Stormwater Management Plan · MCU15/0122
Attached to the e-mail MCU15/0122 - Response to Information Request - Stormwater Mgmt Plan, Bioretention & Rainwater reuse Email 2 of 3.
Plans and drawings: the text below has words only, no drawings.
Original PDF page 13, section 1. The text section number identifies this passage in the reader.
15099 - SBSMP/3
Page 13
Source node parameters used in the post-development mitigated model are as per the post-
development un-mitigated model documented in Table 5.3.
5.6.4 On-Site Detention
In order for the post-development stormwater discharge conditions to match the pre-
development conditions it is proposed to provide on-site detention in an underground detention
basin to be located within the southern portion of the site. Refer to Appendix C for the
Concept Drainage Plans.
The proposed basin will have the following dimensions:
Basin base area = 38m2;
Maximum basin depth = 2.0m;
Maximum basin volume = 76m3
Discharge orifice 1 diameter = 0.14m;
Discharge orifice 1 centre height = 0.07m
Discharge orifice 2 diameter = 0.15m;
Discharge orifice 2 centre height = 1.1m
Site Based Stormwater Management Plan
Proposed Medical Development at Cnr Val Crescent & Goodchap Street, Noosaville
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Stormwater Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 7.6 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.