2506-46399 SRA_Response with conditions_MCU25-0059_OPW25-0080 · MCU25/0059
RA6-N SARA reference: 2506-46399 SRA Council reference: MCU25/0059 & OPW25/0080 Applicant reference: 05069 15 July 2025 Chief Executive Officer Noosa Shire Council PO Box 141 Tewantin QLD 4565 [email protected] Attention: Mark Lewis Dear Mr Lewis SARA referral agency response—32 Noosa Parade, Noosa Heads (Referral agency response given under section 56 of the Planning Act 2016) The development application described below was confirmed as properly referred by the State Assessment and Referral Agency (SARA) on 19 June 2025. Response Outcome: Referral agency response – with conditions Date of response: 15 July 2025 Conditions: The conditions in Attachment 1 must be attached to any development approval Advice: Advice to the applicant is in Attachment 2 Reasons: The reasons for the referral agency response are in Attachment 3 Development details Description: Development permit Material change of use for landing Operation work from prescribed tidal work (Pontoon and gangway) South East Queensland (North) regional office Level 4, Foundation Place 3 South Sea Islander Way, Maroochydore Page 1 of 8 PO Box 1129, Maroochydore QLD 4558
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
2506-46399 SRA
SARA role: Referral agency
SARA trigger: Schedule 10, Part 17, Division 3, Table 2, Item 1 (Planning Regulation
2017)
Development application for operational works within navigable
waterways
Schedule 10, Part 17, Division 3, Table 1, Item 1 (Planning Regulation
2017)
Development application for operational works within tidal waterway
SARA reference: 2506-46399 SRA
Assessment manager: Noosa Shire Council
Street address: 32 Noosa Parade, Noosa Heads
Real property description: Lot 15 on N21842
Applicant name: Laurison James & Irene Gail Smith
C/- Marine Structures
Applicant contact details: 18 Ron Parkinson Crescent
Corbould Park QLD 4551
[email protected]
Human Rights Act 2019 A consideration of the 23 fundamental human rights protected under
considerations: the Humans Right Act 2019 has been undertaken as part of this
decision. It has been determined that this decision does not limit
human rights.
Representations
An applicant may make representations to a concurrence agency, at any time before the application is
decided, about changing a matter in the referral agency response (s.30 Development Assessment
Rules). Copies of the relevant provisions are in Attachment 4.
A copy of this response has been sent to the applicant for their information.
For further information please contact Rosanna Nobile, Planning Officer, on (07) 5352 9777 or via email
[email protected] who will be pleased to assist.
Yours sincerely
Jamaica Hewston
Manager
cc Laurison James & Irene Gail Smith C/- Marine Structures, [email protected]
enc Attachment 1 - Referral agency conditions
State Assessment and Referral Agency Page 2 of 8
Page 3
2506-46399 SRA
Attachment 2 - Advice to the applicant
Attachment 3 - Reasons for referral agency response
Attachment 4 - Representations about a referral agency response provisions
Attachment 5 - Documents referenced in conditions
State Assessment and Referral Agency Page 3 of 8
Page 4
2506-46399 SRA
Attachment 1—Referral agency conditions
(Under section 56(1)(b)(i) of the Planning Act 2016 the following conditions must be attached to any development
approval relating to this application) (Copies of the documents referenced below are found at Attachment 5)
No. Conditions Condition timing
Development Permit – Operational work
Schedule 10, Part 17, Division 3, Table 2, Item 1 — Tidal works or work in a coastal management
district—The chief executive administering the Planning Act 2016 nominates the Director-General of
the Department of Transport and Main Roads to be the enforcement authority for the development to
which this development approval relates for the administration and enforcement of any matter relating
to the following conditions:
Approved plan
1. The development must be carried out generally in accordance with At all times
the following plan:
Site plan and water allocation, prepared by Marine
Structures, dated 21 February 2025, drawing number MS-
05069-01, Revision D
Layout plan, prepared by Marine Structures, dated 25
February 2025, drawing number MS-05069-02, Revision F
Lighting
2. (a) Light/mark all vessels, structures, plant and equipment For the duration of
associated with: works and for operation
i. the works, in accordance with the following to be maintained at all
times
specifications:
any anchors deployed must be marked with yellow
buoys and fitted with FL yellow lights fitted
lighting provided must not obscure, disguise or
otherwise interfere with the effectiveness of
navigational lighting.
ii. operations, in accordance with the following
specifications:
section 3 of AS4282-1997 Control of the obtrusive
effects of outdoor lighting
(b) Lighting provided must not obscure, disguise or otherwise
interfere with the safe navigation of other vessels, including the
effectiveness of navigational lighting.
Protection of navigable waterways
3. The construction, operation and maintenance of the pontoon and any For the duration of
ship berthed, moored or attached to the structure, must not: works, and at all times
(a) encroach into, pass over or under a navigation corridor
(b) be located in a high-risk maritime zone
(c) impede the safe navigation of other ships or boats
(d) restrict safe access to or from neighbouring structures.
4. Remove and dispose of any debris or similar obstruction For the duration or
encountered whilst undertaking the work at an appropriately licensed works
facility.
5. All piles and/or structure to be demolished both above and below the Prior to the completion
waterline must be completely extracted/removed. of the works
State Assessment and Referral Agency Page 4 of 8
Page 5
2506-46399 SRA
Schedule 10, Part 17, Division 3, Table 1, Item 1 — Tidal works or work in a coastal management
district— The chief executive administering the Planning Act 2016 nominates the Director-General of
The Department of Environment, Tourism, Science and Innovation to be the enforcement authority for
the development to which this development approval relates for the administration and enforcement of
any matter relating to the following conditions:
6. The works must be carried out generally in accordance with the For the duration of
following plans: works and to be
Site plan and water allocation, prepared by Marine maintained
Structures, dated 21 February 2025, drawing number MS-
05069-01, Revision D
Layout plan, prepared by Marine Structures, dated 25
February 2025, drawing number MS-05069-02, Revision F
Elevation, prepared by Marine Structures, dated 25 February
2025, drawing number MS-05069-03, Revision F
7. The works to which this approval relates are to be for a private At all times
purpose only.
8. Any operator and contractor involved in the works to which this During construction
approval relates
must:
(a) be provided a copy of these referral agency conditions
(b) install all measures, plant and equipment necessary to ensure
compliance with the conditions of this approval
(c) maintain such measures, plant and equipment in a proper and
efficient condition
(d) operate such measures, plant and equipment in a proper and
efficient manner.
9. For the proposed works only use materials which are free from During construction
contaminants as defined under section 11 of the Environmental
Protection Act 1994.
10. Should the works become damaged as a result of erosion, flooding At all times
or storm tide inundation, the registered landowner(s) of the subject
land shall be responsible for the removal of all debris at their own
expense.
State Assessment and Referral Agency Page 5 of 8
Page 6
2506-46399 SRA
Attachment 2—Advice to the applicant
General advice
1. Terms and phrases used in this document are defined in the Planning Act 2016, its regulation
or the State Development Assessment Provisions (SDAP) (version 3.2). If a word remains
undefined it has its ordinary meaning.
State Assessment and Referral Agency Page 6 of 8
Page 7
2506-46399 SRA
Attachment 3—Reasons for referral agency response
(Given under section 56(7) of the Planning Act 2016)
The reasons for the SARA’s decision are:
The proposed development is for a material change of use for landing and operational work for
prescribed tidal works to construct a new catwalk and pontoon system at 32 Noosa Parade,
Noosa Heads, which is formally described as Lot 15 on N21842.
The pontoon and catwalk is for private use and for one vessel with a maximum wet vessel beam of
2.8 metres.
The pontoon will be located in a canal.
The proposed structure, including any vessel berthed, moored or attached to the structure:
o will not encroach into, pass over or under a navigation corridor, and
o is not located in a high-risk maritime development zone.
SARA assessed the development against FT5 qualifying criteria checklist 4 and State code 8:
Coastal development for tidal works, of the State Development Assessment Provisions (SDAP
v3.2).
The proposed structure meets the FT5 qualifying criteria checklist 4 and complies with the SDAP,
subject to conditions to ensure:
o the development is carried out generally in accordance with the plans of development
submitted with the application
o that at all times, all lights on or above the development site do not interfere with safe
navigation in surrounding waterways
o the development does not encroach on the navigation corridor or high-risk maritime zone to
ensure the safe passage of vessels
o that debris from the development does not create a hazard to navigation
o that there is no residual material that could create a hazard to navigation.
The development complies with the assessment benchmarks of State code 8 of SDAP (version 3.2)
in that the development:
o does not adversely impact life, buildings and infrastructure from the impacts of coastal
erosion
o maintains and concerns both coastal processes and resources
o maintains appropriate public use of, and access to and along, State coastal land
o avoids impacts or, where the matters of state environmental significance cannot be
reasonably avoided, impacts are reasonably minimised and mitigated
o does not result in a significant residual impact on a matter of state environmental significance.
Material used in the assessment of the application:
the development application material and submitted plans
Planning Act 2016
Planning Regulation 2017
the SDAP (version 3.2), as published by SARA
the Development Assessment Rules
SARA DA Mapping system
section 58 of the Human Rights Act 2019
Attachment 4—Representations about a referral agency response
provisions
(page left intentionally blank)
State Assessment and Referral Agency Page 7 of 8
Page 8
2506-46399 SRA Attachment 5—Documents referenced in conditions (page left intentionally blank) State Assessment and Referral Agency Page 8 of 8
Used in these records
2506-46399 SRA_Response with conditions_MCU25-0059_OPW25-0080.pdfRelated documentApplication case desk ↗