20220218 22 Grant SWMP · MCU22/0172

of 31

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

22 Grant Street, Noosa Heads
20220218


Molti Investments Pty Ltd
Stormwater Management Plan


September 2022
Full text of the other 30 pages

Page 2

Document control record
Document prepared by:

RECOR Pty Ltd
ABN 89 647 469 707
75 Noosa Drive
Noosa Heads, QLD 4567
Australia

T +61 7 5211 1003
E [email protected]
W recorconsulting.com

A person using RECOR documents or data accepts the risk of:
a)     Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard
       copy version.
b)     Using the documents or data for any purpose not agreed to in writing by RECOR.



 Document control

 Report title                      Stormwater Management Plan

 Document code                     20220218-SWMP01                 Project number                   20220218

 File path                         C:\12dS\data\RecorSYN\20220218 22 Grant St, Noosa Heads_652\03 Engineering\02
                                   Reports\20220218 22 Grant SWMP.docx

 Client                                Molti Investments Pty Ltd

 Client contact                    -                               Client reference                 -
 Rev      Date                     Revision details/status         Author          Reviewer         Verifier              Approver
                                                                                                    (if required)

 0        15/09/2022               Initial Version                 BP              JB                                     BP




 Current revision                  0


 Approval

 Author signature                                                  Approver signature




 Name                             B. Parry                         Name                             B. Parry
                                                                                                    RPEQ: 28084

 Title                            Civil Engineer                   Title                            Civil Engineer




                                                                                                                    recorconsulting.com
                                                A 75 Noosa Dr, Noosa Heads Qld 4567                                 E [email protected]
P +61 7 5211 1003

Page 3

Contents
Introduction..........................................................................................................................................4
Site Details ...........................................................................................................................................5
          2.1. Existing Site Description & Drainage .................................................................................................. 5
          2.2. Existing Drainage Patterns .................................................................................................................. 5
          2.3. Proposed Development Drainage Pattern ......................................................................................... 5
          2.4. Flood Considerations ........................................................................................................................... 6

Stormwater Quantity ............................................................................................................................7
          3.1. Pre-Post Comparison .......................................................................................................................... 7

Stormwater Quality ..............................................................................................................................9
          4.1. Construction Phase .............................................................................................................................. 9
          4.2. Operational Phase ............................................................................................................................ 10

Conclusion ........................................................................................................................................ 11




Appendices
Appendix A
          Proposed Development Concept Plans

Appendix B
          DRAINS Modelling Parameters and Results




Project number 20220218
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1                                                                                 recorconsulting.com
P +61 7 5211 1003                                      A 75 Noosa Dr, Noosa Heads Qld 4567                                             E [email protected]

Page 4

 INTRODUCTION
RECOR has been engaged to prepare a Stormwater Management Report to accompany a development application
for a residential development located at 22 Grant Street, Noosa Heads.

This report investigates the stormwater management considerations for the existing and proposed development
site and assesses how the run-off from the site is to be managed in accordance with Noosa Shire Council
requirements for stormwater drainage.




Project number 20220218                                                                                       Page 4 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 5

 SITE DETAILS

     2.1. Existing Site Description & Drainage
The existing site, known in real property terms as Lot 90 RP92518, is located at 22 Grant Street. The existing site
contains a residential dwelling within a total site area of 594m².


     2.2. Existing Drainage Patterns
The subject land is located in moderately sloping terrain with the lands falling at typically 20% to 25% to the south
west towards Grant Street. The run-off from the existing developed site typically drains as overland surface flows
towards the south eastern portion of the site, however sandy soils are typical of the locality and a portion of surface
run-off is expected to infiltrate into the site soils.
A stormwater inlet pit is located immediately in front of the subject site to which the site’s overland flows will drain.
No kerb adaptor outlets were observed within the site frontage so it is expected that roof drainage is discharged
directly into the pit.




                                    Figure 2.1 - Site Locality Plan (Noosa Council Intramaps, 2022)




     2.3. Proposed Development Drainage Pattern

          2.3.1 Stormwater Concept
An internal stormwater drainage network will consist of inlet pits and pipes will capture run-off from impervious areas
and convey it to the lawful point of discharge from the site. The drainage will capture any upstream run-off entering
the property, as well as provide connection points for roof drainage.



Project number 20220218                                                                                       Page 5 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 6

Due to the central location of the driveway, the existing kerb inlet pit in front of the site will be demolished and
replaced. A new kerb inlet will be provided downstream of the driveway access, with the existing 375mm stormwater
line connected into the pit and all drainage from the site discharged into the new pit.

The roof and allotment drainage system for the proposed site shall be designed to comply with:

     1. Noosa Shire Council Planning Scheme Policy (PSP) - Engineering Design Standards – Roads, drainage and
        earthworks;

     2. The Queensland Urban Drainage Manual (QUDM); and

     3. AS/NZS 3500.3:2015 - Plumbing and Drainage Part 3: Stormwater Drainage.

Refer to Appendix A Proposed Development Concept Plan for the proposed stormwater drainage layout plan
illustrating the concept described above.



     2.4. Flood Considerations
Review of the Noosa Shire Council Intramaps flood layers including the Flood Hazards Overlay has identified that
the site is located outside of any flood or inundation areas within the locality indicating it is not expected that that
the proposed development will be subject to flooding.




Project number 20220218                                                                                       Page 6 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 7

 STORMWATER QUANTITY

     3.1. Pre-Post Comparison
As the development proposes to increase the impervious area of the site by approximately 177m² (from 257m² to
434m²), there is likely to be an increase in peak flows from the site. The site has been modelled using the DRAINS
software to assess the impact on peak flows, comparing the existing site conditions to the proposed development.

In accordance with ARR2019, an Initial Loss-Continuing Loss (IL-CL) model has been used to assess the site against
the ensemble of storm temporal patterns for the East Coast North region. The loss parameters and temporal patterns
have been imported from the ARR Datahub, and rainfall intensities have been imported from the Bureau of
Meteorology IFD rainfall data allowing for a 20% increase to rainfall depths to account for future climate change
patterns.

The parameters obtained from the Australian Rainfall and Runoff (ARR) Data Hub for the location and the rainfall
IFD data obtained from the Bureau of Meteorology have been imported into Drains to generate the storm events.
The models have been run using the ensemble of storm events for 1EY, 50%, 0.2EY, 10%, 5%, 2% and 1% Annual
Exceedance Probability (AEP) for durations from 1 minutes to 24 hours to determine the critical storm duration and
the mean peak flowrate from the storms. Refer to Appendix B DRAINS Modelling Parameters and Results for details
of the parameters used and summary of the results from the modelling.

The impervious areas and composition of each site has been determined using survey data and architectural
designs. The configuration of the catchment areas for pre-development and post-development conditions are
shown in Figure 3.1 – DRAINS Pre-development catchment and Figure 3.2 – DRAINS Post-development catchments
respectively.




                                            Figure 3.1 – DRAINS Pre-development catchment




                                           Figure 3.2 – DRAINS Post-development catchments



Project number 20220218                                                                                       Page 7 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 8

The results of the modelling against the range of design storms for the development under the existing and
proposed development conditions are shown in Table 3.1 Existing and proposed unmitigated site peak discharge
rates.


                              Table 3.1 Existing and proposed unmitigated site peak discharge rates

                                                                      Delorme Street
                                                                                                      Qchange
                                           A.E.P               Qexisting   Qproposed     Qchange       (%)
                                                               (m³/s)      (m³/s)        (m³/s)
                                             1EY                0.016       0.018         0.002        13%
                                            50%                0.018         0.020       0.002         11%
                                           0.2 EY              0.027         0.030       0.003         11%
                                            10%                0.035         0.036       0.001          3%
                                             5%                0.040         0.041       0.001          3%
                                             2%                0.047         0.047       0.000          0%
                                             1%                0.051         0.051       0.000          0%



As expected, the site has increased the total peak flows from the site, however the overall increase is minor with a
maximum of 3L/s increase under 2100 climate conditions. This level of increase is unlikely to result in significant
impact or nuisance to the downstream network and is therefore negligible. No attenuation is proposed for the
development.




Project number 20220218                                                                                           Page 8 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567       E [email protected]    recorconsulting.com

Page 9

 STORMWATER QUALITY
The following sections discuss the stormwater quality considerations for the construction and operational phase of
the development.


     4.1. Construction Phase

          4.1.1 Erosion and Sediment Control Measures
During construction, it is necessary to manage stormwater run-off to avoid potential contamination of downstream
drainage networks and receiving environments from sediments and other pollutants from the site. A range of best
practice sediment and erosion controls should be implemented on the development to ensure negative impacts to
the downstream systems are mitigated.

As the area being developed is below 2,500m², the development’s construction will be managed using best practice
erosion and sediment control principles in line with the desired outcomes of Appendix 2 of the SPP (DERM, July
2017), which are shown below in Figure 4.1.




                     Figure 4.1 SPP 2017 Construction Phase Stormwater Management Design Objectives

A site-specific erosion and sediment control plan is required for the development. Suitable erosion and sediment
controls for the site may include:

     1. Sediment fencing along downstream of the work areas within the site to prevent sediment from leaving the
        construction area.




Project number 20220218                                                                                       Page 9 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 10

     2. A shakedown area is to be installed at the construction entry/exit to the proposed development area to
        minimise sediment being transported to and from the site.

     3. Filter socks or similar are to be provided within the downstream kerb and drainage to prevent sediment from
        entering the downstream drainage system.

     4. Diversion of upstream catchments around any exposed areas using diversion drains around the site.

     5. Grass turf strips along the kerb line until stabilisation of any exposed verge has taken place.


     4.2. Operational Phase
The development consists of a small lot duplex consistent in character with the existing residential dwelling. The
proposed development is not considered to significantly alter the pollutant generation potential of the site, and
therefore no additional stormwater quality treatment is proposed for the development.




Project number 20220218                                                                                       Page 10 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 11

 CONCLUSION
This Stormwater Management Report has outlined how the stormwater run-off from the site is to be managed to
comply with the relevant requirements and minimise any adverse impacts to the downstream catchments.

     •    The proposed site surface run-off is captured internally and discharged into the Council stormwater
          infrastructure on Grant Street as the lawful point of discharge.

     •    An existing kerb inlet pit will be relocated downstream of the proposed driveway location and any existing
          drainage pipes will be reconnected into the new pit to maintain the existing drainage characteristics of the
          network.

     •    Field inlet pits are provided within the development to capture upstream run-off and provide connection
          points for roof drainage to convey it through the development.

     •    The existing and proposed development site have been modelled for the critical design storm events for the
          site, which found there is an insignificant increase in peak flows which is unlikely to result in significant
          impacts or nuisance to downstream drainage networks. No attenuation is therefore proposed for the site.

     •    During construction, erosion and sediment control measures are to be implemented to minimise potential
          contaminants impacting the downstream receiving environment in line with the objectives of Appendix 2 of
          the SPP.

     •    As the development is a small residential site that does not significantly alter the pollutant generating
          characteristics of the site, stormwater quality treatment is not proposed for the development.

     •    The proposed stormwater solution is considered to minimise any adverse impacts to the downstream
          environment arising from the stormwater run-off while also meeting the stormwater quality targets required
          for the development.




Project number 20220218                                                                                       Page 11 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 12

Appendix A
Proposed Development Concept Plans




Project number 20220218                                                                                       Page 12 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 13

PROPOSED RESIDENTIAL DUPLEX
22 GRANT STREET, NOOSA HEADS, QLD, 4567
Lot 90 ON RP92518
CIVIL WORKS




                          DRAWING SCHEDULE
   DRAWING NUMBER                               DRAWING TITLE
                001                      COVER SHEET & LOCALITY PLAN
                002                             GENERAL NOTES
                003      EXISTING SITE SERVICES AND DEMOLITION LAYOUT PLAN
                010                         DRIVEWAY LAYOUT PLAN
                020                     BULK EARTHWORKS LAYOUT PLAN
                                                                                                                                                  Lot 90 on RP92518
                021                   EARTHWORKS LONGITUDINAL SECTIONS
                030            EROSION AND SEDIMENT CONTROL LAYOUT PLAN
                031              EROSION AND SEDIMENT CONTROL DETAILS
                040                       STORMWATER LAYOUT PLAN
                045               STORMWATER CATCHMENT LAYOUT PLANS
                060                         VEHICLE SWEPT PATHS




                                                                                                                                                                            LOCALITY PLAN
                                                                                                                                                                             NOT TO SCALE




                                                                             CLIENT DETAILS:                                   PROJECT ADDRESS:                       APPROVED BY:              PROJECT NAME:

                                                                                                                                                                                                PROPOSED RESIDENTIAL DUPLEX
                                                                                        INTEGRA PARTNERSHIPS                                                                                    TITLE:                STATUS:

                                                                                                                                          22 GRANT STREET                                       COVER SHEET AND       FOR APPROVAL - NOT FOR
  © ABN 89 647 469 707
                                                                                                                                        NOOSA HEADS, QLD, 4567              NATHAN WAGSTAFF     LOCALITY PLAN         CONSTRUCTION
    75 NOOSA DRIVE                                                                                                                                                             RPEQ: 20693
                                                                             SCALE:
 NOOSA HEADS, QLD 4567                                                                                                                                                           CPEng
     +61 7 5211 1003     REV   DATE        DESCRIPTION     DWN   CHK   APP
                                                                                                         N.T.S                                                               DATE: 23/09/2022
                                                                                                                                                                                                DRAWING NUMBER:       PROJECT NUMBER:   SHEET REV:
                                                                                                                                                                                                                                         SIZE:
 RECORCONSULTING.COM                           REVISIONS
                                                                                               DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                001                   20220218          A1 01

Page 14

GENERAL NOTES                                                                             COMPLETELY REMOVED AND BACKFILLED TO LEVEL 1 SUPERVISION.                  EARTHWORKS NOTES                                                                 ARE TO COVER OR ENCLOSE STOCKPILES WHERE REASONABLY
                                                                                          CONTRACTOR TO ALLOW TO MULCH ALL CLEARED VEGETATION AND                                                                                                     PRACTICAL TO RESTRICT DUST MOVEMENT.
1.   ALL DIMENSIONS SHOWN ARE IN METERS UNLESS OTHERWISE SHOWN.                           STOCKPILE ON SITE OR REMOVE FROM SITE AS DIRECTED.                         1.  FOR DETAILED GEOTECHNICAL INFORMATION, REFER GEOTECHNICAL                19. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON
                                                                                                                                                                         INVESTIGATION REPORT BY GEOTECHNICAL ENGINEER. IT IS                         THIS DRAWING, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE
2.   ALL SETOUT ON SITE IS THE SOLE RESPONSIBILITY OF THE CONTRACTOR.             18. DRAWINGS TO BE READ IN CONJUNCTION WITH ARCHITECT, SURVEYOR,                       RECOMMENDED THAT THE GEOTECHNICAL CONSULTANT BE CONTACTED                    WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.
     CONTRACTOR TO ALLOW FOR ALL MEANS NECESSARY TO ACCURATELY                        HYDRAULICS, ETC. CONSULTANT AND CONTRACTOR DRAWINGS.                               TO CONFIRM THE SOIL CONDITIONS PRIOR TO EARTHWORKS
     SETOUT THE WORKS.                                                                                                                                                                                                                            20. ALL EXCAVATIONS ARE TO BE CONDUCTED IN ACCORDANCE WITH THE
                                                                                  19. CONTRACTOR TO PREPARE AND HAVE APPROVED BY RELEVANT                                COMMENCING.
                                                                                                                                                                                                                                                      REQUIREMENTS OF THE GEOTECHNICAL ENGINEER AS OUTLINED IN THE
3.   ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH PROJECT                           AUTHORITY: ROAD OPENING PERMIT AND TRAFFIC MANAGEMENT PLAN                     2. GRASS AND TOPSOIL SHALL BE STRIPPED TO A MINIMUM DEPTH OF                     GEOTECHNICAL INVESTIGATION REPORT BY TECTONIC. TEMPORARY
     SPECIFICATIONS AND WHERE FURTHER DETAILS ARE REQUIRED THE                        FOR ALL WORKS WITHIN COUNCIL ROAD RESERVES. CONTRACTOR TO                          100MM OVER THE EXTENT OF THE WORKS UNLESS DIRECTED                           UNSURCHARGED CUTS IN LOOSE TO VERY LOOSE SAND TO BE FORMED
     CONTRACTOR SHALL REFER TO NOOSA SHIRE COUNCIL DEVELOPMENT                        ALLOW FOR ALL COSTS ASSOCIATED WITH IMPLEMENTATION OF THE                          OTHERWISE AND STOCKPILED WHERE REQUIRED FOR FILL OF                          AT 1V:2H, AND IN MEDIUM DENSE SAND AT 1V:1H FOR BATTERS UP TO 3M
     GUIDELINES, LOCAL WATER AUTHORITY GUIDELINES, ASSOCIATED                         TMP.                                                                               LANDSCAPING AREAS. TOPSOIL MATERIALS MUST NOT BE USED IN                     IN HEIGHT. DEEPER CUTS ARE TO BE ASSESSED BY THE GEOTECHNICAL
     STANDARD DRAWINGS AND SPECIFICATIONS U.N.O.                                                                                                                         STRUCTURAL FILL.
                                                                                  20. ALL WORKS TO BE COMPLETED IN ACCORDANCE WITH ALL LOCAL                                                                                                          ENGINEER.
3.   SHOULD ANY OF THE CONSTRUCTED WORKS BE CONSTRUCTED OUTSIDE                       AUTHORITY APPROVALS RECEIVED FOR THE PROJECT AND IN                            3. UNSUITABLE NATURAL MATERIALS SUCH AS SATURATED, LOOSE OR                  21. WHERE THE ABOVE TEMPORARY BATTER SLOPES CAN NOT BE
     OF THE TOLERANCES SPECIFIED WITHIN THE PROJECT SPECIFICATION                     ACCORDANCE WITH OPW APPROVALS BY COUNCIL.                                          SOFT MATERIALS ENCOUNTERED SHOULD BE REMOVED DURING                          ACHIEVED, TEMPORARY SHORING WILL BE REQUIRED UNDER THE ADVICE
     AND LOCAL AUTHORITY REQUIREMENTS, THE CONTRACTOR WILL                                                                                                               SUBGRADE PREPARATION FOR BULK EARTHWORKS. ALL UNSUITABLE                     OF A SPECIALIST SHORING CONTRACTOR.
     RECTIFY AT THEIR COST INCLUSIVE OF ANY ADDITIONAL COSTS                      21. NO WORKS ARE TO BE UNDERTAKEN ON LAND OUTSIDE OF THE SITE                          MATERIAL TO BE REMOVED FROM SITE AT CONTRACTORS EXPENSE.
                                                                                      BOUNDARY WITHOUT FORMAL APPROVAL BY THE OWNER/CUSTODIAN OF                                                                                                  22. EXCAVATIONS IN PROXIMITY TO EXISTING STRUCTURES WILL REQUIRE
     INCURRED BY RECOR.                                                                                                                                              4. COMPACTION OF THE EXPOSED SAND SUBGRADE REQUIRES                              SPECIFIC DESIGN TO PREVENT UNDERMINING WHICH SHOULD BE
                                                                                      THAT LAND INCLUDING BUT NOT LIMITED TO PRIVATE PROPERTY, ROAD                      SUBSTANTIAL VOLUMES OF WATER COMBINED WITH VIBRATORY
4.   EXISTING SERVICES HAVE BEEN PLOTTED FROM SUPPLIED DATA AND AS                    RESERVE, PARKS/OPENSPACE, EASEMENTS.                                                                                                                            CARRIED OUT BY A SUITABLY QUALIFIED AND EXPERIENCED RPEQ
     SUCH THEIR ACCURACY CANNOT BE GUARANTEED. NO RESPONSIBILITY                                                                                                         COMPACTION EQUIPMENT. CARE MUST BE TAKEN TO ENSURE THERE ARE                 STRUCTURAL ENGINEER.
     IS TAKEN BY RECOR OR THE PRINCIPAL FOR THE ACCURACY AND                      22. THE CONTRACTOR SHALL HAVE AN APPROVED SET OF CONSTRUCTION                          NO IMPACTS ON SURROUNDING STRUCTURES. MATERIAL TO BE
                                                                                                                                                                                                                                                  23. CONTRACTOR'S RPEQ GEOTECHNICAL ENGINEER IS TO CONFIRM THAT
     COMPLETENESS OF THIS INFORMATION. IT IS THE RESPONSIBILITY OF                    DRAWINGS AND APPROVALS ON SITE AT ALL TIMES.                                       COMPACTED IN ACCORDANCE WITH GEOTECHNICAL REPORT AND
                                                                                                                                                                                                                                                      ANY CONSTRUCTED CUT/FILL BATTERS AND RETAINING STRUCTURES ON
     THE CONTRACTOR TO ACCURATELY ESTABLISH THE LOCATION AND                                                                                                             AS1289.
                                                                                  23. ALL WATER AND SEWER RETICULATION WORKS TO BE CONSTRUCTED IN                                                                                                     THE SITE HAVE ACHIEVED ADEQUATE STABILITY WITH A LONG-TERM
     LEVEL OF ALL EXISTING SERVICES PRIOR THE COMMENCEMENT OF ANY                     ACCORDANCE WITH THE SEQ WATER SUPPLY AND SEWERAGE DESIGN                       5. A MINIMUM 150MM THICK GRANULAR WORKING PLATFORM MAY BE                        FACTOR OF SAFETY AGAINST GEOTECHNICAL FAILURES TO THEIR
     WORKS. ANY DISCREPANCIES SHALL BE REPORTED TO THE                                AND CONSTRUCTION CODE (2013).                                                      REQUIRED ON SOIL SUBGRADES ALONG HAUL ROADS AND LAYDOWN                      SATISFACTION.
     SUPERINTENDENT. CONTRACTOR TO LOCATE AND PROTECT SERVICES                                                                                                           AREAS TO IMPROVE TRAFFICABILITY. SPECIFIC PLATFORM DESIGN
                                                                                                                                                                                                                                                  24. EARTHWORKS LEVELS SHOWN ARE FINISHED SURFACE LEVELS
     AS REQUIRED DURING PROPOSED WORKS.                                                                                                                                  WOULD BE REQUIRED PRIOR TO MOBILISATION AND TRAFFICKING OF ANY
                                                                                                                                                                                                                                                      INCLUSIVE OF TOPSOIL LAYER. REFER TO STRUCTURAL ENGINEERING
                                                                                  STANDARD SIGNS AND LINE MARKING NOTES                                                  HEAVY MOBILE PLANT ON THE SITE.
                                                                                                                                                                                                                                                      DRAWINGS FOR BUILDING SLAB THICKNESSES AND HYDRAULIC
5.   THE CONTRACTOR IS TO CHECK THROUGH LOCATING, POTHOLING AND                                                                                                      6. IMPORTED GENERAL FILL MATERIAL SHALL BE SUPPLIED AND
     SURVEY ALL CRITICAL CONNECTION POINTS FOR ALL CIVIL WORKS                    1. GENERAL                                                                                                                                                          DRAWINGS FOR SUB-FLOOR DRAINAGE FOR DETERMINATION OF
                                                                                                                                                                         COMPACTED WHERE UNSUITABLE NATURAL MATERIALS ARE LOCATED                     REQUIRED BULK EARTHWORKS SURFACE.
     SHOWN ON THE DRAWINGS INCLUDING ANY POTENTIAL EXISTING                        1.1.  ALL SIGNS AND PAVEMENT MARKING IS TO BE IN ACCORDANCE WITH                      AND AS OTHERWISE NECESSARY TO OBTAIN SUBGRADE/PLATFORM
     SERVICES CLASHES PRIOR TO COMMENCEMENT OF CIVIL WORKS.                              THE QUEENSLAND TRANSPORT MANUAL OF UNIFORM TRAFFIC                                                                                                       25. ANY PRELOADING REQUIRED IS TO OCCUR IN ACCORDANCE WITH THE
                                                                                                                                                                         LEVEL. IMPORTED GENERAL FILL MATERIAL SHALL BE CLEAN GRADED
     CONTRACTOR TO IMMEDIATELY REPORT ANY DISCREPANCIES TO RECOR                         CONTROL DEVICES (CURRENT EDITION).                                                                                                                           GEOTECHNICAL ENGINEERS REQUIREMENTS. CONTRACTOR TO ALLOW
                                                                                                                                                                         MATERIAL FREE OF ORGANIC MATTER AND STONES, WITH MAXIMUM
     AND AWAIT FORMAL DIRECTION PRIOR TO COMMENCING CIVIL WORKS.                  2. SIGNS                                                                                                                                                            FOR THE IMPORT AND REMOVAL OF ALL NECESSARY MATERIAL TO
                                                                                                                                                                         PARTICLE SIZE OF 100mm AND CAPABLE OF BEING COMPACTED INTO
                                                                                    2.1. ALL SIGNS TO BE REFLECTORISED CLASS 1 TO AS1906.1:2007 UNLESS                                                                                                UNDERTAKE THE PRELOADING OPERATIONS.
6.   ON COMPLETION OF SERVICES INSTALLATION, ALL DISTURBED AREAS                                                                                                         COHERENT FILLING TO THE SPECIFIED STANDARD. THE MATERIAL SHALL
                                                                                         NOTED OTHERWISE.                                                                HAVE A MAXIMUM PLASTICITY INDEX OF 15%, A SHRINK-SWELL INDEX OF          26. REFER ARCHITECTURAL DRAWINGS FOR BUILDING SETOUT.
     SHALL BE RESTORED TO ORIGINAL LEVEL, INCLUDING KERBS,
     FOOTPATHS, CONCRETE AREAS, GRAVEL AREAS, GRASSED AREAS AND                     2.2. SIGNS ARE TO BE INSTALLED WITH THE FOLLOWING CLEARANCES TO                      LESS THAN OR EQUAL TO 1% AND A MINIMUM C.B.R. OF 10%.
     ROAD PAVEMENTS.                                                                     EDGE OF SIGN: LOCATION CLEARANCE NO KERB 600 BEHIND GUIDE                   7. ALL EARTHWORKS TO BE CARRIED OUT AT +/- 2% OPTIMUM MOISTURE               INSPECTIONS:
                                                                                         POSTS BARRIER KERB 300 FROM FACE MOUNTABLE KERB 500 FROM                        CONTENT FOR STANDARD COMPACTION.
7.   CONTRACTOR SHALL BE RESPONSIBLE FOR REPAIR OF ANY DAMAGE TO                                                                                                                                                                                  THE FOLLOWING INSPECTIONS MUST BE COMPLETED BY RECOR ENGINEERS
                                                                                         FACE OF KERB.                                                               8. ANY PROPOSED RETAINING WALL WORKS MUST BE WHOLLY WITHIN THE
     AUTHORITY/COUNCIL'S INFRASTRUCTURE. SUCH REPAIR OR                                                                                                                                                                                           BEFORE ENGINEERING CERTIFICATION WILL BE ISSUED. THE CONTRACTOR IS
     REINSTATEMENT TO BE CARRIED OUT IMMEDIATELY TO THE                             2.3. PARKING CONTROL SIGNS TO BE MOUNTED TO FACE APPROACHING                         PROPERTY BOUNDARY OF THE SUBJECT SITE, INCLUDING REAR OF
                                                                                         TRAFFIC AT 45° TO KERB OR CARRIAGEWAY EDGE. ALL OTHER SIGNS                     RETAINING WALL DRAINAGE INFRASTRUCTURE FOR RETAINING WALLS IN            TO PROVIDE A MINIMUM OF 72 HOURS NOTICE TO RECOR FOR REQUIRED
     SATISFACTION OF INFRASTRUCTURE OWNER/MANAGER /                                                                                                                                                                                               INSPECTIONS. SHOULD THE
     AUTHORITY/COUNCIL.                                                                  TO BE TURNED AWAY BY 5° FROM THE NORMAL TO APPROACHING                          CUT. RETAINING WALLS ARE TO BE PREPARED IN ACCORDANCE WITH
                                                                                         HEADLIGHT.                                                                      STRUCTURAL ENGINEERS SPECIFICATIONS, AND IN CONFORMANCE WITH             CONTRACTOR FAIL TO REQUEST AN INSPECTION, THE CONTRACTOR WILL BE
8.   CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH ALL                     3. SIGN SUPPORTS                                                                       CONSTRUCTION REQUIREMENTS OF GEOTECHNICAL REPORT.                        RESPONSIBLE FOR ALL COSTS TO ALLOW FOR THE WORKS TO BE INSPECTED
     WORKPLACE HEALTH AND SAFETY REQUIREMENTS.                                                                                                                                                                                                    TO THE SATISFACTION OF RECOR. ANY INSPECTIONS THAT FAIL ARE TO BE
                                                                                    3.1.  SLEEVED SIGNS SUPPORTS ARE TO BE PROVIDED IN ALL AREAS                     9. REFER ARCHITECT/LANDSCAPE ARCHITECT DRAWINGS FOR
9.   WHERE ANY EXCAVATION OR CONSTRUCTION WORKS ARE TO BE IN                             WHERE THEY ARE IN A PAVED SURFACE.                                              CONFIRMATION OF RETAINING WALL COLOUR AND FINISH.                        RE-INSPECTED WITH ALL REINSPECTION COSTS TO BE PAID BY THE
     CLOSE PROXIMITY TO NEIGHBOURING LOT BOUNDARIES OR                            4. LINEMARKING                                                                     10. ALL EARTHWORKS OPERATIONS SHALL BE CARRIED OUT WITH 'LEVEL 2'            CONTRACTOR.
     INFRASTRUCTURE, CONTRACTOR TO ALLOW IN SCOPE OF WORKS TO                       4.1. REDUNDANT LINEMARKING IS TO BE GROUND OFF.                                      SOIL ENGINEERING SUPERVISION IN ACCORDANCE WITH APPENDIX B OF            a.   PRESTART
     PROVIDE ALL MEASURES NECESSARY TO ENSURE THE INTEGRITY OF                      4.2. THERMOPLASTIC LINEMARKING TO BE USED FOR ALL CONCRETE.                          AS 3798. THE NOMINATED GEOTECHNICAL TESTING AUTHORITY SHALL
     EXISTING BOUNDARIES AND INFRASTRUCTURE. THIS MAY INCLUDE THE                                                                                                        PROVIDE CERTIFICATION THAT ALL GENERAL EARTHWORKS OPERATIONS             b.   EARTHWORKS - FINAL STRIPPING OF TOPSOIL, INSTALLATION OF
     USE OF LOW VIBRATION EQUIPMENT, TRENCH SHORING ETC AS                                                                                                               HAVE BEEN CARRIED OUT IN ACCORDANCE WITH THE DRAWINGS AND                     SEDIMENT AND EROSION CONTROL MEASURES UNSUITABLE GROUND
     REQUIRED.                                                                    JOINTING NOTES                                                                         SPECIFICATIONS AND THE CONTROLLED FILL IS SUITABLE FOR PURPOSE           c.   SIDE AND CUT OFF DRAINS
10. PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS DETAILED ON                                                                                                             TO THE REQUIRED BEARING CAPACITY UNDER THE
                                                                                  1.      ALL JOINTING AND CONCRETE TO BE IN ACCORDANCE WITH THE                                                                                                  d.   STORMWATER PIPE LAID ON BEDDING PRIOR TO BACKFILL
    THESE DRAWINGS, THE CONTRACTOR IS TO NOTIFY RECOR AND RECEIVE                                                                                                        PLATFORM/STRUCTURES AS SPECIFIED BY THE GEOTECHNICAL REPORT.
    WRITTEN CONFIRMATION THAT WORKS CAN COMMENCE.                                         REQUIREMENTS OF AS3727.1:2016.                                             11. ALL EARTHWORKS FILL AND EXCAVATED AREAS SHALL BE COMPACTED               e.   STORMWATER TRENCH BACKFILLED PRIOR TO PAVEMENT PLACEMENT
                                                                                  2.      SAW CUT JOINTS MUST BE:                                                        TO 98% STANDARD MAXIMUM DRY DENSITY OR A DRY DENSITY INDEX OF
11. CONTRACTOR TO PROVIDE AS CONSTRUCTED DRAWINGS FOR ALL                                                                                                                                                                                         f.   STORMWATER STRUCTURE BASE SLABS
                                                                                              BETWEEN 1 AND 1 OF CONCRETE PAVEMENT DEPTHS.
                                                                                                                                                                         AT LEAST 75% IN ACCORDANCE WITH THE GEOTECHNICAL REPORT IN
    CONSTRUCTED WORKS IN ACCORDANCE WITH LOCAL GOVERNMENT                              2.1.                                                                                                                                                       g.   SEWER RETICULATION
                                                                                                      4     3                                                            LAYERS OF 250MM LOOSE THICKNESS (PRIOR TO COMPACTION).
    REQUIREMENTS. UNLESS OTHERWISE ADVISED BY RECOR CONTRACTOR                         2.2.
                                                                                          CLEARED OF ANY DEBRIS FROM THE CUTTING METHOD.                             12. COMPACTION TESTING TO BE CARRIED OUT AT A MINIMUM OF TWO                 h.   WATER RETICULATION
    TO NOTE COUNCILS ADAC REQUIREMENTS.
                                                                                       2.3.
                                                                                          PERFORMED WITHIN 6 TO 12 HOURS OF FINISHING CONCRETE                           TESTS PER VERTICAL LIFT WHERE STRUCTURAL FILL HEIGHTS EXCEED
12. CONTRACTOR TO UNDERTAKE ALL WORKS IN ACCORDANCE WITH                                                                                                                                                                                          i.   PAVEMENT SUBGRADE
                                                                                          POURS.                                                                         300MM IN ACCORDANCE WITH AS3798. CONTRACTOR TO UNDERTAKE ALL
    RELEVANT APPROVALS.                                                           3. DOWELL BARS MUST BE INSTALLED EXACTLY 90° TO THE FACE OF JOINT                      EARTHWORKS TESTING IN ACCORDANCE WITH GEOTECHNICAL                       j.   PAVEMENT REINFORCING
13. CONTRACTOR TO ALLOW TO LIASE/CO-ORDINATE WITH ELECTRICAL,                         TO ALLOW EXPANSION AND CONTRACTION MOVEMENTS.                                      ENGINEER AND LOCAL AUTHORITY REQUIREMENTS.
                                                                                                                                                                                                                                                  k.   PAVEMENT PRIOR TO SEALING (PRESEAL)
    LANDSCAPE AND OTHER SERVICE CONTRACTORS THROUGHOUT CIVIL                      4. JOINTING LAYOUT TO BE CONFIRMED BY SUPERINTENDANT PRIOR TO                      13. FINISHED SURFACES TO ALL DISTURBED AREAS ARE TO BE TREATED IN
                                                                                      CONSTRUCTION COMMENCING. LAYOUT SHOULD AVOID ACUTE ANGLES                          ACCORDANCE WITH LANDSCAPE DRAWINGS.                                      l.   RETAINING WALL FOOTING REINFORCING
    CONSTRUCTION.
                                                                                      IN THE CONCRETE SLAB AND AVOID MISMATCHED JOINTS.                              14. ALL NEW WORKS TO MATCH NEATLY INTO EXISTING LEVELS.                      m. RETAINING WALL BLOCKWORK PRIOR TO CORE FILL
14. CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS PRIOR
                                                                                  5. JOINT SEALANTS WHERE USED MUST ADHERE TO SIDE OF JOINT FACES                    15. ALL WORKS TO BE CONSTRUCTED IN ACCORDANCE WITH APPROVED                  n.   STEEL REINFORCEMENT OF CONCRETE STRUCTURES
    DEMOLITION WORKS COMMENCING ON SITE.
                                                                                      ONLY AND SHALL NOT EXTEND ABOVE SIDES OF JOINTS ONTO THE SLAB                      MANAGEMENT PLANS.
15. CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING STRUCTURES,                          SURFACE.                                                                       16. CONTRACTOR TO ENSURE SUITABLE EROSION CONTROL MEASURES ARE               o.   PRACTICAL COMPLETION
    ROADS AND SERVICES WITHIN LIMIT OF WORKS AND REMOVE FROM SITE                 6. DOWEL BARS ARE TO BE                                                                INSTALLED INCLUDING BUT NOT LIMITED TO SHAKE DOWNS, SILT FENCE           p.   ON MAINTENANCE
    U.N.O.                                                                         6.1.   FOR 100MM THICK SLAB, 12MM Ø OF LENGTH 300MM AND SPACED AT                     ETC IN ACCORDANCE WITH EROSION AND SEDIMENT CONTROL PLAN.
                                                                                                                                                                                                                                                  q.   OFF MAINTENANCE
16. CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR ADJOINING                             400MM CENTRES                                                              17. ADEQUATE SAFETY FENCING/BARRIERS TO BE APPLIED TO ALL BATTERS
    PROPERTIES AND COUNCIL ROADS AND VERGES PRIOR TO                               6.2.   FOR 125MM THICK SLAB, 16MM Ø OF LENGTH 350MM AND SPACED AT                     OR RETAINING WALLS (TEMPORARY OR PERMANENT) AS PER RELEVANT              r.   ANY OTHER INSPECTION AS SPECIFIED BY LOCAL COUNCIL (REFER
    COMMENCEMENT OF ANY WORKS ON SITE.                                                    300MM CENTRES                                                                  AUSTRALIAN STANDARDS AND LEGISLATION.                                         DEVELOPMENT APPROVAL)
17. CONTRACTOR TO CLEAR AND GRUB ALL VEGETATION ON SITE AS                         6.3.   FOR 150MM THICK SLAB, 20MM Ø OF LENGTH 400MM AND SPACED AT                 18. DUST CONTROL MEASURES ARE TO INCLUDE SPRAYING WATER ON                   s.   ANY OTHER INSPECTION AS REQUIRED BY UNITY WATER AND WHERE
    IDENTIFIED IN THE APPROVED VEGETATION MANAGEMENT PLAN.                                300MM CENTRES                                                                  UNPAVED ROADS, ACCESS TRACKS AND STOCKPILES AT A SUFFICIENT                   RELEVANT TO THEIR CERTIFICATION SCHEME
    CONTRACTOR TO ENSURE ALL TREE ROOTS AND STUMPS ARE                                                                                                                   LEVEL TO SUPPRESS DUST GENERATION. ADDITIONALLY CONTRACTORS




                                                                                                                   CLIENT DETAILS:                                        PROJECT ADDRESS:                                   APPROVED BY:                  PROJECT NAME:

                                                                                                                                                                                                                                                           PROPOSED RESIDENTIAL DUPLEX
                                                                                                                              INTEGRA PARTNERSHIPS                                                                                                         TITLE:                               STATUS:

                                                                                                                                                                                     22 GRANT STREET                                                       GENERAL NOTES                        FOR APPROVAL - NOT FOR
                 © ABN 89 647 469 707
                                                                                                                                                                                   NOOSA HEADS, QLD, 4567                          NATHAN WAGSTAFF                                              CONSTRUCTION
                  75 NOOSA DRIVE                                                                                                                                                                                                      RPEQ: 20693
                                                                                                                   SCALE:
               NOOSA HEADS, QLD 4567                                                                                                                                                                                                    CPEng
                   +61 7 5211 1003               REV   DATE             DESCRIPTION             DWN    CHK   APP
                                                                                                                                               N.T.S                                                                                DATE: 23/09/2022
                                                                                                                                                                                                                                                           DRAWING NUMBER:                      PROJECT NUMBER:          SHEET REV:
                                                                                                                                                                                                                                                                                                                          SIZE:
               RECORCONSULTING.COM                                          REVISIONS
                                                                                                                                     DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                           002                                   20220218                A1 01

Page 15

                                                            S


                                                                    W
                                                                                                                                                                                                                                                                                                                LEGEND




                                                            S
                                                       V




                                                                    W
                                                                                                                                                                                                                                                                                                                       EXISTING FIRE HYDRANT




                                                            S
                                                                                                                                                                                                                                                                                                                       EXISTING POWER POLE




                                                                    W
                                                       V
                                                                                                                                                                                                                                                                                                                       EXISTING 'LIVE' SEWER CHAMBER

                                                                                                                                                                                                                                                                                                                       EXISTING STORMWATER MANHOLE




                                                            S


                                                                    W
                                                                                                                                                                                                                                                                                                                       EXISTING STORMWATER PIT




                                                       V
                                                                                                                                                                                                                                                                                                                       EXISTING STORMWATER STRUCTURES


  N                                                                                                                                                                                                                                                                                                 S       S          EXISTING SEWERAGE LINE




                                                            S


                                                                    W
                                                                                                                                                                                                                                                                                                    W       W          EXISTING WATER RETICULATION MAIN




                                                       V
                                                                                                                                                                                                                                                                                                   V        V          OVERHEAD ELECTRICITY


                                                                                                                        BU CP
                                                            S
                                                                                                                                                                                                                                                                                                    SW      SW         STORMWATER PIPE

                                                                                                                          P1
                                                                    W
                                                                                                                                                                                                                                                                                                                       WATER VALVE

                                                                                                                             37
                                                       V



                                                                                                                                3
                                                                                                                                                                                                                                                                                                                       WATER SERVICE

                                                                                                                                           1
                                                            S


                                                                    W
                                                       V


                                                            S


                                                                    W
               GRANT STREET
GRANT STREET




                                                       V


                                                            S


                                                                    W
                                                       V


                                                            S


                                                                    W




                                                                                                                                           90
                                                            S
                                                       V




                                                                    W
                                                  SW




                                                                                                                                                                                                                                 EXISTING TREES TO BE
                                                                                                                                                                                                                                 FELLED, MULCHED AND
                                                            S




                                                                                                                                                                                                                                 REMOVED OFF SITE U.N.O
                                                       V




                                                                    W




                                                                                                                                                                                                                                                                                NOTES
                                                            S




                                                                                                                                                                                                                                   BU       CP                                        1.    FOR GENERAL NOTES REFER DWG 002, WHICH IS TO BE
                                                                    W
                                                       V




                              EXISTING DRIVEWAY                                                                                                                                                                                         P5                                                  REQUESTED AND VIEWED PRIOR TO COMMENCEMENT OF
                              CROSSOVER TO BE
                                                                                                                                                                                                                                           71                                         2.
                                                                                                                                                                                                                                                                                            CONSTRUCTION IF NOT SUPPLIED.
                                                                                                                                                                                                                                                                                            THE CONTRACTOR WILL MAKE HIMSELF FULLY AWARE OF
                                                                                                                                                                                                                                              4
                              REMOVED
                                                            S


                                                                    W




                                                                                                                                                                                                                                                                                            THE EXISTING FEATURES OF THIS SITE AND ENSURE ANY
                                                       V




                                                                                                                                                                                                                                                                                            ADDITIONAL WORKS NOT SHOWN ON THIS PLAN ARE
                                                                                                                                                                                                                                                                                            INCLUDED IN THE CONTRACT.
                                                            S




                                                                                                                        V
                                                                                                           V                                                                                                                                                                          3.    LOCATION AND DEPTH OF EXISTING SERVICES BASED ON
                                                                    W




                                                                                               V
                                                                                  V
                                                                           V                                                                                                                                                                                                                SURVEY, DBYD AND COUNCIL RECORDS. IT IS THE
                                                                V
                                                                                                                                                                                                                                                                                            CONTRACTORS RESPONSIBILITY TO CONFIRM ACTUAL
                                                                                                                                                                                                                                                                                            LOCATION AND DEPTH PRIOR TO CARRYING OUT ANY
                                                            S




                                                                                                                                                                                        EXISTING BUILDINGS,
                                                                    W




                                                                                                                                                                                        STRUCTURES AND
                                                                                                                                                                                                                                                                                            EXCAVATION OR TRENCHING WORKS.
                                                                                         EXISTING SEWER SERVICE TO BE
                                                                                                                                               LOCATION AND EXTENT OF EXISITING         IMPERVIOUS SURFACES TO BE                                                                     4.    CONTRACTOR TO LOCATE AND PROTECT ALL EXISTING
                                                                                                                                               ELECTRICAL CONNECTION TO BE CONFIRMED    REMOVED U.N.O
                                                                                         DISCONNECTED AND CAPPED OFF
                                                                                                                                               ON-SITE. REMOVAL AND REPLACEMENT TO BE                                                                                                       SERVICES ON SITE PRIOR TO COMMENCEMENT OF WORKS.
                                                                                         DURING CONSTRUCTION
                                                       V


                                                            S




                                                                                                                                               ARRANGED BY SITE SUPERINTENDANT                                                                                                        5.    CONTRACTOR TO ORGANISE ALL DEMOLITION PERMITS
                                                                    W




                                                                                                                                                                                                                                                                                            PRIOR TO ANY DEMOLITION WORKS COMMENCING ON SITE.
                                                                               EXISTING WATER SERVICE TO BE                                                                                                                                                                           6.    ALL VEGETATION WITHIN THE LIMIT OF WORKS TO BE
                                                                               DISCONNECTED AND CAPPED OFF
                                                                               DURING CONSTRUCTION                                                                                                                                                                                          CLEARED, MULCHED AND REMOVED FROM SITE IN
                                                            S
                                                       V




                                                                                                                                                                                                                                                                                            ACCORDANCE WITH APPROVED VEGETATION CLEARING
                                                                    W




                                                                                                                                                                                                                                                                                            PLAN (BY OTHERS) OR IF SCHEDULED STOCKPILE FOR USE
                                                                                                                                                                                                                                                                                            BY LANDSCAPER.
                                                                                                                                                                                                                                                                                      7.    CONTRACTOR TO LOCATE ALL EXISTING UTILITIES ON SITE
                                                            S


                                                                    W




                                                                                                                                                                                                                                                                                            AND MAKE SUITABLE ARRANGEMENTS TO HAVE
                                                                                                                                                                                                                                                                                            DISCONNECTED PRIOR TO DEMOLITION WORKS BEGINNING.
                                                                                                                                                                                                                                                                                      8.    PRIOR TO THE CONTRACTOR COMMENCING ANY WORKS
                                                                                                                                                                                                                                                                                            DETAILED ON THIS DRAWING, THE CONTRACTOR IS TO
                                                                    W




                                                                                                                                                                                                                                                                                            NOTIFY RECOR AND RECEIVE WRITTEN CONFIRMATION THAT
                                                                                                                                                                                                                                                                                            WORKS CAN COMMENCE.
                                                                                                                                                                                                                                                                                      9.    CONTRACTOR TO UNDERTAKE DILAPIDATION REPORT FOR
                                                                    W




                                                                                                                                                                                                                                                                                            ADJOINING PROPERTIES AND COUNCIL ROADS AND VERGES
                                                                                                                                                                                                                                                                                            PRIOR TO COMMENCEMENT OF ANY WORKS ON SITE.
                                                                                                                                                                                                                                                                                      10.   CONTRACTOR TO ALLOW TO DEMOLISH ALL EXISTING
                                                                                                                                                                                                                                                                                            STRUCTURES, ROADS AND SERVICES WITHIN LIMIT OF
                                                                    W




                                                                                                                                                                                                                                                                                            WORKS AND REMOVE FROM SITE U.N.O.
                                                                                                                                                                                                                                                                                      11.   WHERE NECESSARY, CONTRACTOR SHALL OBTAIN ALL
                                                                                                                                                                                                                                                                                            NECESSARY APPROVALS TO CARRY OUT SERVICES
                                                                    W




                                                                                                                                                                                                                                                                                            RELOCATION OR ALTERATIONS.


                                                                                                                                  CLIENT DETAILS:                                              PROJECT ADDRESS:                            APPROVED BY:               PROJECT NAME:
                                                                    W




                                                                                                                                                                                                                                                                      PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                               INTEGRA PARTNERSHIPS                                                                                                   TITLE:                                     STATUS:

                                                                                                                                                                                                          22 GRANT STREET                                             EXISTING SERVICES AND  FOR APPROVAL - NOT FOR
                                                                    W




                  © ABN 89 647 469 707
                                                                                                                                                                                                        NOOSA HEADS, QLD, 4567                    NATHAN WAGSTAFF     DEMOLITION LAYOUT PLAN CONSTRUCTION
                  75 NOOSA DRIVE                                                                                                                                                                                                                     RPEQ: 20693
                                                                                                                                  SCALE:
               NOOSA HEADS, QLD 4567                                                                                                                                                                                                                   CPEng
                   +61 7 5211 1003                         REV      DATE       DESCRIPTION              DWN     CHK         APP
                                                                                                                                                               1:100                                                                               DATE: 23/09/2022
                                                                                                                                                                                                                                                                      DRAWING NUMBER:                            PROJECT NUMBER:                       SHEET REV:
                                                                    W




                                                                                                                                                                                                                                                                                                                                                        SIZE:
               RECORCONSULTING.COM                                                    REVISIONS
                                                                                                                                                     DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                      003                                        20220218                              A1 01

Page 16

                                                     S


                                                          W
                                                     S


                                                          W
                                                     S


                                                          W
                                                     S


                                                          W
N




                                                     S


                                                          W
                                                     S


                                                          W
                           NEW CONNECTION TO         S
                           EXISTING SEWER SERVICE
                                                          W
                                                     S


                                                          W




    NEW TYPE 'B1' BARRIER
    KERB TO REPLACE EXISTING
    STORMWATER PIT
                                                     S


                                                          W
            GRANT STREET




                                                     S


                                                          W
                                                     S


                                                          W




PROPOSED RESIDENTIAL DRIVEWAY TO
BE CONSTRUCTED IN ACCORDANCE
WITH IPWEA RS-049 & RS-050
                                                     S


                                                          W
                                                     S


                                                          W
                                                     S


                                                          W




    NEW STORMWATER INLET
                                                     S




    PIT AND BARRIER KERB.
                                                          W




    MATCH NEATLY TO EXISTING
    LEVELS
                                                     S


                                                          W




                                                                      NEW CONNECTION TO
                                                                      EXISTING WATER SERVICE
                                                     S


                                                          W
                                                     S


                                                          W
                                                     S


                                                          W
                                                          W
                                                          W




                                                                                                                                                                                                                                           NOTE:
                                                                                                                                                                                                                                           EXCEPT WHERE NOTED ON PLAN AND ASSOCIATED DESIGN DRAWINGS, ALL
                                                                                                                                                                                                                                           IN-GROUND SERVICES WITHIN THE PROPERTY BOUNDARY INCLUDING BUT NOT
                                                                                                                                                                                                                                           LIMITED TO: STORMWATER DRAINAGE, SEWERAGE, WATER, GAS, ELECTRICAL
                                                          W




                                                                                                                                                                                                                                           AND COMMUNICATIONS TO BE SAFELY BE DISCONNECTED, REMOVED FROM
                                                                                                                                                                                                                                           SITE AND CAPPED OFF AT SITE BOUNDARY. CONTRACTOR TO ARRANGE ALL
                                                                                                                                                                                                                                           NECESSARY APPLICATIONS AND PERMITS WITH THE RELEVANT AUTHORITIES.
                                                                                                                                                                                                                                           SERVICES TO BE CAPPED IN ACCORDANCE WITH RELEVANT SERVICE
                                                                                                                                                                                                                                           PROVIDER SPECIFICATIONS AND STANDARD DETAILS
                                                          W




                                                                                                           CLIENT DETAILS:                                   PROJECT ADDRESS:                  APPROVED BY:              PROJECT NAME:
                                                          W




                                                                                                                                                                                                                         PROPOSED RESIDENTIAL DUPLEX
                                                                                                                      INTEGRA PARTNERSHIPS                                                                               TITLE:                                STATUS:

                                                                                                                                                                        22 GRANT STREET                                  LAYOUT PLAN                           FOR APPROVAL - NOT FOR
                                                          W




            © ABN 89 647 469 707
                                                                                                                                                                      NOOSA HEADS, QLD, 4567         NATHAN WAGSTAFF                                           CONSTRUCTION
             75 NOOSA DRIVE                                                                                                                                                                             RPEQ: 20693
                                                                                                           SCALE:
          NOOSA HEADS, QLD 4567                                                                                                                                                                           CPEng
              +61 7 5211 1003                       REV   DATE   DESCRIPTION             DWN   CHK   APP
                                                                                                                                       1:100                                                          DATE: 23/09/2022
                                                                                                                                                                                                                         DRAWING NUMBER:                       PROJECT NUMBER:                           SHEET REV:
                                                          W




                                                                                                                                                                                                                                                                                                          SIZE:
          RECORCONSULTING.COM                                        REVISIONS
                                                                                                                             DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                         010                                   20220218                                   A1 01

Page 17

N

                                                                                                                                                                                                                                           CUT/FILL DEPTH RANGE
                                                                                                                                                                                                                                           Lower_value Upper_value   Colour

                                                                                                                                                                                                                                           -0.9   to     -1.    M

                                                                                                                                                                                                                                           -0.8   to     -0.9   M

                                                                                                                                                                                                                                           -0.7   to     -0.8   M

                                                                                                                                                                                                                                           -0.6   to     -0.7   M
                                                                                  D                                                       C
                                                                                 021                                                     021                                                                                               -0.5   to     -0.6   M
    GRANT STREET




                                                                                                                                                                                                                                           -0.4   to     -0.5   M

                                                                                                                                                                                                                                           -0.3   to     -0.4   M

                                                                                                                                                                                                                                           -0.2   to     -0.3   M

                                B                                                                                                                                             B                                                            -0.1   to     -0.2   M
                               021                                                                                                                                           021
                                                                                                                                          FL 24.8m AHD                                                                                     0      to     -.1    M
                                                                  FL 21.4m AHD

                                                                                                                                                                                                                                           0      to     .1     M

                                                                                                                                                                                                                                           0.1    to     0.2    M

                                                                                                                                                                                                                                           0.2    to     0.3    M

                                                                                                                                                                                                                                           0.3    to     0.4    M

                                                                                                                                                                                                                                           0.4    to     0.50   M

                                                                                                                                                                                                                                           0.5    to     0.6    M

                                                                  FL 21.4m AHD                                                             FL 24.8m AHD
                               A                                                                                                                                             A                                                             0.6    to     0.7    M
                              021                                                                                                                                           021
                                                                                                                                                                                                                                           0.7    to     0.8    M

                                                                                                                                                                                                                                           0.8    to     0.9    M

                                                                                                                                                                                                                                           0.9    to     1      M




                                                                                  D                                                       C
                                                                                 021                                                     021




                                                                                                                                                                                                                                      EARTHWORKS VOLUMES
                                                                                                                                                                                                                                      EARTHWORKS VOLUMES FROM
                                                                                                                                                                                                                                      EXISTING SURFACE TO DESIGN
                                                                                                                                                                                                                                      SURFACE
                                                                                                                                                                                                                                      CUT = 506m³
                                                                                                                                                                                                                                      FILL = 30m³
                                                                                                                                                                                                                                      BALANCE = 476m³


                                                                                                                                                                                                                                 NOTE:
                                                                                                                                                                                                                                 EXCEPT WHERE NOTED ON PLAN AND ASSOCIATED DESIGN
                                                                                                                                                                                                                                 DRAWINGS, ALL IN-GROUND SERVICES WITHIN THE PROPERTY
                                                                                                                                                                                                                                 BOUNDARY INCLUDING BUT NOT LIMITED TO: STORMWATER
                                                                                                                                                                                                                                 DRAINAGE,   SEWERAGE,   WATER,     GAS,  ELECTRICAL  AND
                                                                                                                                                                                                                                 COMMUNICATIONS TO BE SAFELY BE DISCONNECTED, REMOVED
                                                                                                                                                                                                                                 FROM SITE AND CAPPED OFF AT SITE BOUNDARY. CONTRACTOR TO
                                                                                                                                                                                                                                 ARRANGE ALL NECESSARY APPLICATIONS AND PERMITS WITH THE
                                                                                                                                                                                                                                 RELEVANT AUTHORITIES. SERVICES TO BE CAPPED IN
                                                                                                                                                                                                                                 ACCORDANCE      WITH    RELEVANT      SERVICE   PROVIDER
                                                                                                                                                                                                                                 SPECIFICATIONS AND STANDARD DETAILS




                                                                                       CLIENT DETAILS:                                             PROJECT ADDRESS:                  APPROVED BY:              PROJECT NAME:

                                                                                                                                                                                                               PROPOSED RESIDENTIAL DUPLEX
                                                                                                  INTEGRA PARTNERSHIPS                                                                                         TITLE:                             STATUS:

                                                                                                                                                              22 GRANT STREET                                  BULK EARTHWORKS                    FOR APPROVAL - NOT FOR
       © ABN 89 647 469 707
                                                                                                                                                            NOOSA HEADS, QLD, 4567         NATHAN WAGSTAFF     LAYOUT PLAN                        CONSTRUCTION
       75 NOOSA DRIVE                                                                                                                                                                         RPEQ: 20693
                                                                                       SCALE:
    NOOSA HEADS, QLD 4567                                                                                                                                                                       CPEng
        +61 7 5211 1003              REV   DATE   DESCRIPTION     DWN     CHK    APP
                                                                                                                   1:100                                                                    DATE: 23/09/2022
                                                                                                                                                                                                               DRAWING NUMBER:                    PROJECT NUMBER:                      SHEET REV:
                                                                                                                                                                                                                                                                                        SIZE:
    RECORCONSULTING.COM                               REVISIONS
                                                                                                         DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                               020                                 20220218                            A1 01

Page 18

                                                                                                  STAIRS                      GARAGE                          GARAGE                   STAIRS
                                                                                                  UNIT 2                       UNIT 2                          UNIT 1                  UNIT 1




                                                                                                                             FFL 21.4                       FFL 21.4




                                                                                                                              D      BULK EARTHWORKS
                                                                                                                              -      SECTION               SCALE 1:100




                                                                                               STAIRS                       DINING                          DINING                  STAIRS
                                                                                               UNIT 2                       UNIT 2                          UNIT 1                  UNIT 1




                                                                                                                            FFL 24.8                      FFL 24.8



                                                                                                                             C    BULK EARTHWORKS
                                                                                                                             -    SECTION                 SCALE 1:100


                                                                                                                                                                                      PATH                      POOL
                                                                                                                                                                                      UNIT 2                    UNIT 2

                                                                       DRIVEWAY                                     GARAGE                                               DINING                               FFL 26.2
                                                                                                                     UNIT 2                                              UNIT 2
                                                                                                                                                                         FFL 24.8               FFL 24.7




                                                                                 FFL 21.4                          FFL 21.4



                                                                                                                             B    BULK EARTHWORKS
                                                                                                                             -    SECTION                 SCALE 1:100




                                                                                                                                                                                     PATH                   POOL
                                                                                                                                                                                     UNIT 1                 UNIT 1

                                                                       DRIVEWAY                                GARAGE                                               DINING                                 FFL 26.2
                                                                                                                UNIT 1                                              UNIT 1
                                                                                                                                                                     FFL 24.8                  FFL 24.7




                                                                         FFL 21.4                            FFL 21.4


                                                                                                                             A    BULK EARTHWORKS
                                                                                                                             -    SECTION                 SCALE 1:100




                                                                        CLIENT DETAILS:                                                        PROJECT ADDRESS:                                            APPROVED BY:              PROJECT NAME:

                                                                                                                                                                                                                                     PROPOSED RESIDENTIAL DUPLEX
                                                                                    INTEGRA PARTNERSHIPS                                                                                                                             TITLE:                  STATUS:

                                                                                                                                                          22 GRANT STREET                                                            EARTHWORKS              FOR APPROVAL - NOT FOR
 © ABN 89 647 469 707
                                                                                                                                                        NOOSA HEADS, QLD, 4567                                   NATHAN WAGSTAFF     LONGITUDINAL SECTIONS   CONSTRUCTION
   75 NOOSA DRIVE                                                                                                                                                                                                   RPEQ: 20693
                                                                        SCALE:
NOOSA HEADS, QLD 4567                                                                                                                                                                                                 CPEng
    +61 7 5211 1003     REV   DATE   DESCRIPTION     DWN   CHK   APP
                                                                                              AS INDICATED                                                                                                        DATE: 23/09/2022
                                                                                                                                                                                                                                     DRAWING NUMBER:         PROJECT NUMBER:   SHEET REV:
                                                                                                                                                                                                                                                                                SIZE:
RECORCONSULTING.COM                      REVISIONS
                                                                                            DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                     021                     20220218          A1 01

Page 19

                                                                                              SEDIMENT RELEASE GUIDELINES                                                                       RUN-OFF FROM THE IMMINENT RAINFALL AND                                       ADDITIONAL CONTROL MEASURES AS DEEMED                 SUPERINTENDENT FOR THE LOCATION OF THE SITE
                                                                                                                                                                                                RUN-OFF.                                                                     NECESSARY THROUGHOUT CONSTRUCTION.                    ACCESS POINT AND WASH DOWN AREA WHICH ARE TO
             SEDIMENT AND EROSION CONTROL:                                                   1.  ALL RELEASES OF STORMWATER CAPTURED ONSITE,                                              2.3. ALL REASONABLE AND PRACTICABLE STEPS HAVE                                3.   THE CONTRACTOR IS RESPONSIBLE TO MAINTAIN ALL         BE MAINTAINED THROUGHOUT THE CONSTRUCTION
             CONTRACTOR TO ALLOW FOR PROVISION OF ALL                                            UNLESS OTHERWISE NOTED IN THIS STANDARD, MUST                                                  BEEN TAKEN TO TREAT THE WATER WITHIN                                         SEDIMENT CONTROL DEVICES IN A FUNCTIONAL              PERIOD.
             REQUIRED SEDIMENT AND EROSION CONTROL                                               NOT EXCEED THE FOLLOWING LIMITS:                                                               BEST-PRACTICE TIME FRAMES;                                                   ORDER AND REPLACE ALL BLOCKED SEDIMENT             8. IF SEDIMENT AND EROSION CONTROL DEVICES HAVE
             DEVICES IN ACCORDANCE WITH IECA AND COUNCIL                                       1.1. 50mg/L OF TOTAL SUSPENDED SOLIDS (TSS) AS A                                           2.4. FLOCCULENT HAS BEEN APPROPRIATELY APPLIED                                     DEVICES AS REQUIRED UNTIL SUCCESSFUL OFF              BEEN FOUND TO BE DIFFERENT OR FAILED IN SERVICE,
             POLICIES AND GUIDELINES                                                                 MAXIMUM CONCENTRATION;                                                                     AND THE CONCENTRATION OF TSS IN THE                                          MAINTENANCE OF WORKS.                                 CORRECTIVE ACTION IS TO BE UNDERTAKEN
                                                                                               1.2. TURBIDITY (NTU) VALUE LESS THAN 10% ABOVE                                                   CAPTURED WATER HAS ALREADY SIGNIFICANTLY                                4.   CONSTRUCTION OF ALL SEDIMENT MANAGEMENT               IMMEDIATELY WHICH MAY INCLUDE AMENDMENTS'
                                                                                                     BACKGROUND;                                                                                DECREASED.                                                                   DEVICES TO THE SATISFACTION OF THE                    ADDITIONS TO THE ORIGINAL APPROVED EROSION
                                                                                               1.3. pH VALUE MUST BE IN THE RANGE 6.5 TO 8.5                                            3. FOR ALL OTHER STORMWATER RELEASES, FLOWS AND                                      SUPERINTENDENT. SHALL BE COMPLETED AND                CONTROL PLANS. SUCH AMENDMENTS ARE TO BE
                                                                                                     EXCEPT WHERE, AND TO THE EXTENT THAT, THE                                              DISCHARGES FROM THE SITE, THE RELEASE LIMIT                                      EFFECTIVE PRIOR TO:                                   APPROVED BY SUPERINTENDENT, IF DEEMED
                                  LEGEND                                                             NATURAL RECEIVING WATERS LIE OUTSIDE THIS                                              PRESCRIBED IN (1a) ABOVE MUST NOT BE EXCEEDED                                    a. STRIPPING OF TOPSOIL AND GRASS.                    NECESSARY AND RELEVANT.
                                                                                                     RANGE.                                                                                 UNLESS THE DEVELOPMENT IS IN FULL COMPLIANCE                                     b. BULK EARTHWORKS TO THE SITE.                    9. OVERALL
                                                                                             2. THE CONCENTRATION OF TSS RELEASED BY                                                        WITH THIS STANDARD.                                                              c. SERVICES INSTALLATION.                             a. TEMPORARY DRAINAGE CONTROL FLOWS SHOULD
                            |S|        SEDIMENT FENCE
                                                                                                 DEWATERING MAY ONLY EXCEED 50mg/L WHERE IT                                                                                                                                  d. PAVEMENT CONSTRUCTION                                  BE DIVERTED AROUND THE WORK SITE WHERE
                                                                                                 CAN BE DEMONSTRATED AND SUPPORTED THROUGH                                              SEDIMENT CONTROL                                                                5.   ALL SEDIMENT MANAGEMENT MEASURES ARE TO                   POSSIBLE.
                                       CONSTRUCTION ENTRY
                                                                                                 DOCUMENTATION THAT:                                                                                                                                                         REMAIN IN PLACE UNTIL INSTRUCTION IS RECEIVED IN      b. ALL DRAINAGE, EROSION AND SEDIMENT
                                                                                                                                                                                        1. ALL SEDIMENT AND EROSION CONTROL MEASURES TO                                      WRITING FROM THE SUPERINTENDENT TO REMOVE                 CONTROLS TO BE INSTALLED AND BE
                                                                                               2.1. FURTHER SIGNIFICANT RAINFALL IS FORECAST TO
                                                                                                                                                                                           BE IN ACCORDANCE WITH INTERNATIONAL EROSION                                       ALL OR PART OF THE SILT CONTROL APPLICATIONS.             OPERATIONAL BEFORE COMMENCING UP-SLOPE
                                                                                                     OCCUR BEFORE THE TSS CONCENTRATION IS
                                                                                                                                                                                           CONTROL ASSOCIATION (IECA) AUSTRALIA GUIDELINES                              6.   THE BULK EARTHWORKS AND SEDIMENT CONTROL                  EARTHWORKS.
                                                                                                     LIKELY TO BE REDUCED TO 50mg/L;
                                                                                                                                                                                           AND THE SPECIFICATIONS.                                                           LAYOUT PLAN SHALL BE READ IN CONJUNCTION WITH         c. IN AREAS WHERE RUNOFF TURBIDITY IS TO BE
                                                                                               2.2. RELEASING A HIGHER CONCENTRATION OF TOTAL
                                                                                                                                                                                        2. SEDIMENT AND EROSION CONTROL DETAILS SHOWN                                        THE APPROVED DRAWINGS.                                    CONTROLLED, EXPOSED SURFACES TO BE EITHER
                                                                                                     SUSPENDED SOLIDS WILL RESULT IN A BETTER
                                                                                                                                                                                           ARE MINIMUM REQUIREMENTS. IT IS THE                                          7.   PRIOR TO COMMENCEMENT OF CONSTRUCTION                     MULCHED, COVERED WITH EROSION CONTROL
                                                                                                     ENVIRONMENTAL OUTCOME BY PROVIDING
                                                                                                                                                                                           CONTRACTORS RESPONSIBILITY TO INSTALL                                             APPROVAL IS TO BE OBTAINED FROM THE                       BLANKETS OR TURFED IF EARTHWORKS ARE
                                                                                                     STORAGE FOR THE CAPTURE AND TREATMENT OF
                                                                                                                                                                                                                                                                                                                                       EXPECTED TO BE DELAYED FOR MORE THAN 14
                                                                                                                                                                                                                                                                                                                                       DAYS.

                                                                                                                                                                                                                                                                                                                                SEDIMENT FENCE
                                                                                                                                                                                                                                                                                                                                10. FOR SEDIMENT FENCE STANDARD DETAIL AND
                                                                                                                                                                                                                                                                                                                                    SPECIFICATION REFER TO INTERNATIONAL EROSION
N                                                                                                                                                                                                                                                                                                                                   CONTROL ASSOCIATION AUSTRALASIA (IECA) BEST
                                                                                                                                                                                                                                                                                                                                    PRACTICES STANDARD DRAWINGS SF-01 AND SF-02
                                                                                                                                                                                                                                                                                                                                    SEDIMENT FENCE.

                                                                                                                                                                                                                                                                                                                                TEMPORARY CONSTRUCTION ENTRY/EXIT
                                                                                                                                                                                                                                                                                                                                11. FOR CONSTRUCTION ENTRY / EXIT STANDARD DETAIL
                                                                                                                                                                                                                                                                                                                                    AND SPECIFICATION REFER TO INTERNATIONAL

                                                                                                                                         BU CP                                                                                                                                                                                      EROSION CONTROL ASSOCIATION AUSTRALASIA (IECA)

                                                                                                                                           P1                                                                                                                                                                                       BEST PRACTICES STANDARD DRAWINGS EXIT-01 AND
                                                            22




                                                                                                                                                                                                                                                                                                                                    EXIT-02 CONSTRUCTION EXIT - ROCK PAD
                                                                                                                                              37                                                                                                                                                                                    (CONSTRUCTION SITES ONLY), EXIT-03 - ROCK PADS
                                                                                                                                                 3            1
                                                                                                                                                                                                                                                                                                                                    FOR BUILDING SITES AND EXIT-04 AND EXIT-05
                                                                         22.5




                                                                                                                                                                                                                                                                                                                                    CONSTRUCTION EXIT - VIBRATION GRID.

                                                                                                                                                                                                                                                                                                                                KERB INLET
                                                                                                                                                                                                                                                                                                                                12. FOR KERB INLET STANDARD DETAIL AND
                                                                                                                 23.5




                                                                                                                                                                                                                          26.5




                                                                                                                                                                                                                                                           27.5
                                                                                                                                                                                               25.




                                                                                                                                                                                                            26
                                                                                                                                                                     24.5
                                                                                              23




                                                                                                                                 24
                                                                          |S|          |S|          |S|             |S|           |S|            |S|          |S|            |S|        |S|           |S|        |S|      |S|           |S|         |S|           |S|




                                                                                                                                                                                                                                              27
                                                                                                                                                                                                                                                                                                                                    SPECIFICATION REFER TO INTERNATIONAL EROSION




                                                                                                                                                                                   25




                                                                                                                                                                                                5
                                                                                                                                                                                                                                                                                                                                    CONTROL ASSOCIATION AUSTRALASIA (IECA) BEST
                                                                                                                                                                                                                                                                                                                                    PRACTICES STANDARD DRAWING ESC-03 KERB INLET
      GRANT STREET




                                                                                                                                                                                                                                                                                                                                    SEDIMENT TRAPS
                                                                  |S|




                                                                                                                                                                                                                                                                                                                                REVEGETATION
                                                                                                                                                                                                                                                                                                                                13. FOR REVEGETATION STANDARD SPECIFICATION
                                                                                                                                                                                                                                                                                                                                    REFER TO INTERNATIONAL EROSION CONTROL
                                                                  |S|




                                                                                                                                                                                                                                                                                                                                    ASSOCIATION AUSTRALASIA (IECA) BEST PRACTICES
                                                                                                                                                                                                                                                                                                                                    STANDARD DRAWING R-01 REVEGETATION GENERAL.

                                                                                                                                                                                                                                                                                                                                FIELD INLET


                                                                                                                                                              90
                                                                                                                                                                                                                                                                                                                                14. FOR FIELD INLET STANDARD DETAIL AND
                                                                                                                                                                                                                                                                                                                                    SPECIFICATION REFER TO INTERNATIONAL EROSION
                                                                                                                                                                                                                                                                                                                                    CONTROL ASSOCIATION AUSTRALASIA (IECA) BEST
                                                                                                                                                                                                                                                                                                                                    PRACTICES STANDARD DRAWING ESC-02 GRATED
                                                                                                                                                                                                                                                                                                                                    STORMWATER (FIELD) INLET SEDIMENT TRAP.

                                                                                                                                                                                                                                                                                                                                OPERATION AND MAINTENANCE
                                                                                                                                                                                                                                                                                                                                15. IN ACCORDANCE WITH NC ESC GUIDELINES, ALL ESC
                                                                                                                                                                                                                                                                                                                                    MEASURES SHALL BE INSPECTED:
                                                                                                                                                                                                                                                                                           BU        CP                             · AT LEAST DAILY (WHEN WORK IS OCCURRING ON
                                                                                                                                                                                                                                                                                                 P5                                    SITE) OR WEEKLY (WHEN WORK IS NOT OCCURRING
                              PROVIDE CONSTRUCTION
                                                                                                                                                                                                                                                                                                    71
                                                                  |S|




                                                                                                                                                                                                                                                                                                                                       ON SITE)
                              SHAKEDOWN ENTRY AS
                              PER NSC STD DWG ESC-01                                                                                                                                                                                                                                                   4                            · WITHIN 24 HOURS OF EXPECTED RAIN; AND
                                                                                                                                                                                                                                                                                                                                    · WITHIN 18 HOURS OF A RAINFALL EVENT (I.E. AN
                                                                                                                                                                                                                                                                                                                                       EVENT OF SUFFICIENT INTENSITY AND DURATION TO
                                                                  |S|




                                                                                                                                                                                                                                                                                                                                       MOBILISE SEDIMENT ON SITE).
                                                  21.5




                                                                                                                                                                                                                                                                                                                                17. IN ACCORDANCE WITH NC ESC GUIDELINES,
                                                                                                                                                                                                                                                              27                                                                    MAINTENANCE OF ESC MEASURES SHALL OCCUR IN
                                                                                                                                                                                               25.5
                                                                                                                                                       24.5




                                                                                                                                                                                                                                                   27|S|
                                                                                                                                                                            25




                                                                                                                                                                                                                                 26.5
                                                                                                                                                                                                                                                                 .5
                                                                                                                                                                                                                 26


                                                                                                                                                                                                                                                                                                                                    ACCORDANCE WITH THE FOLLOWING TABLE:
                                                                                                          23.5




                                                                          |S|          |S|          |S|                 |S|        |S|           |S|           |S|           |S|         |S|          |S|         |S|
                                                                                                                                 24




                                                                                                                                                                                                                           |S|          |S|                     |S|
                                                                                             23
                                                                                22.5




                                                                                                                                                                                                                                                                                                                                                            MAINTENANCE SCHEDULE
                                                                                                                                                                                                                                                                                                                                                                                   TIMEFRAME FOR COMPLETION
                                                                                                                                                                                                                                                                                                                                    ESC MEASURES        MAINTENANCE TRIGGER
                                                                                                                                                                                                                                                                                                                                                                                        OF MAINTENANCE
                                                                 22




                                                                                                                                                                                                                                                                                                                                                        WHEN SETTLED SEDIMENT
                                                                                                                                                                                                                                                                                                                                    SEDIMENT BASIN                                    WITHIN 7 DAYS OF THE
                                                                                                                                                                                                                                                                                                                                                      EXCEEDS THE VOLUME OF THE
                                                                                                                                                                                                                                                                                                                                   (WHERE UTILISED)                                       INSPECTION
                                                                                                                                                                                                                                                                                                                                                        SEDIMENT STORAGE ZONE
                                                                                PROVIDE SEDIMENT FENCE                                                                                                                                                                                                                               OTHER ESC        1/3 OF THE CAPACITY OF ESC
                                                                                                                                                                                                                                                                                                                                                                                     BY THE END OF THE DAY
                                                                                TO DOWNSTREAM                                                                                                                                                                                                                                        MEASURES           MEASURES IS EXCEEDED
                                                                                BOUNDARY AS PER NSC                                                                                                                                                                                                                             REPORTING
                                                                                STD DWG ESC-04 & ESC-05                                                                                                                                                                                                                         18. CONTRACTOR IS TO PROVIDE AN UPDATED PROGRAM
                                                                                                                                                                                                                                                                                                                                    OF ESC MAINTENANCE AND CONTROL OF ALL STAGES
                                                                                                                                                                                                                                                                                                                                    OF WORK FOR APPROVAL BY THE SUPERINTENDENT.

                                                                                                                               CLIENT DETAILS:                                                               PROJECT ADDRESS:                                                     APPROVED BY:                PROJECT NAME:

                                                                                                                                                                                                                                                                                                              PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                          INTEGRA PARTNERSHIPS                                                                                                                                                TITLE:                                     STATUS:

                                                                                                                                                                                                                          22 GRANT STREET                                                                     EROSION AND SEDIMENT                       FOR APPROVAL - NOT FOR
     © ABN 89 647 469 707
                                                                                                                                                                                                                        NOOSA HEADS, QLD, 4567                                          NATHAN WAGSTAFF       CONTROL LAYOUT PLAN                        CONSTRUCTION
       75 NOOSA DRIVE                                                                                                                                                                                                                                                                      RPEQ: 20693
                                                                                                                               SCALE:
    NOOSA HEADS, QLD 4567                                                                                                                                                                                                                                                                    CPEng
        +61 7 5211 1003                     REV    DATE          DESCRIPTION                      DWN      CHK           APP
                                                                                                                                                                    1:100                                                                                                                DATE: 23/09/2022
                                                                                                                                                                                                                                                                                                              DRAWING NUMBER:                            PROJECT NUMBER:                           SHEET REV:
                                                                                                                                                                                                                                                                                                                                                                                                    SIZE:
    RECORCONSULTING.COM                                                 REVISIONS
                                                                                                                                                       DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                                                              030                                        20220218                                   A1 01

Page 20

                                                                                                                             1 METER MAX.               STAR PICKETS

                                             PROVIDE WASH WATER FOR                                                                                     DROP INLET
TIMBER SLEEPER OR METAL                                                                                                                                 WITH GRATE
                                             TRUCKS EXITING SITE
GRID 100mm HIGH AND




                                                                                                                                                                                                                                                                                                                                   500 - 600mm
                                             MIN LENG                                                                                                   WIRE OR STEEL MESH
SPACED AT 300mm CTS                                                                                                                                     (14 GAUGE x 150mm                                                                                                    WRAP FILTER
                                                      T   H 10m                                                                                         OPENINGS) WHERE GEOTEXTILE                                                                                           CLOTH OVER GRATE
                                                                         BERM 300 HIGH MIN
  CONSTRUCTION SITE                                                                                                                                     IS NOT SELF-SUPPORTING
                                                                                                                                                        WOVEN GEOTEXTILE                                                                                                                                                                                                     1.5m STAR
                                                                               EXISTING ROADWAY                                                                                                                                                                                                                                                                              PICKETS
                                                                                                                                                                                                                                                                                                                                                                             AT MAX. 2.5m CENTRES

  GEOTEXTILE FABRIC                                                                                                                                STAR PICKET                                                                                                                                                                                                            SELF-SUPPORTING
                                                                                                                                                   FITTED WITH                                                                                                                                                                                                            GEOTEXTILE
                                             50-75mm GRAVEL BED                                                                                    SAFETY CAP                                                                                                                                                                                                                        OW
                                             MIN 200mm THICK                                                                                                                                                                                                                                                                                                          DIRECTION OF FL
                 RUNOFF FROM PAD DIRECTED                                                           SANDBAGS                                 WOVEN GEOTEXTILE
                 TO SEDIMENT TRAP
                                                                                                                                                      RUNOFF                                                                               WRAP FILTER
                                                                                                                                                                                                                   RUNOFF                                                                                                                                                    ON SOIL, 150mm x 100mm
           TEMPORARY CONSTRUCTION VEHICLE EXIT                                                                                                        WATER WITH                                                                           CLOTH OVER GRATE




                                                                                                                            FLOW
                                                                                                                                                                                                                   WATER WITH                                                                                                                                                TRENCH WITH
                                   SCALE: N.T.S.                                                    WATERWAY                                          SEDIMENT
                                                                                                                                                                                                                   SEDIMENT                                                                                                                                                  COMPACTED BACKFILL
                                                                                                                                                                                                                                                                                                                                                                             AND ON ROCK, SET INTO
                                                                                                                                                                                                                                                                                                                                                                             SURFACE CONCRETE




                                                                                                                                                                                                                                                                                                                                   600mm MIN.
                                                                                                    EXCAVATION
                                                                                                                                                                                                                                                          FILTERED                                                                                       SECTION DETAIL
                                                                                                                                                                             FILTERED
                                                                                                                                                                              WATER                                                                        WATER
                                                                                                                                                     GEOTEXTILE
                                                                                                    EARTH BANK                                       EMBEDDED 150mm




                                                                                                                                                                                                                                                                                                              MIN. 1.5m
                                                                                                                                                     INTO GROUND                                                                                                                                                                                                 20m MAX.
                                                                                                                                             FOR DROP INLETS AT NON-SAG POINTS,                                          GEOTEXTILE INLET FILTER TYPE B                                                                                                                         FLOW
                                                                                                                                             SANDBAGS, EARTH BANK OR EXCAVATION                                                                 SCALE N.T.S
                                                                                                                                             USED TO CREATE ARTIFICIAL SAG POINT                                                                                                                                                           STAR PICKETS AT
                                                                                                                                                                                                                                                                                                                                           MAX. 2.5m SPACINGS
                                                                                                      GEOTEXTILE INLET FILTER CONSTRUCTION NOTES:                                                                                                                                                                                          TYPICAL
                                                                                                      1. FABRICATE A SEDIMENT BARRIER MADE FROM GEOTEXTILE OR STRAW BALES.

                                                                                                      2.   PICKET SPACING TO BE A MAXIMUM 1.0m CENTRES.                                                                                                                                                                                                            PLAN

                                                                                                      3.   IN WATERWAYS, ARTIFICIAL SAG POINTS CAN BE CREATED WITH SANDBAGS
                                                                                                           OR EARTH BANKS AS SHOWN IN THE DRAWING.

                                                                                                      4.   DO NOT COVER THE INLET WITH GEOTEXTILES UNLESS THE DESIGN IS
                                                                                                                                                                                                                                                                                                                                                 DISTURBED             DIRECTION           1.5m STAR PICKETS
                                                                                                           ADEQUATE TO ALLOW FOR ALL WATERS TO BYPASS IT.
                                                                                                                                                                                                                                                                                                                                                 AREA                  OF FLOW             AT MAX. 2.5m
                                                                                                                 GEOTEXTILE INLET FILTER A                                                                                                                                                                                                                                                 CENTRES
                                                                                                                                    SCALE N.T.S

                  TIMBER SPACER                     KERB-SIDE
                  TO SUIT                           INLET




                                                                                                                                                                                                                                                                                                                                                 UNDISTURBED
                                                                                                                                                                                                                                                                                                                                                 AREAS

                                                    GRAVEL-FILLED WIRE
                                                    MESH OR GEOTEXTILE
                                                    "SAUSAGE"
                            OVERFLOW         TIMBER SPACER
  RUNOFF                                                                                                           GRADIENT OF
  WATER WITH                                 TO SUIT                                                                                                 CAN BE CONSTRUCTED       ALL BATTER
                                                                                                                   DRAIN 1% TO 5%
  SEDIMENT                                                                                                                                           WITH OR WITHOUT          GRADES 2(H):1(V)
                                                                                                                                                     CHANNEL                                                                                                                                                  SEDIMENT FENCE CONSTRUCTION NOTES:
                                                                                                                                                                              MAX.                                                                             STABILISE STOCKPILE SURFACE
                                                                                                                   DIRECTION O                                                                                                                                                                                1. CONSTRUCT SEDIMENT FENCES AS CLOSE AS POSSIBLE TO BEING PARALLEL
                                                                                                                                    F FLOW                                                                 EARTH BANK                                        2:1                                                  TO THE CONTOURS OF THE SITE, BUT WITH SMALL RETURNS AS SHOWN IN THE




                                                                                                                                                                                   300mm MIN.
    SEDIMENT                                                                                                                                                                                                                                       AX.)            SLO                                            DRAWING TO LIMIT THE CATCHMENT AREA OF ANY ONE SECTION. THE
                                                                                                                                                                                                                                              E (M                    PE
                                                                                                                                                                                                                  FLOW                  LOP                                (MA                                    CATCHMENT AREA SHOULD BE SMALL ENOUGH TO LIMIT WATER FLOW IF
      GRAVEL-FILLED WIRE                           FILTERED WATER                                                                                                                                                               2   :1 S                                      X.)
                                                                                                                                                                                                                                                                                                                  CONCENTRATED AT ONE POINT TO 50 LITRES PER SECOND IN THE DESIGN
      MESH OR GEOTEXTILE                                                                                                                                                                                                                                                                                          STORM EVENT, USUALLY THE 10-YEAR EVENT.
                                                                                                                                                         2m MIN
                                                                                                                        150mm MIN




      "SAUSAGE"
      MESH & GRAVEL INLET FILTER CONSTRUCTION NOTES:                                                                               NOTE: ONLY TO BE USED AS TEMPORARY                                                                                      SEDIMENT FENCE                                     2.          CUT A 150mm DEEP TRENCH ALONG THE UPSLOPE LINE OF THE FENCE FOR
      1. INSTALL FILTERS TO KERB INLETS ONLY AT SAG POINTS.                                                                        BANK WHERE MAXIMUM UPSLOPE LENGTH                                                                                                                                                      THE BOTTOM OF THE FABRIC TO BE ENTRENCHED.
                                                                                                                                   IS 80 METRES.
                                                                                                                                                                                                             STOCKPILE CONSTRUCTION NOTES:                                                                    3.          DRIVE 1.5m LONG STAR PICKETS INTO GROUND AT 2.5m INTERVALS (MAX.) AT
      2.   FABRICATE A SLEEVE MADE FROM GEOTEXTILE OR WIRE MESH LONGER THAN                                      DIVERSION DRAIN CONSTRUCTION NOTES:
           THE LENGTH OF THE INLET PIT AND FILL IT WITH 25mm TO 50mm GRAVEL.                                                                                                                                 1.     PLACE STOCKPILES MORE THAN 2 (PREFERABLY 5) METRES FROM EXISTING                                      THE DOWNSLOPE EDGE OF THE TRENCH. ENSURE ANY STAR PICKETS ARE
                                                                                                                 1. BUILD WITH GRADIENTS BETWEEN 1% AND 5%.
                                                                                                                                                                                                                    VEGETATION, CONCENTRATED WATER FLOW, ROADS AND HAZARD AREAS.                                          FITTED WITH SAFETY CAPS.
      3.   FORM AN ELLIPTICAL CROSS-SECTION ABOUT 150mm HIGH x 400mm WIDE.                                         2.      AVOID REMOVING TREES AND SHRUBS IF POSSIBLE - WORK AROUND THEM.
                                                                                                                                                                                                             2.     CONSTRUCT ON THE CONTOUR AS LOW, FLAT, ELONGATED MOUNDS.                                  4.          FIX SELF-SUPPORTING GEOTEXTILE TO THE UPSLOPE SIDE OF THE POSTS
      4.   PLACE THE FILTER AT THE OPENING LEAVING AT LEAST A 100mm SPACE                                                                                                                                                                                                                                                 ENSURING IT GOES TO THE BASE OF THE TRENCH. FIX THE GEOTEXTILE WITH
                                                                                                                   3.      ENSURE THE STRUCTURES ARE FREE OF PROJECTIONS OR OTHER
           BETWEEN IT AND THE KERB INLET. MAINTAIN THE OPENING WITH SPACER                                                                                                                                   3.     WHERE THERE IS SUFFICIENT AREA, TOPSOIL STOCKPILES SHALL BE LESS                                      WIRE TIES OR AS RECOMMENDED BY THE MANUFACTURER. ONLY USE
                                                                                                                           IRREGULARITIES THAT COULD IMPEDE WATER FLOW.
           BLOCKS.                                                                                                                                                                                                  THAN 2 METRES IN HEIGHT.                                                                              GEOTEXTILE SPECIFICALLY PRODUCED FOR SEDIMENT FENCING. THE USE OF
                                                                                                                   4.      BUILD THE DRAINS WITH CIRCULAR, PARABOLIC OR TRAPEZOIDAL                                                                                                                                       SHADE CLOTH FOR THIS PURPOSE IS NOT SATISFACTORY.
      5.   FORM A SEAL WITH THE KERB TO PREVENT SEDIMENT BYPASSING THE FILTER.                                                                                                                               4.     WHERE THEY ARE TO BE PLACE FOR MORE THAN 10 DAYS, STABILISE
                                                                                                                           CROSS-SECTIONS, NOT "V" SHAPED.
                                                                                                                                                                                                                    FOLLOWING THE APPROVED ESCP OR SWMP TO REDUCE THE C-FACTOR TO                             5.          JOIN SECTIONS OF FABRIC AT A SUPPORT POST WITH A 150mm OVERLAP.
      6.   SANDBAGS FILLED WITH GRAVEL CAN SUBSTITUTE FOR THE MESH OR                                                                                                                                               LESS THAN 0.10.
                                                                                                                   5.      ENSURE BANKS ARE PROPERLY COMPACTED TO PREVENT FAILURE.
           GEOTEXTILE PROVIDING THEY ARE PLACED SO THAT THEY CAN FIRMLY ABUT                                                                                                                                                                                                                                  6.          BACKFILL THE TRENCH OVER THE BASE OF THE FABRIC AND COMPACT IT
           EACH OTHER AND SEDIMENT-LADEN WATERS CANNOT PASS BETWEEN.                                                                                                                                         5.     CONSTRUCT EARTH BANKS ON THE UPSLOPE SIDE TO DIVERT WATER AROUND                                      THOROUGHLY OVER THE GEOTEXTILE.
                                                                                                                   6.      COMPLETE PERMANENT OR TEMPORARY STABILISATION WITHIN 10 DAYS OF
                                                                                                                                                                                                                    STOCKPILES AND SEDIMENT FENCES 1 TO 2 METRES DOWNSLOPE.
                                                                                                                           CONSTRUCTION.
                     MESH & GRAVEL INLET FILTER                                                                                              DIVERSION DRAIN                                                                                       STOCKPILES                                                                                       SEDIMENT FENCE
                                   SCALE N.T.S                                                                                                     SCALE N.T.S                                                                                            SCALE N.T.S                                                                                        SCALE: N.T.S.




                                                                                                                        CLIENT DETAILS:                                                         PROJECT ADDRESS:                                                                    APPROVED BY:                          PROJECT NAME:

                                                                                                                                                                                                                                                                                                                          PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                     INTEGRA PARTNERSHIPS                                                                                                                                                                 TITLE:                                                        STATUS:

                                                                                                                                                                                                           22 GRANT STREET                                                                                                EROSION AND SEDIMENT                                          FOR APPROVAL - NOT FOR
     © ABN 89 647 469 707
                                                                                                                                                                                                         NOOSA HEADS, QLD, 4567                                                           NATHAN WAGSTAFF                 CONTROL DETAILS                                               CONSTRUCTION
      75 NOOSA DRIVE                                                                                                                                                                                                                                                                         RPEQ: 20693
                                                                                                                        SCALE:
   NOOSA HEADS, QLD 4567                                                                                                                                                                                                                                                                       CPEng
       +61 7 5211 1003                       REV    DATE              DESCRIPTION             DWN    CHK     APP
                                                                                                                                              NOT TO SCALE                                                                                                                                 DATE: 23/09/2022
                                                                                                                                                                                                                                                                                                                          DRAWING NUMBER:                                               PROJECT NUMBER:        SHEET REV:
                                                                                                                                                                                                                                                                                                                                                                                                                SIZE:
   RECORCONSULTING.COM                                                       REVISIONS
                                                                                                                                             DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                                                                          031                                                           20220218               A1 01

Page 21

                                                                                                                                                                                                                                                                                                          LEGEND

                                                                                                                                                                                                                                                                                                SW       SW     PROPOSED STORMWATER DRAINAGE


                                                                                                                                                                                                                                                                                                                PROPOSED GRATE



                                                                                                                                                                                                                                                                                                                PROPOSED FIELD INLET PIT



                                                                                                                                                                                                                                                                                                                PROPOSED STORMWATER TANK




                                                                                                                                                                                                                                                                                DRAINAGE NOTES
                                                                                                                                                                                                                                                                                1. REFER HYDRAULIC DRAWINGS FOR BUILDING DRAINAGE DETAILS.
                                                                                                                                    BU CP                                                                                                                                       2. ALL ROADWORKS AND DRAINAGE (EXTERNAL TO SITE BOUNDARIES
                                                                                                                                      P1                                                                                                                                            AND/OR COUNCIL OWNED DRAINAGE PIPES INTERNAL TO THE SITE

                                                                                                                                         37                                                                                                                                         BOUNDARIES) CONSTRUCTION AND TESTING TO BE IN ACCORDANCE
                                                                                                                                                                                                                                                                                    WITH NOOSA SHIRE COUNCIL DEVELOPMENT GUIDELINES, DRAWINGS
                                                                                                                                            3     1                                                                                                                                 AND SPECIFICATIONS.
                                                                                                                                                                                                                                                                                3. ALL DRAINAGE CONSTRUCTION (PRIVATELY OWNED DRAINAGE LINES
                                                                                                                                                                                                                                                                                    INTERNAL TO THE SITE BOUNDARIES) CONSTRUCTED AND TESTED TO
                                                                                                                                                                                                                                                                                    BE IN ACCORDANCE WITH RELEVANT AUSTRALIAN STANDARDS.
DEMOLISH EXISTING STORMWATER
                                                                                                                                                                      SW
                                                                                                                                                                                                                                                                                4. ALL STORMWATER DRAINAGE PIPES INTERNAL TO SITE SHALL BE: Ø225
PIT END REMOVE APPROX 8m OF
REDUNDANT PIPE. REINSTATE
                                                                                      SW           SW          SW              SW          SW          SW        SW                                                                                                                 RRJ RCP OR APPROVED EQUIVALENT.
KERB TO MATCH EXISTING                                                                                                                                                                   SSW
                                                                                                                                                                                          W           SW          SW                                                            7. ALL STORMWATER PIPES ARE TO BE MANUFACTURED TO RELEVANT
                                                                                                                                                                                                     SW                                                                             AUSTRALIAN STANDARDS INCLUDING BUT NOT LIMITED TO AS4058 AND
    GRANT STREET




                                                                                                                                                                                                                SW                                                                  AS1992.
                                                                         SW




                                                                                                                                                                                                                              SW
                                                                                                                                                                      SW           SW          SW          SW
                                                                                                               SW                                                                                                                                                               8. STORMWATER DRAINAGE AND STRUCTURES HAVE BEEN DESIGNED
                                                                                                                                                                                                                                                                                    FOR OPERATIONAL LOADS ONLY. CONTRACTOR TO CONSIDER
                                                                                                                                                                                                                                                                                    CONSTRUCTION LOADINGS AND ENSURE NO EXCESSIVE LOADS ARE
                                                                                                                                                                                                                                                                                    PLACED ON STORMWATER DRAINAGE OR STRUCTURES.




                                                                                                                                                                                                                  SW
                                                                    SW




                                                                                                        SW
                                                                                                                                                                                                                                                                                9. CONTRACTOR TO CONFIRM LOCATION AND LEVEL OF EXISTING




                                                                                                                                                                                                                              SW
                                                                                                                                                                                                                                                                                    STORMWATER DRAINAGE WHERE CONNECTING ON TO EXISTING.
                                              0.25




                                                                                                             SW
                                                                                                                                                                                                                                                                                10. CONTRACTOR TO NOTIFY THE SUPERINTENDENT OF ANY UNSUITABLE
                                  1




                                                               SW




                                                                                                                                                                                                                                                                                    FOUNDING MATERIAL WITHIN DRAINAGE TRENCH OR STORMWATER




                                                                                                                                                                                                                  SW
                                                                                                        SW
                                                                                                                                                   90
                                                                                                                                                                                                                                    SW
                                                                                                                                                                                                                                                                                    STRUCTURES AND AWAIT DIRECTION PRIOR TO LAYING OF PIPES.
                                                                                                                                                                                                                                                                                11. ALL STORMWATER GRATES/LIDS WITHIN TRAFFICABLE AREAS TO BE
                                                                                                                                                                                                                                                                                    CLASS "D" IN ACCORDANCE WITH AS3996.
                                                                                                                                                                                                                             SW         SW
                                                          SW




                                                                                                                  SW
                                                                                                                       SW                                                                                                          SW                                           12. ALL GRATES AND LIDS SHALL SIT FLAT WITH ITS SURROUND AND NOT
                                                                                                                                                                                                                                                                                    BE LOOSE OR MOVE UNDER WHEEL LOADS.
                                   4




                                                                                                                                                                                                                                                                                13. ALL STORMWATER STRUCTURES TO BE CONSTRUCTED IN
                                                                                                                                                                                                                                    SW                                              ACCORDANCE WITH PROJECT SPECIFICATION, AND LOCAL AUTHORITY
                                                     SW




                                                                                                               SW




                                                                                                                                                                                                                        SW
                                                                                                                                                                                                                                                                                    GUIDELINES AND SPECIFICATIONS. WHERE STRUCTURES EXCEED

                                                                                                                                                                                                                                               BU
                                                                                                                                                                                                                                                                                    MAXIMUM DEPTH AS IDENTIFIED WITHIN STANDARD DRAWINGS THE
                                                                                                                                                                                                                                                       CP
                                                                                                                    SW
                                  1.5




                                                                                                                                                                                                                                                                                    CONTRACTOR WILL ENSURE AN ADEQUATE STRUCTURAL DESIGN IS
                                          0.5 SW




                                                                                                                                                                                                                              SW
                                                                                                                                                                                                                                                   P5                               UNDERTAKEN FOR THE SUBJECT STRUCTURE TO BE CONSTRUCTED
                                                                                                                                                                                                                                                      71
                                                                                                               SW




                                                                                                                                                                                                                        SW
                                                                                                                                                                                                                                                                                    TO.

                                                                                                                                                                                                                                                         4                      14. CONTRACTOR TO ENSURE ALL MANHOLE STRUCTURES COMPLY WITH
                                                                                                                                                                                                                                                                                    THE MAXIMUM DEPTH SPECIFIED IN THE PROJECT SPECIFICATION OR
                                  2.4




                                                                                                                         SW                                                                                                                                                         LOCAL AUTHORITY FROM FINISHED SURFACE LEVEL TO UNDERSIDE OF




                                                                                                                                                                                                                              SW
                                                     SW                                                                                                                    SW           SW          SW          SW SW
                                                                                                                                                                                                         SW
                                                                                                                                                                                                                                                                                    ROOF SLAB. ANY NON CONFORMANCE IS TO BE RECTIFIED AT THE
                                  1




                                                               SW                                                                                                                                         SW           SW                                                           CONTRACTORS EXPENSE.
                                                                                                                                                                                             SSW
                                                                                                                                                                                              W
                                  0.4




                                                                                 SW           SW          SW              SW          SW          SW        SW             SW                                                                                                   15. ALL FOOTPATHS TO BE CONSTRUCTED IN ACCORDANCE WITH
                                                                                                                                                                             SW                                                                                                     ARCHITECTURAL/LANDSCAPING DRAWINGS AND RELEVANT
                                                                                                                                                                                                                                                                                    AUTHORITY STANDARD DRAWINGS AND SPECIFICATIONS. FOOTPATHS
                                                                                                                                                                                                                                                                                    TO BE CONSTRUCTED WITH MAXIMUM 2.5% CROSSFALL. SHOULD
                                                                                                                                                                                                                                                                                    CONSTRUCTED FOOTPATHS EXCEED 2.5% CROSSFALL, THE
                                                                                                                                                                                                                                                                                    CONTRACTOR WILL BE REQUIRED TO RECTIFY BY REMOVING AND
                                                                                                                                                                                                                                                                                    REPLACING AT THEIR COST.
                                                                                                                                                                                                                                                                                16. CONCRETE FOOTPATH TO BE 100mm THICK N32 WITH SL72 MESH IN
                                                                                                                                                                                                                                                                                    ACCORDANCE WITH NSC STD DWG RS-065, AS1679 AND AS3600 UNO
                                                                                                                                                                                                                                                                                17. THE CONTRACTOR IS TO CONFIRM THE LOCATION AND DEPTH OF ALL
                                                                                                                                                                                                                                                                                    SERVICE CONDUITS IN VERGE PRIOR TO COMMENCING WORKS. THE
                                                                                       PROVIDE NEW ON GRADE LIP IN LINE STORMWATER
                                                                                                                                                                                                                                                                                    SUPERINTENDANT IS TO BE NOTIFIED OF ANY CONFLICTS WITH WORKS
                                                                                       INLET PIT AS PER NSC STD DWG DS-061 TO DS-063.                                                                                                                                               IDENTIFIED IN THESE PLANS IMMEDIATELY.
                                                                                       MAKE SMOOTH JOIN TO EXISTING Ø375 SW PIPE                                                                                                                                                18. ALL TRENCH EXCAVATION AND CONSTRUCTION SHALL COMPLY WITH
                                                                                       SL: 21.01                                                                                                                                                                                    THE REQUIREMENTS OF THE QUEENSLAND WORKPLACE HEALTH AND
                                                                                       IL: 19.76
                                                                                                                                                                                                                                                                                    SAFETY ACT 2011.
                                                                                                                                                                                                                                                                                19. REMOVE ANY REDUNDANT DRAINAGE OUTLETS FROM THE KERB AND
                                                                                                                                                                                                                                                                                    CHANNEL INCLUDING ANY ASSOCIATED PIPEWORK ACROSS THE
                                                                                                                                                                                                                                                                                    FOOTWAY AND REINSTATE THE KERB AND CHANNEL AND THE
                                                                                                                                                                                                                                                                                    FOOTWAY AREA IN ACCORDANCE WITH COUNCIL GUIDELINES.
                                                                                                                                                                                                                                                                                20.ROADBASE MATERIAL SHOULD BE PLACED IN LAYERS AT LEAST 75 MM
                                                                                                                                                                                                                                                                                    THICK BUT NOT EXCEEDING 150 MM IN THICKNESS, AND COMPACTED
                                                                                                                                                                                                                                                                                    TO A MINIMUM DENSITY OF 95% OF THE MAXIMUM DRY DENSITY AS
                                                                                                                                                                                                                                                                                    DETERMINED IN ACCORDANCE WITH AUSTRALIAN STANDARD
                                                                                                                                                                                                                                                                                    AS1289.6.2.
                                                                                                                                                                                                                                                                                21. CONTRACTOR TO UNDERTAKE ROADWORKS TESTING IN ACCORDANCE
                                                                                                                                                                                                                                                                                    WITH NOOSA SHIRE COUNCIL GUIDELINES, DRAWINGS AND
                                                                                                                                                                                                                                                                                    SPECIFICATIONS.
                                                                                                                                                                                                                                                                                22.INTERNAL CONCRETE TO BE 125MM THICK (EXCLUDING FINISHED
                                                                                                                                                                                                                                                                                    TREATMENTS) N32 IN ACCORDANCE WITH AS1379 AND AS3600. SL72
                                                                                                                                                                                                                                                                                    MESH MIN 50MM TOP COVER TO AS1304. MIN 100MM BASE COURSE
                                                                                                                                                                                                                                                                                    WHERE SUBGRADE CBR <=6. LOCATION AND TYPE OF INTERNAL
                                                                                                                                                                                                                                                                                    CONCRETE JOINTS TO CONFORM TO STRUCTURAL ENGINEERS SPECIFICATION.

                                                                                                                                CLIENT DETAILS:                                                          PROJECT ADDRESS:                    APPROVED BY:              PROJECT NAME:

                                                                                                                                                                                                                                                                       PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                            INTEGRA PARTNERSHIPS                                                                                                       TITLE:                                  STATUS:

                                                                                                                                                                                                                    22 GRANT STREET                                    STORMWATER LAYOUT                       FOR APPROVAL - NOT FOR
           © ABN 89 647 469 707
                                                                                                                                                                                                                  NOOSA HEADS, QLD, 4567           NATHAN WAGSTAFF     PLAN                                    CONSTRUCTION
            75 NOOSA DRIVE                                                                                                                                                                                                                            RPEQ: 20693
                                                                                                                                SCALE:
         NOOSA HEADS, QLD 4567                                                                                                                                                                                                                          CPEng
             +61 7 5211 1003            REV        DATE                  DESCRIPTION               DWN       CHK         APP
                                                                                                                                                             1:100                                                                                  DATE: 23/09/2022
                                                                                                                                                                                                                                                                       DRAWING NUMBER:                         PROJECT NUMBER:                 SHEET REV:
                                                                                                                                                                                                                                                                                                                                                SIZE:
         RECORCONSULTING.COM                                                  REVISIONS
                                                                                                                                                   DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                       040                                     20220218                        A1 01

Page 22

                                                                                                                                UP
                                                                                                                                    13
N                                                                                                                                     73
    GRANT STREET                                                                                                                         1




                                                                                                                                              90




                                                                                                                                                                                                                                                             SITE CATCHMENT AREAS
                                                                                                                                                                                                                                                                                                                             FRACTION
                                                                                                                                                                                                                                           PAVED AREA   ROAD AREA            ROOF AREA             PERVIOUS
                                                                                                                                                                                                                               NAME                                                                            AREA (M²)    IMPERVIOUS
                                                                                                                                                                                                                                              (M²)         (M²)                 (M²)               AREA (M²)
                                                                                                                                                                                                                                                                                                                                (%)

                                                                                                                       EXISTING DEVELOPMENT CATCHMENTS                                                                        EXISTING          105.5        21.5               129.9                 337.8      594.7            43.2

                                                                                                                                                                                                                              PROPOSED          161.7        75.2               197.2                 160.6      594.7            73.0

                                                                                                                                                                                                                               CHANGE           56.2         53.7                   67.3              -177.2       0              29.8




                                                                                                                                                                                                                                                                                      LEGEND
                                                                                                                                                                                                                                                                                           PERVIOUS GROUND


                                                                                                                                                                                                                                                                                           IMPERVIOUS GROUND


                                                                                                                                                                                                                                                                                           DRIVEWAY SURFACE


                                                                                                                                                                                                                                                                                            IMPERVIOUS ROOF



                                             21.17
                                           Gully Pit
                                                                IL19.82
                                                       375dia




                                                                          Telstra Pit




                                                                                          Hyd




                                                       Power pole




                                                                                                                         PROPOSED DEVELOPMENT CATCHMENTS

                                                                                                                                          CLIENT DETAILS:                                   PROJECT ADDRESS:                     APPROVED BY:                       PROJECT NAME:

                                                                                                                                                                                                                                                                    PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                                     INTEGRA PARTNERSHIPS                                                                                           TITLE:                                      STATUS:

                                                                                                                                                                                                       22 GRANT STREET                                              STORMWATER CATCHMENT FOR APPROVAL - NOT FOR
                    © ABN 89 647 469 707
                                                                                                                                                                                                     NOOSA HEADS, QLD, 4567              NATHAN WAGSTAFF            LAYOUT PLANS         CONSTRUCTION
                      75 NOOSA DRIVE                                                                                                                                                                                                        RPEQ: 20693
                                                                                                                                          SCALE:
                   NOOSA HEADS, QLD 4567                                                                                                                                                                                                      CPEng
                       +61 7 5211 1003                                                  REV     DATE   DESCRIPTION      DWN   CHK   APP
                                                                                                                                                                      1:100                                                               DATE: 23/09/2022
                                                                                                                                                                                                                                                                    DRAWING NUMBER:                             PROJECT NUMBER:          SHEET REV:
                                                                                                                                                                                                                                                                                                                                          SIZE:
                   RECORCONSULTING.COM                                                                     REVISIONS
                                                                                                                                                            DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                    045                                         20220218                 A1 01

Page 23

         N




                                                                          B99 (AU_NZ)                                                                                                                                                                                                                                                              B99 (AU_NZ)
                                                                  STANDARDS 2004                                                                                                                                                                                                                                                          STANDARDS 2004
                                                                                                               All rights reserved.                                                                                                                                                                                                                                                    All rights reserved.
                                                                           (c) 2022 Transoft Solutions, Inc.                                                                                                                                                                                                                                       (c) 2022 Transoft Solutions, Inc.




                                                                          B99 (AU_NZ)                                                                                                                                                                                                                                                              B99 (AU_NZ)
                                                                  STANDARDS 2004                                                                                                                                                                                                                                                          STANDARDS 2004
                                                                                                                          reserved.                                                                                                                                                                                                                                                               reserved.
                                                                           (c) 2022 Transoft Solutions, Inc. All rights                                                                                                                                                                                                                            (c) 2022 Transoft Solutions, Inc. All rights




AU_NZ)
                                                                                                                                                                                                                               B
                                                                                                                                                                                                                      STANDARDS 2909




                                                                                                                                                                                                                                                                                                               STAND
                                                                                                                                                                                                                                   04 (AU_NZ)




                                                                                                                                                                                                                                                                                                                     ARDS
                                                                                                                                                                                                                                                                                                                        B99
                                                                                                                                                                                                                                                                                                                          2004 (
                                                                                                                                                                                                                                                                                                                         U_NZ)  A
                                                                          B99 (AU_NZ)                                                                                                                                                                                                                                                              B99 (AU_NZ)
                                                                  STANDARDS 2004                                                                                                                                                                                                                                                          STANDARDS 2004
                                                                                                               All rights reserved.                                                                                                                                                                                                                                                    All rights reserved.
                                                                           (c) 2022 Transoft Solutions, Inc.                                                                                                                                                                                                                                       (c) 2022 Transoft Solutions, Inc.




                                                                          B99 (AU_NZ)                                                                                                                                                                                                                                                              B99 (AU_NZ)
                                                                  STANDARDS 2004                                                                                                                                                                                                                                                          STANDARDS 2004
                                                                                                                          reserved.                                                                                                                                                                                                                                                               reserved.
                                                                           (c) 2022 Transoft Solutions, Inc. All rights                                                                                                                                                                                                                            (c) 2022 Transoft Solutions, Inc. All rights




                                                                                                                                                                                                                                B99
  B9904 (AU_NZ)                                                                                                                                                                                                        STANDARDS 2004 (AU_NZ
                                                                                                                                                                                                                                   (c) 2022 Transoft
                                                                                                                                                                                                                                                       Solutions, Inc. All
                                                                                                                                                                                                                                                                             rights reserved.




                                                                                                                                                                                                                                                                                                     )
RDS 20
                                          STA
                                           NDA
                                             DSR
                                                B929004 (
                                                   AU_
                                                      NZ)




                                                                                                                                                                    CLIENT DETAILS:                                           PROJECT ADDRESS:                                                                                      APPROVED BY:                                                              PROJECT NAME:

                                                                                                                                                                                                                                                                                                                                                                                                              PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                                                               INTEGRA PARTNERSHIPS                                                                                                                                                                                                           TITLE:                STATUS:

                                                                                                                                                                                                                                                                                                  22 GRANT STREET                                                                                             VEHICLE SWEPT PATHS   FOR APPROVAL - NOT FOR
                   © ABN 89 647 469 707
                                                                                                                                                                                                                                                                                                NOOSA HEADS, QLD, 4567                    NATHAN WAGSTAFF                                                     SHEET 1 OF 2          CONSTRUCTION
                     75 NOOSA DRIVE                                                                                                                                                                                                                                                                                                          RPEQ: 20693
                                                                                                                                                                    SCALE:
                  NOOSA HEADS, QLD 4567                                                                                                                                                                                                                                                                                                        CPEng
                      +61 7 5211 1003                       REV   DATE                                                        DESCRIPTION         DWN   CHK   APP
                                                                                                                                                                                                1:100                                                                                                                                      DATE: 23/09/2022
                                                                                                                                                                                                                                                                                                                                                                                                              DRAWING NUMBER:       PROJECT NUMBER:   SHEET REV:
                                                                                                                                                                                                                                                                                                                                                                                                                                                       SIZE:
                  RECORCONSULTING.COM                                                                                                 REVISIONS
                                                                                                                                                                                      DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                                                                                                                                                              060                   20220218          A1 01

Page 24

      N




                                                                                                                                                                                                                                                                   ST AN
                                                                                                                                                                                                                                                         DA
                                                                                                                                                                                                                                                           R B
                                                                                                                                                                                                                                                            D S 99
                                                                                                                                                                                                                                                   2 004
                                                                                                                                                                                                                                          (A U_
                                                                                                                                                                                                                     B9904 (AU_NZ)




                                                                                                                                                                                                                                               N Z)
                                                                                                                                                                                                          STANDARDS 20
004 (AU_NZ)
                                                             B99
                                                     STANDARDS 2004 (AU_NZ)
                                                                                                                                                                                                                                                                                              B99
                                                                                                                                                                                                                                                                                      STANDARDS 2004 (AU_NZ)
                                                              (c) 2022 Transoft Solutions,
                                                                                             Inc. All rights reserved.
                                                                                                                                                                                                                                                                                               (c) 2022 Transoft Solutions, Inc. All rights reserved.




                                                             B99
                                                     STANDARDS 2004 (AU_NZ)
                                                              (c) 2022 Transoft Solutions,
                                                                                             Inc. All rights reserved.
                                                                                                                                                                                                                                                                                              B99
                                                                                                                                                                                                                                                                                      STANDARDS 2004 (AU_NZ)
                                                                                                                                                                                                                                                                                               (c) 2022 Transoft Solutions,
                                                                                                                                                                                                                                                                                                                              Inc. All rights reserved.




                                                                                                                                                                                                                                                       STANDA
                                                                                                                                                                                                                                              DS 20    R
                                                                                                                                                                                                                                                        B99
                                                                                                                                                                                                                                                    0 4 (
                                                                                                                                                                                                         STANDARD




                                                                                                                                                                                                                                                          A
                                                                                                                                                                                                                 S 2004 (




                                                                                                                                                                                                                                                           U
                                                                                                                                                                                                                            AU_NZ)




                                                                                                                                                                                                                                                            _NZ)
 2004 (AU_NZ)

                                                             B99
                                                     STANDARDS 2004 (AU_NZ)
                                                              (c) 2022 Transoft Solutions,
                                                                                             Inc. All rights reserved.
                                                                                                                                                                                                                                                                                              B99
                                                                                                                                                                                                                                                                                      STANDARDS 2004 (AU_NZ)
                                                                                                                                                                                                                                                                                               (c) 2022 Transoft Solutions,
                                                                                                                                                                                                                                                                                                                              Inc. All rights reserved.




                                                             B99
                                                     STANDARDS 2004 (AU_NZ)
                                                              (c) 2022 Transoft Solutions,
                                                                                             Inc. All rights reserved.
                                                                                                                                                                                                                                                                                              B99
                                                                                                                                                                                                                                                                                      STANDARDS 2004 (AU_NZ)
                                                                                                                                                                                                                                                                                               (c) 2022 Transoft Solutions,
                                                                                                                                                                                                                                                                                                                              Inc. All rights reserved.




                                                                                                                                                       CLIENT DETAILS:                                              PROJECT ADDRESS:                                       APPROVED BY:                                                                   PROJECT NAME:

                                                                                                                                                                                                                                                                                                                                                          PROPOSED RESIDENTIAL DUPLEX
                                                                                                                                                                  INTEGRA PARTNERSHIPS                                                                                                                                                                    TITLE:                STATUS:

                                                                                                                                                                                                                               22 GRANT STREET                                                                                                            VEHICLE SWEPT PATHS   FOR APPROVAL - NOT FOR
                 © ABN 89 647 469 707
                                                                                                                                                                                                                             NOOSA HEADS, QLD, 4567                              NATHAN WAGSTAFF                                                          SHEET 2 OF 2          CONSTRUCTION
                   75 NOOSA DRIVE                                                                                                                                                                                                                                                   RPEQ: 20693
                                                                                                                                                       SCALE:
                NOOSA HEADS, QLD 4567                                                                                                                                                                                                                                                 CPEng
                    +61 7 5211 1003     REV   DATE           DESCRIPTION                                                             DWN   CHK   APP
                                                                                                                                                                                   1:100                                                                                          DATE: 23/09/2022
                                                                                                                                                                                                                                                                                                                                                          DRAWING NUMBER:       PROJECT NUMBER:   SHEET REV:
                                                                                                                                                                                                                                                                                                                                                                                                   SIZE:
                RECORCONSULTING.COM                                                                                      REVISIONS
                                                                                                                                                                         DO NOT SCALE, IF IN DOUBT ASK
                                                                                                                                                                                                                                                                                                                                                          061                   20220218          A1 01

Page 25

Appendix B
DRAINS Modelling Parameters and Results




Project number 20220218                                                                                       Page 13 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Page 26

Site Catchment Areas for DRAINS Modelling
Project number:    20220218                                         Calculations:                       B. Parry
Street Address:    22 Grant St
Locality:          Noosa Heads, NSC                                 Date:                               5/09/2022


Existing Site
                                            Existing Site           Directly connected (m²)             Indirectly connected (m²)
22 Grant St        Roof                                     129.9                               129.9                                  -
                   Impervious Ground                        105.5                                 -                                  105.5
                   Driveway                                  21.5                                21.5                                  -

                   Total Imp                                256.9                               151.4                                105.5
                   Total Per                                337.8                                 -                                  337.8
                   Site Area                                594.7                               151.4                                105.5

% impervious                                                        Effective DCIA = 75% DCIA           ICIA +25% ineffective DCIA
                                                                                                113.6                                143.4
                   Impervious                               43.2%                               19.1%                                24.1%
                   Pervious                                 56.8%



Proposed Site



                                            Proposed                Directly connected (m²)             Indirectly connected (m²)
22 Grant St        Roof                                     197.2                               197.2                                  -
                   Impervious Ground                        161.7                                                                    161.7
                   Driveway                                  75.2                                75.2

                   Total Imp                                434.1                               272.4                                161.7
                   Total Per                                160.6                                 -                                  160.6
                   Site Area                                594.7                               272.4                                322.3

% impervious                                                        Effective DCIA = 75% DCIA           ICIA +25% ineffective DCIA
                                                                                                204.3                                229.8
                   Impervious                               73.0%                               34.4%                                38.6%
                   Pervious                                 27.0%

Page 27

BOM IFDs Frequent and Infrequent Storm Events
Project number:                           20220218
Street Address:                           22 Grant St
Locality:                                 Noosa Heads, NSC                                                                                                     Date:   5/09/2022

Source :                                 http://www.bom.gov.au/water/designRainfalls/revised-ifd/

Location:                                Latitude                                   -26.457
                                         Nearest Latitude            26.4625 (S)
                                         Longitude                                  153.08
                                         Nearest Longitude           153.1125 (E)

Date obtained:                                     29/03/2022


                                           Annual Exceedance
                                            Probability (AEP)
Duration                                        63.20%                       50%#             20%*           10%          5%          2%          1%
1 min                                                         174                       196           264           309         352         407         449
2 min                                                         147                       167           230           274         317         377         423
3 min                                                         138                       157           215           255         294         347         389
4 min                                                         132                       149           204           240         276         323         359
5 min                                                         126                       142           193           227         260         303         335
10 min                                                        103                       116           156           182         206         237         260
15 min                                                       87.4                      98.4           132           154         174         200         219
20 min                                                       76.3                        86           115           134         153         176         193
25 min                                                          68                     76.7           103           120         137         158         174
30 min                                                       61.6                      69.5          93.7           110         125         145         160
45 min                                                       48.7                      55.1             75         88.3         101         118         131
1 hour                                                       40.9                      46.4          63.6          75.3        86.7         102         114
1.5 hour                                                     31.8                      36.2          50.2          59.9        69.4        82.3        92.4
2 hour                                                       26.5                      30.3          42.4          50.8        59.2        70.6        79.6
3 hour                                                       20.5                      23.6          33.4          40.4        47.3        56.9        64.4
4.5 hour                                                     15.9                      18.4          26.4          32.1        37.9        45.7        51.9
6 hour                                                       13.4                      15.5          22.4          27.3        32.3        39.2        44.6
9 hour                                                       10.4                      12.2          17.8          21.8        25.9        31.4        35.8
12 hour                                                      8.76                      10.2          15.1          18.5          22        26.8        30.6
18 hour                                                      6.83                         8          11.8          14.6        17.5        21.4        24.5
24 hour                                                        5.7                     6.68          9.94          12.3        14.7        18.1        20.8
30 hour                                                      4.94                      5.79          8.63          10.7        12.8        15.8        18.2
36 hour                                                      4.38                      5.13          7.66          9.51        11.4        14.2        16.4
48 hour                                                        3.6                     4.21            6.3         7.84        9.47        11.8        13.7
72 hour                                                      2.68                      3.14            4.7         5.87        7.12        8.94        10.5
96 hour                                                      2.16                      2.52          3.77          4.72        5.74        7.24          8.5
120 hour                                                     1.81                      2.12          3.16          3.96        4.81        6.08        7.14
144 hour                                                     1.57                      1.83          2.73          3.41        4.14        5.23        6.14
168 hour                                                     1.38                      1.62            2.4            3        3.64        4.58        5.36


[OCR of page images]
 

BOM IFDs Frequent and Infrequent Storm Events

 

REC:<R

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

  

 

 

 

 

  

 

 

 

 

 

 

 

 

 

 

 

Project number: 20220218
Street Address: 22 Grant St
Locality: Noosa Heads, NSC Date: 5/09/2022
Source = http://www.bom.gov.au/water/designRainfalls/revised-ifd/
Intensit
Location: Latitude 26487 ee {AEP Anal Exceedance Proabity
Nearest Latitude 26.4625 (S) 3000
Longitude 153.08 iit. Legend |
Nearest Longitude 153.1125 (E) xs00 | lea was |
Date obtained: 29/03/2022 oe =< 3%: |]
[ oa x |]
=i H
Annual Exceedance 400 —e— 10% el
Probability (AEP) 300 o
Duration 63.20% SO%H 20%* 10% 5% 2% 1% 200 ae
Fz) 7 Fa 309 3a aa aaa
17 167 230] 77 307 377 a soo =
133 157 23 253] 234 37 39
132 19 24 2a0] 77a 323 359 os
24 12 133 27] 260] 303 335
103 ra 156 12 20 27 260]
wal 384 rH 153 774 20] 79 .
763 86 rr 134 153 74 133
8 763 103 720 137 ra 174
61.6] 69.5] 93.7| 110] 125] 145] 160] »
a5 min 187] $5 75 283 101 rrr) Fr
hour 40.9] 46.4) 63.6] 75.3| 86.7| 102| 114) 5
1.5 hour 318 36.2 50.2 59.9 69.4] 82.3 92.4] +
2 hour 26.5| 30.3 42.4] 50.8 59.2| 70.6 79.6 3
3 hour 20.5] 23.6) 33.4) 40.4} 47.3] 56.9] 64.4) 2
4.5 hour 15.9] 18.4) 26.4) 32.1 37.9] 45.7] 51.9]
[6 hour 13.4] 155 22.4] 273 323 39.2 44.6 ab 4
9 hour 10.4} 12.2| 17.8) 21.8) 25.9] 31.4) 35.8]
12 hour 8.76 10.2| 15.1) 18.5] 22] 26.8) 30.6]
18 hour 6.83 a 118 14.6 175 214] 245 ser 1
24 hour 5.7| 6.68] 9.94) 12.3] 14.7] 18.1] 20.8)
30 hour 4.94) 5.79] 8.63] 10.7] 12.8) 15.8] 18.2| i ii H i i i : i i Eb eis
36 hour 4.38) 5.13] 7.66 9.51] 11.4) 14.2| 16.4 oy 209345 wo 15 30 1 203 6 DR 1 203 4567
48 hour 3.6] 4.21 6.3] 7.84) 9.47] 11.8) 13.7]
72 hour 2.68 3.14] 47] 5.87 72 8.94] 105 Snlattes I hous I days
96 hour 2.16) 2.52| 3.77) 4.72| 5.74] 7.24) 8.5]
120 hour 1.81 2.12| 3.16) 3.96] 4.81 6.08] 7.14) Duration
144 hour 1.57] 1.83] 2.73] 3.41) 4.14) 5.23] 6.14)
168 hour 1.38] 1.62) 2.4) 3 3.64) 458) 5.36] ©Copyright Commonwealth of Australia 2016, Bureau of Meteorology (ABN 92 637 533 532)

 

 

 

 

 

 

 

 

 

 

 

Page 28

ARR Datahub Parameters
Project number:  20220218
Street Address:  22 Grant St
Locality:        Noosa Heads, NSC   Date:   5/09/2022

Page 29

oun

120 (2.0)

180 (3.0)

360 (6.0)

720 (12.0)

1080 (18.0)

1440 (24.0)

2160 (36.0)

2880 (48.0)

4320 (72.0)

Interim Climate Change Factors

RCP 4.5
2030 0.869 (4.3%)
2040 1.087 (5.3%)
2050 1.272 (6.4%)
2060 1.488 (7.5%)
2070 1.676 (8.5%)
2080 1.810 (9.2%)

2080 1.862 (9.5%)

(0.140)

19.4
(0.316)

21.9
(0.311)

21.6
(0.233)

20.4
(0.166)

133
(0.092)

39
(0.024)

24
(0.012)

0.0
(0.000)

00
(0.000)

(0.158)

215
(0.258)

25.4
(0.254)

47.4
(0.353)

412
(0.228)

37.7
(0.17)

22.4
(0.093)

16.5
(0.060)

92
(0.031)

37
(0.011)

RCP6
0.783 (3.9%)
1.014 (5.1%)
1.236 (6.2%)
1.458 (7.4%)
1.691 (8.6%)

1.944 (9.9%)

(0.164)

23.4
(0.228)

278
(0.230)

64.4
(0.393)

54.9
(0.247)

53.9
(0.204)

34.2
(0.116)

26.0
(0.076)

153
(0.041)

62
(0.015)

2.227 (11.5%)

(0.168) (0.157)
24.7 23.2
(0.209) (0.165)
30.0 73.5
(0.212) (0.433)
80.8 114.0
(0.417) (0.486)
68.1 90.4
(0.258) (0.308)
69.4 102.0
(0.220) (0.265)
45.9 95.4
(0.129) (0.219)
35.2 656
(0.085) (0.128)
21.2 48.8
(0.046) (0.086)
86 13.7
(0.017) (0.021)

ROP 8.5

0.983 (4.9%)
1.349 (6.8%)
1.773 (9.0%)

2.287 (11.5%)

2.722 (14.2%)

3.209 (16.9%)

3.679 (19.7%)

(0.151)

22.0
(0.140)

106.2
(0.553)

138.8
(0.521)

1223
(0.332)

126.5
(0.286)

132.6
(0.265)

88.3
(0.149)

69.5
(0.105)

176
(0.023)

Layer Info

Time
Accessed

Version

Note

remain unchanged

29 March 2022 05:13PM

2019_v1

ARR recommends the use of RCP4.5 and RCP 8.5
values. These have been updated to the values that
can be found on the climate change in Australia
website.

Page 30

DRAINS Modelling Results
Project number:     20220218                                                                Calculations:         B. Parry
Street Address:     22 Grant St
Locality:           Noosa Heads, NSC                                                        Date:                 5/09/2022




Pre / Post Comparison

                                 3                        3                  3
A.E.P                   Qy Pre (m /s)           Qy Post (m /s)     Qchange (m /s)           Qchange (%)
                1 EY                    0.016              0.018                    0.002                   13%
            50% AEP                     0.018              0.020                    0.002                   11%
              0.2 EY                    0.027              0.030                    0.003                   11%
            10% AEP                     0.035              0.036                    0.001                    3%
             5% AEP                     0.040              0.041                    0.001                    3%
             2% AEP                     0.047              0.047                    0.000                    0%
             1% AEP                     0.051              0.051                    0.000                    0%

Page 31

Document prepared by

RECOR Pty Ltd
ABN 89 647 469 707
75 Noosa Drive
Noosa Heads, QLD 4567
Australia

T +61 7 5211 1003
E [email protected]
W recorconsulting.com




Project number 20220218                                                                                       Page 14 of 14
File 20220218 22 Grant SWMP.docx, 2022-09-15 Revision 1

P +61 7 5211 1003                          A 75 Noosa Dr, Noosa Heads Qld 4567   E [email protected]    recorconsulting.com

Used in these records

About this file

File size
5.0 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

20220218 22 Grant SWMP.pdf · 5.0 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.