Infiltration losses from the systems will, almost certainly, exceed the values of 0.02m3/s
to 0.03m3/s required for the basin peak discharges, from the developed site, for the 2
year ARI events, to be reduced to values less than those from the undeveloped site.
When allowance is made for these losses, the basin peak discharges, for all average
recurrence intervals, are less than those from the undeveloped site.
2.6.4 Summary
Significant attenuation of peak discharges from the proposed development is required to
ensure that discharges to the Noosa National Park are not worsened, compared to
those from the current undeveloped site. It is proposed to provide the storage required
to achieve this attenuation in two separate basins located adjacent to the northern
boundary of Lot 6 and the western boundary of Lot 1. The detention basins will be
combined with the bioretention basins required for stormwater runoff quality treatment.
Discharges from the basins will be converted from concentrated to sheet flows by
means of spreader channels constructed within the 10m fire break within the buffer
areas to the national park.
Modelling, using the XP-SWMM package, has demonstrated that satisfactory
attenuation of peak discharges from the development can be achieved.
Blue Care Property Development Unit Version 1.1 24 June 2008
2008 06 24 2383-01 Engineering Report for DA Commercial in Confidence Page 13
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
080624 2383-01 FINAL Engineering Report for DA.pdf [As Published]Related documentApplication case desk ↗
About this file
- File size
- 4.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.