type of device to be installed shall be established at the “pre start” meeting with
Council’s Construction Technical Officer and shall be installed prior to the commencement of any works.
4. Council’s Construction Technical Officer (ph 0410 512 505), shall be given seven (7) days’ notice of
intention to commence works to arrange a “pre start” meeting regarding the civil works.
5. The principal contractor must have all the appropriate insurance and public liability documentation to carry
out the works. The principal contractor is also responsible to ensure that any sub contractors also have
the appropriate insurance and public liability documentation.
6. Prior to the “pre start” meeting, the principal contractor must be provided with a copy of Council’s
signed approved drawings and conditions by the applicant.
7. The Consulting Engineers for the project shall be currently Registered Professional Engineers of
Queensland (RPEQ). The consulting engineers are responsible for arranging all inspections, with
Council’s Construction Technical Officer or nominated staff.
8. Prior to works commencing, Council is to be advised of the Engineer (RPEQ) supervising the project.
(This person will be the contact for the project).
9. Council standards shall apply to these works unless otherwise modified herein.
10. The person acting on this permit shall ensure that its consultants and contractors take all reasonable care
during the construction of the engineering works to ensure that Council property, road pavements or
facilities (such as underground drainage, water supply, sewerage, footpaths, kerbing, landscaping, street
furniture etc.) are protected against any damage or interference whatsoever.
If any Council property or facilities should be damaged by the Applicant or any of its Consultants or
Contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the Applicant and/or its Contractors shall forthwith notify the Manager Land
Development and shall forthwith rectify the damage to that property or facility at its cost and to the
satisfaction of the Manager Land Development.
All rectification works are to be completed prior to the sealing of the survey plan or, alternatively, the
Applicant may request the Council to carry out the rectification work at the Applicant’s cost, such cost
being paid by the Applicant to the Council prior to the sealing of the survey plan.
In the case of any emergency the Council shall be entitled to rectify such damage at the cost of the
Applicant, such cost being paid prior to the sealing of the survey plan.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 4
NOOSA COUNCIL IDAS Development Application Decision Notice 4 of 9
11. The development of the site shall be carried out in such a manner as to prevent dust and/or sand
nuisance to residents and/or tenants in the vicinity of the development.
12. Construction work and other associated activities are permitted only during the hours of 7.00 am and 6.00
pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Manager-Land Development or his nominee.
13. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Traffic Infrastructure (Roads) Act.
14. Safe pedestrian access on Headland Drive and Eumundi Noosa Road shall be maintained at all times.
Should footpath / road closures be necessary to carry out construction works, Council’s Construction
Technical Officer (ph 0410 512 505) must be notified prior to the proposed closure.
15. Sediment and erosion control measures must be in place prior to works commencing. If such measures
are not in place or are not satisfactory, “on the spot “fines may be issued. Such fines can be issued if
sediments from the site are found to enter or have the potential to enter Council’s stormwater system or
natural waterways. Although the sediment and erosion control measures have been approved on drawing
No 07562-4A dated September 2007 by TOD Noosa, Council’s Manager – Land Development may
request further controls to be installed should approved measures be inefficient.
16. Certification of the completed works must be provided to Council by the supervising engineer.
17. These works are also to be in compliance with the relevant conditions of Development Permit No.
2006/2241.
18. Pursuant to Section 3.5.21(5) of the Integrated Planning Act 1997, the Relevant Period is two (2) years
from the day this permit takes effect (until 17 December 2009) during which time all conditions must have
been complied with and the Plan of Survey lodged with the Council for endorsement.
19. Notwithstanding that Council has checked the plans with due care, where it is found during construction
that variations from Council's standards exist, then Council standards shall apply.
Water and Sewerage
The water & sewerage plans listed below are satisfactory:
07562-2A – Sewer Reticulation and Water Supply Plan
07562-3A – Sewer Longitudinal Section and Notes
This Decision Notice is issued subject to and conditional upon the relevant Approved Development
Permit having been granted to the applicant.
20. A copy of the job specification is to be provided to Council’s Inspector within seven (7) days of the date of
this Decision Notice, and prior to commencement of works.
21. The names of any proposed contractors for works are to be submitted in writing, together with copies of
current Public Liability and Workers Compensation Insurances together with certificates of currency for
those policies, for consideration by the Assessment Manager seven (7) days prior to pre-start meetings
and commencement of works.
A separate letter will then be issued approving the contractor (or otherwise) for the works. No other
contractor or subcontractor shall be engaged to carry out the works or any part of the works without the
written approval of the Assessment Manager.
22. Council’s Water & Sewerage Inspector shall be given (7) days notice of intention to commence works. A
pre-start meeting shall be arranged prior to commencement of works by contacting Council’s Water &
Sewerage Inspector, Mr Trevor Mourilyan, Ph. 0417 780 830. Inspector is only available for pre-start
meetings, inspections and testing etc. between the hours of 6:30am to 4:00pm, Monday to Friday.
Inspector will not be available outside these hours unless prior approval is obtained from the Water &
Sewerage Capital Works Manager with any costs incurred by Council outside the hours nominated above,
met by the Contractor/Developer. These costs will be in addition to normal inspection fees.
23. Notwithstanding that Council has checked the plans with due care, where it is found during construction
that variations exist with Council's standards, Council standards shall apply.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 5
NOOSA COUNCIL IDAS Development Application Decision Notice 5 of 9
24. It is the responsibility of the applicant to ensure that its consultants and contractors take all reasonable
care during the construction of the engineering works to ensure that Council property or facilities (such as
underground drainage, water supply and sewerage) are protected against any damage or interference
whatsoever.
25. If any Council property or facilities should be damaged by the applicant or any of its consultants or
contractors through any cause whatsoever in the course of, directly or indirectly, carrying out the
engineering works, the applicant and/or its contractors shall forthwith notify the Assessment Manager and
shall forthwith rectify the damage to that property or facility at its cost to the satisfaction of the Assessment
Manager prior to the sealing of the survey plan and/or acceptance of the works on-maintenance.
Alternatively, the applicant may request the Council to carry out the rectification work at the applicant's
cost, such cost being paid by the applicant to the Council prior to the sealing of the survey plan and/or
acceptance of the works 'on maintenance' provided that in the case of emergency, the Council shall be
entitled to rectify such damage at the cost of the applicant such cost being paid prior to the sealing of the
survey plan and/or acceptance of the work 'on maintenance'.
26. The Contractor shall make all necessary arrangements for supply of water required for construction works.
The use of hydrant standpipes on Council mains will NOT be permitted. Contractors should contact
Council’s Water Section on phone 5449 5254 to obtain an application form for issue of a key to access
Council’s water tanker filling stations. Conditions of access and location of filling stations are detailed on
the application form.
27. All connections to existing live water mains are to be carried out by Noosa Council at completion of
construction of internal works.
28. All sewerage reticulation mains are to be inspected by closed circuit television (CCTV) prior to acceptance
'on maintenance'.
CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council following
satisfactory completion of construction works. The developer will be responsible for the full cost of CCTV
inspection, including any additional inspection necessary following defect identification and rectification.
This charge is payable prior to commencement of works and will be determined on the unit rate basis
current at the time of approval.
29. All signage, including that for safety during construction shall be in accordance with the Manual of Uniform
Traffic Control Devices and Main Roads Department Roadworks Signing Guide.
30. As Constructed drawings in both hardcopy and digital format (ADAC) produced in GDA94 Zone 56
coordinate value to the standards and requirements of the Assessment Manager are required for Council
records. Such 'as constructed' drawings will be required prior to works being accepted "on maintenance",
where applicable. Requirements for "as constructed" information are detailed in the current version of
Council's Engineering Design Standards (Water & Sewerage) Manual.
Release of plans of survey and/or acceptance of the works on-maintenance will not be considered until
lodgement of satisfactory 'as constructed' records.
Please note that bonding of outstanding works will not be considered by Council.
31. TOD Group, as Consulting Engineers for the project, are responsible for arranging all inspections and
ensuring that all relevant details required by Council are supplied. The attached Water and Sewerage
Inspection Report form is to be kept by you and presented to Council's Inspector at each stage of the
development requiring a meeting or inspection. The Inspector will sign the form at each stage when
conditions have been satisfied. The works will be accepted 'on maintenance' when this form, signed by
the Inspector for each stage, is returned with a letter requesting that it go 'on maintenance'.
32. It is Council policy that a maintenance bond be imposed on construction works during the maintenance
period. The maintenance bond shall be 5% of the agreed value of the development obligations, or $1,500
whichever is the greater amount. This bond must be lodged by (and shall only be accepted from) the
Developer for the works.
33. Construction work and other associated activities are permitted only during the hours of 7:00am and
6:00pm Monday to Saturday. No work is permitted on Sundays or public holidays, except where extended
hours are approved by the Assessment Manager or his nominee.
34. Cut-ins to existing live sewer are to be performed by Approved Contractor. Noosa Council Works
Inspector shall be present during any work on live sewer undertaken by contractor. An additional fee of
$160.00 (included below) is required to cover costs associated with these live sewer works.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 6
NOOSA COUNCIL IDAS Development Application Decision Notice 6 of 9
35. Fees applicable to the above project are listed below.
Plan Examination $ 930 PAID 05/10/07
Inspection Fee $ 810 RN 342304
Checking as-constructed data $ 135.00
CCTV fee $ 114.75
Live sewer inspection $ 160.00
BALANCE OWING $ NIL
36. All water connection fees are to be paid prior to the pre-start meeting. Costs to be advised.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 7
NOOSA COUNCIL IDAS Development Application Decision Notice 7 of 9
Local Laws, Policies & State
Regulation Requirements
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
CONDITIONS OF APPROVAL
1. Should any changes or modifications to the approved plans be required as a result of construction
constraints, a Change to an Existing Approval Application under the Integrated Planning Act must be made.
Amended plans clearly indicating the changes must be lodged with this application along with the
appropriate fees.
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 8
NOOSA COUNCIL IDAS Development Application Decision Notice 8 of 9
Appeal Rights
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
The following is an extract from the Integrated (6) If an application involves assessment against
Planning Act (Chapter 4). a concurrence agency code, appeal rights for
submitters for the application are not available
Division 8 - Appeals to court relating to against the part of the approval that represents the
development applications concurrence agency’s response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application 4.1.29.(1) An advice agency may, within the limits of
may appeal to the court against any of the following- its jurisdiction, appeal to the court about the giving of
(a) the refusal, or the refusal in part, of a a development approval for a development
development application; application if-
(b) a matter stated in a development approval, (a) the development application involves impact
including any condition applying to the assessment; and
development, and the identification of a code (b) the advice agency told the applicant and the
1
under section 3.1.6; assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a currency period; days after the day the decision notice or negotiated
decision notice is given to the advice agency as a
(e) a deemed refusal. submitter.
(2) An appeal under subsection (1)(a) to (d) must Appeals for matters arising after approval given
be started within 20 business days (the “applicant’s (co-respondents)
appeal period”) after the day the decision notice or
negotiated decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
development application, a person to whom any of
(3) An appeal under subsection (1)(e) may be the following notices have been given may appeal to
started at any time after the last day a decision on the the court against the decision in the notice-
matter should have been made.
(a) a notice giving a decision on a request for
Appeals by submitters extension of the currency period for an approval;
4.1.28.(1) A submitter for a development application (b) a notice giving a decision on a request to make a
may appeal to the court about- minor change to an approval.
(a) the giving of a development approval, including (2) The appeal must be started within 20 business
any conditions (or lack of conditions) or other days after the day the notice of the decision is given
provisions of the approval; or to the person.
(b) the length of a currency period for the approval. (3) Subsection (1)(a) does not apply if the
approval resulted from a development application
(2) The appeal must be started within 20 business (superseded planning scheme) that was assessed as
days (the “submitters appeal period”) after the day if it were an application under a superseded planning
the decision notice or negotiated decision notice is scheme.
given to the submitter.
(4) Also, a person who has made a request
(3) If a person withdraws a submission before the mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the against a deemed refusal of the request.
decision.
(5) An appeal under subsection (4) may be
(4) If an application involves both impact started at any time after the last day the decision on
assessment and code assessment, appeal rights for the matter should have been made.
submitters are available only for the part of the
application involving impact assessment. Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the (no co-respondents)
application are available only for the aspects of the
development that would have required public 4.1.31.(1) A person to whom any of the following
notification under the repealed Act. notices have been given may appeal to the court
against the decision in the notice-
(a) a notice giving a decision on a request to change
or cancel a condition of a development approval.
1
Section 3.1.6 (Preliminary approval may override local planning
instrument)
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Page 9
NOOSA COUNCIL IDAS Development Application Decision Notice 9 of 9
2
(b) a notice under section 6.1.44 giving a decision to
change or cancel a condition of a development
approval.
(2) The appeal must be started within 20 business
days after the day the notice of the decision is given
to the person.
(3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.
(4) An appeal under subsection (3) may be
started at any time after the last day the decision on
the matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
(3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to the
court against the decision or the conditions applied.
(2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.
2
Section 6.1.44 (Conditions may be changed or cancelled by
assessment manager or concurrence agency in certain
circumstances)
NSC c:\docume~1\rhr\locals~1\temp\bcl technologies\easypdf 5\@bcl@e40c7ff4\@[email protected]
Used in these records