Skip to the record
Mmm.. taste the original NoosaWatch™

Original source · versioned page text

Amended Stormwater Plan

Attached to the e-mail Information Request Response REC16/0014.

of 39

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
SC5551 - 28 Elkhorn Dr, Tewantin                                                                     7


During the construction phase of the development, silt fences should be erected downstream of all
disturbed areas. In addition erosion and sediment control devices should be regularly inspected and
maintained following storm events. An Erosion and Sediment Control Plan will be provided as part of the
operational works application.



3.3      Operational Phase
During the operational stage of the development, the following impacts have been identified in relation to
stormwater runoff and water quality of the receiving waterways:
         Gross pollutants which include human derived litter, course sediment and vegetation
         Sediment and suspended solids
         Nutrients such as phosphorous and nitrogen
To target these potential pollutants stormwater quality improvement devices (SQID’s) are proposed to be
incorporated within the design.


3.3.1    Water Quality Objectives
The water quality objectives (WQO’s) for this site were determined in accordance with Appendix 2 of the
State Planning Policy (SPP) Dec 2013.


Table 3.2 indicates the minimum load reduction targets required to be met:


                                   Pollutant               Minimum Reduction Targets

                     Total Suspended Sediments (TSS)                   80%

                            Total Phosphorus (TP)                      60%

                              Total Nitrogen (TN)                      45%

                           Gross Pollutants (>5mm)                     90%

                                         Table 3.2 - Water Quality Objectives



3.3.2    Pollutant Export Modelling
The Model for Urban Stormwater Improvement Conceptualisation (MUSIC) has been utilised to calculate
pollutant loads from the proposed development and to predict performance characteristics of the proposed
treatment train. The pollutants have been generated stochastically and modelling parameters used were
adopted from the Water by Design “Music Modelling Guidelines for South-East Queensland”, and the
updated MUSIC Version 5 recommended parameters for Bio-retention basin nodes. MUSIC modelling
setup and results are attached within Appendix B.
Log in to download the original file

Amended Stormwater Plan.pdf · 2.8 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.