Annex 8 - Safety in Design Report V1

Attached to the e-mail DA Application - Noosa Oyster Project (2 of 3).

of 13

Page text shows just the words. Original shows the document exactly as it was published.

  RISK IDENTIFICATION                     RISK ASSESSMENT                          RISK EVALUATION                                                                RISK TREATMENT                                              RESIDUAL RISK EVALUATION


        Risk Name                    Causes                Consequences                                                                      Controls to be implemented to reduce risk                             Control
                                                                                                                                                                                                                   Owner




                                                                                                                                                                                                                                                                         Accepted / Not
                                                                                Consequence




                                                                                                                                                                                                                              Consequence




                                                                                                                                                                                                                                                         Residual Risk
                                                                                              Likelihood




                                                                                                                                                                                                                                            Likelihood
                                                                                                           Risk
                                                                                                                   Notice to Mariners / Updated Chart to be issued for the works by MSQ.                        Owner /
                                                                                                                   Monitoring and maintenance of the structure in line with ICM Drawings and Project            TNC
                                                                                                                    Implementation Plan.
                                                                                                                   Issue public information locally to advise of site locations and hazards.
Displacement of rock from     Unstable rock placement     Damage to                                              Suitable rock size to be determined based on site conditions and design event.               Designer
restoration substrate         Undersized rock material     restoration reef




                                                                                                                                                                                                                                                                         Accepted
                              Wave impact                 Impacts to
                                                            access between




                                                                                                           M
                                                                                              C




                                                                                                                                                                                                                                            E
                                                                                2




                                                                                                                                                                                                                              2




                                                                                                                                                                                                                                                         L
                              Excessive water                                                                     Contractor to install appropriate rock size within tolerances as specific in the design      Contractor
                                                            and around                                              specifications.
                               currents                     restoration
                                                            footprint
Erosion adjacent to           Excessive water             Injury                                                 Periodic monitoring and maintenance of the structure in line with ICM Drawings and Project   Owner /
restoration footprints         currents                     (collapsing                                             Implementation Plan.                                                                         TNC
                              Wave impacts                 vegetation/steep
                                                            steps in riverbed
                                                            profile)




                                                                                                                                                                                                                                                                         Accepted
                                                           Damage to




                                                                                                                                                                                                                                                         M
                                                                                              C


                                                                                                           H




                                                                                                                                                                                                                                            D
                                                                                4




                                                                                                                                                                                                                              4
                                                            restoration reef
                                                           Impacts to
                                                            access between
                                                            and around
                                                            restoration
                                                            footprint
                                                                                                           MAINTENANCE, UPGRADE OR REMOVAL

Risks as outlined in                                                                                               As per above
Construction Phase (above)




                                                                                                                                                                                                                                                                                    11
Log in to download the original file

Annex 8 - Safety in Design Report V1.pdf · 769 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.