Council archive · source document
Decision Notice - 010.2005.00000813.001 [As Published] · 132005.813
Form 6 - Decision Notice
INTEGRATED PLANNING ACT 1997, S3.5.15, IDAS DEVELOPMENT APPLICATION
File No: 2005/813 Date of Decision: 3 October 2007
1. APPLICANT DETAILS
Name: Michael J Taylor
1/28 Bryan Street
Postal address: SUNSHINE BEACH QLD 4567
Phone no: 5447 3662 Fax no:
2. PROPERTY DESCRIPTION
Street address: 28 Bryan Street Sunshine Beach
Real property Lot 0, 1 & 2 GTP 468
description:
3. OWNER DETAILS
Name: Body Corporate - Unefrolic
Postal address: 28 Bryan Street
SUNSHINE BEACH QLD 4567
4. REFERRAL AGENCIES
Referral Agency Address Basis
Nil
5. APPLICATION TYPE
Development Development Details Preliminary Development
Approval Permit
Material Change of Use Duplex Dwelling No Yes
6. DECISION DETAILS
Council decided to approve the application and grant a Preliminary Approval, subject to conditions.
7. APPLICABLE CODES
The developer must comply with the following codes for self-assessable development related to the development
approved under this Development Permit:-
Nil.
8. SUBMISSIONS
1 not properly made.
9. CONDITIONS
The approval is subject to conditions. Noosa Council’s conditions are attached.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 11 pages
Page 2
NOOSA COUNCIL IDAS Development Application Decision Notice 2 of 12
10. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit required Subject of the required Development Permit
Development Permit for Material Change of Duplex Dwelling
Use
Development Permit for Building works All Building Works
Development Permit for Operational Works Landscaping, access and/or carparking, site civil works,
stormwater drainage, frontage works and erosion and
sediment control
11. RIGHTS OF APPEAL
Rights of appeal in relation to this application are attached.
12. ASSESSMENT MANAGER
Name: Noosa Council Signature: Date: 4 October 2007
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 3
NOOSA COUNCIL IDAS Development Application Decision Notice 3 of 12
Noosa Council Conditions
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
1. A code assessable application for a Development Permit for Material Change of Use shall be lodged with
Council for assessment against the conditions of this development approval.
2. Development undertaken in accordance with this approval must generally comply with the approved plans
of development. The approved plans are numbered1c, 2c, 3c, 4c, 5c, 6c, 7c and 8c prepared and
submitted by Macchia Pty Ltd for Taylor Developments and dated 2 August 2007 and as may be amended
by the conditions herein.
3. The staircases within the rear setback area shall be relocated so that they are a minimum of 6m from the
rear boundary. The area that was occupied by these staircases shall be landscaped with deep planting.
4. The depth of the vehicle manoeuvring area in front of the building shall be reduced by 1m and the
landscaped area increased accordingly.
5. A vegetation survey shall be submitted indicating the size and species of existing vegetation on the site
and any trees proposed to be retained.
6. The development must be undertaken and operated in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other
emissions.
7. The open space and setback areas are to be landscaped in accordance with Council’s Policy on
Landscaping Guidelines and a properly prepared landscape plan prepared by a suitably qualified
Landscape Architect or Horticulturalist. Such landscaping is to be completed prior to the premises being
occupied and maintained at all times thereafter. In this regard:-
7.1. Native screening vegetation, shall be provided along the front, side and rear boundaries. The
vegetation shall include understorey plantings and a diverse range of trees ranging from 45 to 75
Litres in size.
7.2. Clothes lines, water tanks, bin enclosures and the like shall not to be located where they will
significantly reduce the effectiveness of any screening vegetation.
7.3. Mature native vegetation to be retained as appropriately identified on the vegetation survey.
7.4. Where mature trees are required to be removed as a result of the development, the plan shall
indicate appropriate, advanced, replacement plantings.
7.5. The landscaping plan shall detail treatment to the undercroft area below the rear of the building.
8. The building height shall not exceed 12.0 metres above natural ground level.
9. A verification survey of the building is to be carried out by a Licensed Surveyor and a certificate lodged
with Council at completion of the work confirming compliance with the maximum building height above
natural ground level required by the provisions of the Planning Scheme.
10. All fencing shall be setback at least 1 metre from the front property boundary, with at least half of the
fencing setback 2 metres. The area of land between the fence and the front property boundary shall be
densely landscaped to screen any fencing from the street.
11. Any deck or balcony areas are not to be enclosed with shutters, glass panelling or the like, thus remaining
as open structures.
12. All hot water systems installed shall be either solar systems; electric heat pump systems; or gas systems
(LPG or natural).
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 4
NOOSA COUNCIL IDAS Development Application Decision Notice 4 of 12
13. The proposed development shall have all kitchen, laundry and bathroom fittings that comply with the AAA
Water Conservation Rating System as defined by the AS/NZS 6400 (Water Efficient Products - Rating
and Labelling 2003) and AS/NZS 3500 (National Plumbing and Drainage Standard Part 1.2), with toilets to
comply with the AAAA Water Conservation Rating System. All tap ware and shower roses shall not
exceed a maximum flow of 9 litres per min. Dishwashers and washing machines are excluded from this
requirement.
14. Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must be submitted,
to secure performance of all conditions of this approval, prior to the issue of a Development Permit for
operational works. The cash bond or trading bank guarantee will be returned on performance of the
conditions of approval less any costs incurred by Council in respect of enforcing performance of this
permit.
15. The requirements of this development approval are to be effected, prior to the use of the premises.
Council reserves the right to call upon the bond or guaranteed sum referred to in this approval to effect
compliance with conditions.
16. The Development Permit for a material change of use of premises lapses if the use has not happened by
11 October 2011, unless an application to extend the currency is approved by Council.
Building Services
Condition Survey
17. A condition survey is to be carried out of adjoining buildings, structures and services prior to any
demolition works or construction works taking place on site. If distress already exists, a photographic
survey shall be undertaken, the distress measured and a plan to monitor changes to distress shall be
implemented.
Demolition
18. Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be protected from
damage and made safe to the standard required by the regulatory authority;
19. All infrastructure must be disconnected, capped or sealed including:-
electricity meters removed and electrical wires disconnected; and
telephone lines are disconnected; and
high speed data cables and television provider boxes are disconnected and removed to the
standard required by the regulatory authority;
20. All building materials containing asbestos, including asbestos cement sheeting or roofing and lagging,
must be removed from the building and disposed of in accordance with industry best practice.
21. Waste generated during construction must be stockpiled in a centralised location and covered as required
to prevent material being blown onto adjoining properties including the road reserve or food waste from
generating vermin. All site waste must be disposed of to an approved waste disposal facility either directly
or via an approved waste receptacle and collection service. Storage areas are to be located near the
temporary access to the site so that access can be gained with out damage to infrastructure.
22. Any damage to footpaths, street plantings, kerb and channel or roadways at the removal site, the
relocation site or between the sites must be repaired or reinstated to at least pre-existing conditions.
23. Sediment and erosion control measures must be placed on site prior to the works commencing and shall
be maintained until all works are complete. The erosion and sediment control measures shall be in
accordance with the “Best practice guidelines for control of stormwater on building sites” prepared by
Healthy Waterways (copy attached or available at www.healthywaterways.org).
24. The transportation of all materials to and from the site must be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying out materials either to or from the site
shall be covered to prevent materials including dust being windblown from the vehicle.
25. A Waste Management Plan shall be submitted for the demolition to the Environmental Health Section of
Noosa Council, prior to the development permit for building works being issued. The Plan shall contain the
following information:-
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 5
NOOSA COUNCIL IDAS Development Application Decision Notice 5 of 12
MATERIALS ON-SITE DESTINATION
Re-use and Recycling Disposal
Expected waste Estimated volume (m³) On-site *specify Off-site *specify *Specify contractor
materials proposed reuse or contractor & & landfill site
onsite recycling recycling outlet
methods
Excavation material
Green waste
Bricks
Concrete
Timber – please
specify
Plasterboard
Metals – please
specify
Asbestos
Other – please
specify
NOTE: Details of site area to be used for onsite separation, treatment and storage (including weather
protection) shall be provided on the plan drawings accompanying your application.
Site Stability
26. Building works shall be undertaken in accordance with conditions and recommendations of the report
titled “GEOTECHNICAL ASSESSMENT OF SITE STABILITY 28 BRYAN STREET, SUNSHINE BEACH”
from Soil Surveys Engineering Pty Ltd Reference Number 3-2423 BR sg 2006-07-17 (Job Number 306-
2423), and the further recommendations contained in the review of the Geotechnical report by Coffey
Geotechnics – dated 18 September 2006 (reference GEOTNATH20028-AA, copy attached herewith and
also available on request).
27. There is to be no uncontrolled discharge of water onto the slope.
28. Additional load due to fill, construction equipment or stockpiled materials should not be located on the
dune slope.
29. The use of vibratory equipment of any kind is not permitted to be used, including vibrating rollers, the use
of vibrating installation techniques for sheet piling and other construction vibrations caused by excavating,
earthmoving or demolition machinery or other similar construction techniques.
30. Boundary wall movement shall be monitored throughout construction by a RPEQ and if movement occurs
construction is to be stopped immediately and appropriate action is to be taken to arrest the movement.
Further work shall only take place after a re-assessment of the conditions on site.
31. An RPEQ is to be engaged by the client to oversee any piling works.
32. The applicant’s Geotechnical Engineer shall supervise the demolition of the existing buildings and the
excavation and construction of the proposed development to ensure that the works are carried out in
accordance with the recommendations of the abovementioned reports in order to protect the stability of
adjoining buildings and/or structures and/or land.
33. The Geotechnical Engineer will be required to be on site for the whole of the time during any excavation.
The construction of the whole of the foundations is to be supervised and directed on site by a consulting
Geotechnical engineer. No work of any kind relating to the foundations shall be carried out if he is not on
the site and supervising and directing this work. Such works shall only be carried out during dry weather
conditions and if there is a risk of sand movement occurring, all work shall be suspended until such steps,
approved by the applicant’s Geotechnical engineer and the Council’s Building Surveyor, have been taken
to ensure that no further slippage will result.
Land Development
Vehicle Access
34. A vehicular access driveway to serve the development shall be constructed from the Bryan Street frontage
of the site with a maximum width of 3.5m.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 6
NOOSA COUNCIL IDAS Development Application Decision Notice 6 of 12
35. The driveway shall be designed and constructed to Council’s design standards and to grades that prevent
vehicles from scraping and/or bottoming whilst also allowing pedestrians movements along the footpath
without any step or level difference. Should any driveways be constructed to grades that do not comply
with AS/NZS 2890.1-2004, Council will require that the driveway be removed and reconstructed to levels
that do comply.
Please note, a step between the driveway and the footpath shall be avoided, as it is preferred to have the
footpath continue at a constant grade to minimise the potential for pedestrians to trip or fall.
36. To ensure safety between vehicles exiting the site and vehicles and pedestrians in Bryan Street, the
driveway and any associated fencing or vegetation near the driveway shall comply with the minimum sight
line requirements as defined in AS/NZS 2890.1, section 3.2.4. The applicant shall demonstrate
compliance by illustrating these sight lines on the plans submitted for both Operational Works approval
and Building Works approval.
37. All vehicles shall enter and leave the site in a forward direction.
Car Parking
38. Carparking shall be provided within the site generally as shown on drawing number dwg.1c dated 2
August 2007 by Macchia Pty Ltd for Taylor Developments, except as modified herein.
39. A minimum of 4 covered carpark spaces shall be provided on site.
40. The carparking area shall be designed to comply with the provisions of AS/NZS 2890.1-2004 for user
class 1A with allowance for vehicles to enter and leave the site in a forward gear and with a minimum
head clearance (headroom) at any point of 2.2m.
41. The proposed manoeuvring area adjacent to the garages shall be sign posted to indicate that the area is
a “Turning Area Only” and that “No Parking is Permitted”. The type and location of the sign shall be clearly
indicated on any plans submitted for Operational Works approval.
42. All carparking shall be kept and maintained in a condition fit for use.
Frontage Works
43. Footpath improvements such as topsoiling, grassing, and tree planting are required to the Bryan Street
frontage of the site in accordance with Planning Scheme Policy PSP03 Landscaping Plants & Guidelines.
Grass shall be couch, free of weeds.
44. A new 1.5m wide concrete path shall be constructed along the Bryan Street frontage of the site in
accordance with Council’s design standards and to an alignment that protects any significant vegetation
or any underground services. The path shall join smoothly with the existing path located in the frontage of
No 30 Bryan Street and extend to the edge of the access driveway to No 16 Bryan Street.
45. All paths, driveways and parking areas shall be designed and constructed to ensure pedestrian safety
using non-slip materials, to produce an evenly graded surface finish, and to be in accordance with the
Disability Discrimination Act 1992 and Australian Standard 1428.1 Design for Access & Mobility.
46. All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel, footpath
paving and landscaping such as trees and grasses in accordance with Council’s Standard specifications
prior to commencement of the use permitted by this permit.
Roof Water & Stormwater Drainage
47. Roof runoff from any new dwelling shall be directed to a rainwater storage system or tank (minimum
storage 3000 litres per attached dwelling/unit) that is installed to ensure water from the tank is used for
external uses (such as watering gardens, irrigation, ornamental ponds, water features, topping-up
swimming pools, outdoor cleaning, etc) and for use in flushing of toilets internal to the dwelling. All
rainwater tanks are to be designed and installed in accordance with the Queensland Development Code
(QDC), Part 25 – Rainwater Tanks, and shall be part of the plumbing application in conjunction with the
building approval. The location and capacity of the tanks shall be clearly shown on the plans submitted
for Building Works / Operational Works approval and any overflow shall be directed to the stormwater
drainage system.
48. All stormwater drainage (including roof water overflow from the rainwater storage system) shall be
collected and discharged so there is no net increase in stormwater runoff from the site. Stormwater
drainage permitted to drain from the site shall be discharged to Council’s kerb & channel street drainage
system in Bryan Street. Plans of the drainage design shall be prepared by a Registered Professional Civil
Engineer and submitted to Council prior to obtaining a Development Permit for Operational Works.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 7
NOOSA COUNCIL IDAS Development Application Decision Notice 7 of 12
The maximum discharge of stormwater drainage allowable to Council’s kerb & channel street drainage
system at any one location is 25 litres/second.
49. All site stormwater drainage shall be by means of a gravity system.
Sewer Mains
50. The site shall be connected to Council’s existing sewerage reticulation systems and be constructed in
accordance with Council’s standards and requirements at no cost to Council.
Town Water Supply
51. The site shall be connected to Council’s existing town water supply and be constructed in accordance with
Council’s standards and requirements at no cost to Council.
52. Each individual water connection to the water reticulation system shall extend to the property boundary
and be metered. All fees for the supply of water meters shall be paid to the Council.
53. All water meters must be located outside the property boundary and in an easily assessable location to
facilitate unhindered reading by Council and/or Council’s contracted water meter readers, and not behind
fences or locked gates. In this regard approval of the water meter configuration and location must be
obtained from Council’s Water & Sewerage Capital Works Manager prior to lodgement and approval of
hydraulic drawings.
54. For Multiple Uses (including Building Format Plans, Group Title Plans, etc) the development shall be
served by:
54.1. A single Body Corporate water meter to measure the total water consumption (including fire hose
reels, but excluding fire hydrants and fire sprinkler systems), and
54.2. Individual water meters to each tenement capable of being separately rated, and
54.3. A fire service (fully testable single detector check with metered bypass), where applicable, for flows
to fire hydrants and fire sprinkler systems (excluding fire hose reels).
55. The proposed access driveway shall not adversely affect the water main or hydrant located in the Bryan
Street frontage of the property. Should the location of the hydrant conflict with the access driveway the
hydrant shall be:
55.1. relocated clear of the access driveway and associated batters or banks, or
55.2. modified to match the proposed driveway. The modifications shall include, but not be limited to,
resetting the lid and extending the spindle.
Council shall carry out all works relating to the relocation to, or modification of, the existing hydrant and
water mains at the applicant’s cost.
Earthworks
56. Earthworks required on site shall be carried out in accordance with Council’s Planning Scheme Policy
PSP5 – Engineering Design Standards, so as not to cause the additional ponding of water on any
adjoining lands or the blockage of, or interference with, any natural watercourses.
57. Earthworks carried out on site shall not affect the structural integrity of any of the existing fences and/or
buildings and/or structures and/or lands that border the development site. Fences that are affected shall
be replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard any fences
to be replaced shall be clearly shown on the plans submitted for Operational Works approval.
Erosion and Sediment Control
58. Any person acting on this permit shall prevent erosion and sediment export from leaving the site. Site
control measures such as silt fencing, controlled gravel access to the site and controlled disposal of
waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to be submitted
to the Council for approval prior to obtaining a Development Permit for Operational Works.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 8
NOOSA COUNCIL IDAS Development Application Decision Notice 8 of 12
General
59. For the following classes of work associated with development, a Development Permit for Operational
Works must be obtained prior to commencement of works relating to that class of work. The application
may combine any or all of these classes of work:-
59.1. Landscaping.
59.2. Access and/or Carparking.
59.3. Site Civil Works.
59.4. Stormwater Drainage.
59.5. Frontage Works.
59.6. Erosion & Sediment Control
60. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be submitted in
conjunction with an application for a Development Permit for Operational Works. In this regard a
DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in conjunction
with any application for Operational Works.
61. Digital detailed designs including drawings, calculations, etc shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage works. The
design shall be in accordance with Council’s Planning Scheme Policy PSP05 – Engineering Design
Standards – Roads, Drainage and Earthworks. To avoid conflict with underground pipes or services, all
existing and proposed services required by the development shall be shown on the plans.
62. To facilitate production of As Constructed drawings it is suggested that all design drawings are submitted
in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
available at www.adac.com.au).
63. Any damage caused to any public utility during the course of construction shall be repaired to Council’s
standards and at no cost to Council.
64. Any alteration of any public utility or other facilities necessitated by the development of the land or
associated construction works external to the site shall be at no cost to Council.
65. The transportation of all materials to and from the site shall be undertaken in a manner such that no
particle matter escapes onto a public road. All vehicles carrying materials either to or from the site shall
be covered to prevent materials including dust being windblown from the vehicle.
66. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer for design
intent, and a Licensed Surveyor shall certify the cadastre and the location, level and type of all services
and structures. All of which shall be submitted to Council for checking and for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage structures,
finished ground levels and pavement surface levels. The data shall be submitted in the Asset Design and
As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are available at
www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied and
accepted by Council.
Environmental Health
67. The developer must provide waste storage and disposal facilities, including an external imperviously
paved area correctly sized for all refuse and recycling containers and suitably screened from public places
and neighbouring properties.
68. Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool pumps etc)
shall comply with the following requirements:
The equipment shall be installed and located in a manner that prevents excessive noise in accordance
with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-the-spot fines) may
apply for offences.
A person must not use equipment on any day if it makes or causes noise to be made –
From 10pm to 7am: More than the lower of either –
40 dB(A)
3 dB(A) above the background noise level
No audible noise for pool pumps apply during these hours -
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 9
NOOSA COUNCIL IDAS Development Application Decision Notice 9 of 12
From 7am to 7pm: More than the lower of either –
50 dB(A)
5 dB(A) above the background noise level
From 7pm to 10pm: More than 3 dB(A) above the background noise level.
Pool pumps must not be audible at an effected premises between 10pm-7am
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 10
NOOSA COUNCIL IDAS Development Application Decision Notice 10 of 12
Local Laws, Policies & State
Regulation Requirements
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
THE FOLLOWING ADVICES ARE FOR INFORMATION PURPOSES ONLY AND DO NOT FORM
CONDITIONS OF APPROVAL
1. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if the cost of
operational works exceeds $80,000, then a portable long service leave levy is required to be paid. In
accordance with Section 77.(1) of the Act, Council is required to sight the approved form issued by the
Building and Construction Industry (Portable Long Service Leave) Authority that confirms that the
requirements of the Act have been satisfied. A statutory declaration outlining the cost of the operational
works must be submitted to Council with the lodgement of any application for operational works over the
site.
2. The applicant is advised that development contributions and infrastructure charges applicable to this
development approval have been based on the following Uses Class/ Uses and applicable quantities:-
Existing Development Approved Development
Existing Use Class / Approved Use Class /
Existing Quantity Approved Quantity
Use Use
Multiple Housing - Type Multiple Housing - Type
2 x 3 Bedroom Units 2 x 3 Bedroom Units
2 – Duplex 2 – Duplex
3. The applicant is informed that payment via credit card transaction will not be an acceptable method of
payment for development contributions conditioned in this permit or for infrastructure charge notices
issued separately.
4. Digital detailed designs including drawings, calculations, etc, shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage works. In
this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be submitted in
conjunction with any application for Operational Works. The design shall be in accordance with Council’s
Planning Scheme Policy PSP05 – Engineering Design Standards – Roads, Drainage and Earthworks.
5. To facilitate production of As Constructed drawings it is suggested that all design drawings are submitted
in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC are
available at www.adac.com.au).
6. The applicant is advised that a Compliance Permit for all plumbing and drainage works within the
boundaries of the development site shall be obtained from Council’s Plumbing Services Section prior to
obtaining a Development Permit for Building Works.
Boundary Realignment (Internal Boundaries)
7. As the development site is currently a Group Titles Plan and the proposal includes construction of
buildings over existing boundaries it will be necessary for the applicant to undertake some form of
amendment to the internal boundaries prior to obtaining a Development Permit for Building Works. The
applicant is advised to contact The Department of Natural Resources and Water to determine the relevant
type of amendment as this may require a further application to the Local Government for Lot
Reconfiguration or alternatively the subdivision of the building may be undertaken with a Building Format
Plan.
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 11
NOOSA COUNCIL IDAS Development Application Decision Notice 11 of 12
Appeal Rights
INTEGRATED PLANNING ACT 1997, IDAS DEVELOPMENT APPLICATION
The following is an extract from the Integrated (6) If an application involves assessment against
Planning Act (Chapter 4). a concurrence agency code, appeal rights for
submitters for the application are not available
Division 8 - Appeals to court relating to against the part of the approval that represents the
development applications concurrence agency’s response for the code.
Appeals by applicants Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application 4.1.29.(1) An advice agency may, within the limits of
may appeal to the court against any of the following- its jurisdiction, appeal to the court about the giving of
(a) the refusal, or the refusal in part, of a a development approval for a development
development application; application if-
(b) a matter stated in a development approval, (a) the development application involves impact
including any condition applying to the assessment; and
development, and the identification of a code (b) the advice agency told the applicant and the
1
under section 3.1.6; assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a application as a submission for an appeal.
development permit was applied for; (2) The appeal must be started within 20 business
(d) the length of a currency period; days after the day the decision notice or negotiated
decision notice is given to the advice agency as a
(e) a deemed refusal. submitter.
(2) An appeal under subsection (1)(a) to (d) must Appeals for matters arising after approval given
be started within 20 business days (the “applicant’s (co-respondents)
appeal period”) after the day the decision notice or
negotiated decision notice is given to the applicant. 4.1.30.(1) For a development approval given for a
development application, a person to whom any of
(3) An appeal under subsection (1)(e) may be the following notices have been given may appeal to
started at any time after the last day a decision on the the court against the decision in the notice-
matter should have been made.
(a) a notice giving a decision on a request for
Appeals by submitters extension of the currency period for an approval;
4.1.28.(1) A submitter for a development application (b) a notice giving a decision on a request to make a
may appeal to the court about- minor change to an approval.
(a) the giving of a development approval, including (2) The appeal must be started within 20 business
any conditions (or lack of conditions) or other days after the day the notice of the decision is given
provisions of the approval; or to the person.
(b) the length of a currency period for the approval. (3) Subsection (1)(a) does not apply if the
approval resulted from a development application
(2) The appeal must be started within 20 business (superseded planning scheme) that was assessed as
days (the “submitters appeal period”) after the day if it were an application under a superseded planning
the decision notice or negotiated decision notice is scheme.
given to the submitter.
(4) Also, a person who has made a request
(3) If a person withdraws a submission before the mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the against a deemed refusal of the request.
decision.
(5) An appeal under subsection (4) may be
(4) If an application involves both impact started at any time after the last day the decision on
assessment and code assessment, appeal rights for the matter should have been made.
submitters are available only for the part of the
application involving impact assessment. Division 9 - Appeals to court about other matters
(5) If an application is processed under section Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the (no co-respondents)
application are available only for the aspects of the
development that would have required public 4.1.31.(1) A person to whom any of the following
notification under the repealed Act. notices have been given may appeal to the court
against the decision in the notice-
(a) a notice giving a decision on a request to change
or cancel a condition of a development approval.
1
Section 3.1.6 (Preliminary approval may override local planning
instrument)
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Page 12
NOOSA COUNCIL IDAS Development Application Decision Notice 12 of 12
2
(b) a notice under section 6.1.44 giving a decision to
change or cancel a condition of a development
approval.
(2) The appeal must be started within 20 business
days after the day the notice of the decision is given
to the person.
(3) Also, a person who has made a request
mentioned in subsection (1)(a) may appeal to the
court against a deemed refusal of the request.
(4) An appeal under subsection (3) may be
started at any time after the last day the decision on
the matter should have been made.
Appeals against decisions to change approval
conditions under the repealed Act
4.1.33A.(1) A person who is dissatisfied with a
decision made on an application to change the
conditions attached to an approval given under
section 2.19(3)or section 4.4 of the repealed Act may
appeal to the court against-
(a) the decision; or
(b) a deemed refusal of the application.
(2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of
the decision is to be given to the person.
(3) An appeal under subsection (1)(b) may be
started at any time after the last day a decision on the
matter should have been made.
Appeals against local laws
4.1.33B.(1) An applicant who is dissatisfied with a
decision of a local government or the conditions
applied under a local law about the use of premises
or the erection of a building or other structure
permitted by the planning scheme may appeal to the
court against the decision or the conditions applied.
(2) The appeal must be started within 20 business
days after the day notice of the decision is given to
the applicant.
2
Section 6.1.44 (Conditions may be changed or cancelled by
assessment manager or concurrence agency in certain
circumstances)
AOP2 c:\docume~1\aop2\locals~1\temp\bcl technologies\easypdf 5\@bcl@bc082f7a\@[email protected]
Used in these records
Decision Notice - 010.2005.00000813.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 56 KB (small file)
- File type
No other editions are linked here.