Skip to the record
The first. The best. The only NoosaWatch™.

Original source · versioned page text

Geotechnical Investigation

of 48

Page text shows just the words. Original shows the document exactly as it was published.

                                PROPOSED CALILE HOTEL NOOSA DEVELOPMENT
                                3 – 7 SERENITY CLOSE, NOOSA HEADS

The advice of a specialist shoring contractor must be sought regarding feasibility, design and installation of
the proposed retention and subsurface drainage system. It will be necessary to conduct numerical analysis
to optimise the retention system. Detailed design will also need to account for relevant factors of safety to
maintain the temporary and long-term stability of the retention system.

Retaining structures greater than 1 m high, or those required to support surcharge loads or sloping backfill,
will require engineer design and certification of construction. Retaining wall design should be carried out in
accordance with AS4678-2002 Earth retaining structures.

Design for temporary and permanent retaining structures could be carried out using a trapezoidal (for
propped or anchored walls) pressure distribution applicable to the wall type and based on the parameters
listed in Table 5. These values do not include allowance for hydrostatic pressures nor transient (e.g.
construction) or adjacent footing loadings.
Table 5: Retaining Structure Design Parameters
                                                                     Lateral earth pressure coefficients
                              Unit
                                         Friction
 Retained material           weight
                                         angle (°)            Ka                        Ko
                             (t/m3)                                                                        Kp
                                                       (Cantilever wall)        (Non-yielding wall)


 Very Loose/ Loose
                               1.8           28               0.36                     0.53                2.77
 Sands


 Medium Dense (or
                               1.9           34               0.28                     0.44                3.54
 Denser) Sands


 Future Controlled Fill*        *            *                   *                       *                  *

Note:    * Depends on fill material type and level of compaction.

Retaining structures must be founded as per the recommendations in Section 6.3.2 above, with the footings
also designed to account for lateral loads imposed by the retaining wall. Detailed design must include an
assessment of internal and global stability. A solution using screw piles to support retaining walls, possibly
including raked piles, may be feasible although bending and shear capacities would need to be carefully
checked in design from a soil-structure interaction viewpoint. Additional lateral capacity may be achieved by
incorporating a deeper pile cap that also acts as a shear key attracting passive resistance from the sands in
front of the wall.

6.5       Drainage
Site drainage should be designed to readily remove surface water and to prevent ponding of water on
subgrade areas during construction and also adjacent to foundations and perimeter slabs once construction
is completed.

Although unlikely, if groundwater seepage is encountered during excavations, Tectonic must be notified to
assess the impact on stability.

Subsurface drainage must be installed behind any retaining walls (e.g. slotted ‘aggi’ pipe wrapped in filter
‘sock’ placed in gravel backfill). Depending on matters such as the extent of drainage installed and site-
specific groundwater conditions, the designer must make an assessment of hydrostatic pressure to be
accounted for in the design of the retaining structure. It is assumed that any pool floors will include a
hydrostatic pressure relief valve. The outlet pipe from this valve must be taken to ‘daylight’ at the ground
surface.
All excess stormwater collected around the site (including overflow from rainwater tanks etc.) must be
directed by pipes or lined channels to discharge into the existing stormwater infrastructure (e.g. along
Serenity Close or within the central/southern easements) where possible, or at least 10 m downslope of any
structure or embankment to a legal point of downstream discharge. Stormwater must not be allowed to


7 October 2022
Report No. 22239-001-Rev0                                   18
Log in to download the original file

Geotechnical Investigation.pdf · 7.4 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.