response to information request - pomona subdivision 19.11.2021
gravity sewer main. Unity Water have confirmed that if the agreement between JNE
Developments Pty Ltd and Noosa A H & I Society Inc cannot be concluded then Unity
Water will permit low-pressure sewer system as an alternative system. As such we have
revised our preliminary engineering drawings to show the proposed gravity sewer. It
should be noted that this sewer line can be extended in the future to service the
development of lots to the north the subject site.
18. Provide details on the easements proposed to be extinguished, including,
but not limited to:
a. Purpose of the easements;
b. Reason for extinguish them;
c. Benefited party(ies) written agreeing to the extinguishment of these
easements.
Agreement has been granted from the existing property owner to re-direct their
stormwater to the new street - so the stormwater easement (Easement C in lot 21
SP316902) is no longer required.
Easement D in lot 21 SP 316902 is for sewer, Unity Water have confirmed that
Easement D can be extinguished to reflect the new road and lot layout.
----------------------------------------------------------------------------------------------------------------------
Pursuant to the Development Assessment Rules, the applicant has given the assessment
manager the information requested in the information request. Please proceed with the
assessment of the application at your earliest convenience.
If you have any further queries in relation to the above, please do not hesitate to contact
myself.
Regards,
Jack Lewis B.Sc Hons UNSW M.Plan Otago MPIA MQELA
Planner/Director
Pivotal Perspective Pty Ltd
0406 334 227
Page 9 of 9
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.