Skip to the record
Noosa's #1 Council Tracker.

Original source · versioned page text

Delegated Report - Code - Planning OPW22 0145

of 1

Page text shows just the words. Original shows the document exactly as it was published.

Author	Sir/Madam,
Development Assessment

APPLICATION DETAILS
Application No.	OPW22/0145
Applicant	Professional Certification Group Pty Ltd
Proposal	Operational Works - Vehicle Crossover
Properly Made Date	6 June 2022
Information Request Date	17 June 2022
Information Response Date	8 July 2022
Decision Due Date	26 August 2022
Report Completed Date	15 July 2022
Report Reviewed By	Mark Lewis – 15 July 2022

PROPERTY DETAILS
Property Address	26 Dayspring St Sunrise Beach Qld 4567
RP Description	Lot 57 N 21851
Land Area	603.0000 m²
Existing Use of Land	Residential

STATUTORY DETAILS
SEQRP Designation	Urban Footprint
Zone	Low Density Residential
Precinct	Not Applicable
Local Plan Area	Not Applicable
Overlays	N/A
Assessment Type	Code
PROPOSAL
The application seeks approval for an Operational Works - Vehicle Crossover.
The locality and proposal plan are included below.

Figure 1 – Locality

Figure 2 – Site Plan
site details
Background
There is no Higher Order Approval requiring the works.
assessment
Instruments for Statutory Assessment
Under the Planning Act 2016 the application must be assessed against each of the following statutory planning instruments to the extent they are relevant to the development:
State Planning Policy;
South East Queensland Regional Plan;
Planning Regulation 2017; and
Noosa Plan 2020.
Noosa Plan 2020
The following codes from the Noosa Plan 2020 are applicable to this development:
Driveways and Parking Code
The application has been found to generally comply with all applicable statutory instruments.
cONSULTATION
Referral Agencies
Not Applicable
Internal Council Referrals
This application was referred internally to Council’s Senior Environmental Officer and to Parks and Gardens’ Tree Assessment Officer as the applicant proposed to remove 1 significant, mature street tree within the road reserve.
Council’s Senior Environmental Officer and Tree Assessment Officer provided their assessment and provided the applicant with two options. Option one included engaging a suitably qualified Arborist to conduct an assessment of the tree to determine if, with proper methods, the health of the existing street tree would not be severely affected as a result of the proposed works. Option two provided approval to remove the existing street tree and provide a suitable replacement street tree.
The applicant opted to proceed with option two. Accordingly, Condition 4 was written.
conclusion & reasons for decision
The proposed development generally complies with the requirements of the planning scheme and does not raise any significant issues that cannot be addressed by reasonable and relevant conditions. The application is therefore recommended for approval.
The report is provided in accordance with Section 63(5) of the Planning Act 2016.
RECOMMENDATION
With regard to Application No OPW22/0145 for an Operational Works - Vehicle Crossover situated at 26 Dayspring St Sunrise Beach Qld 4567 and described as Lot 57 N 21851, it is recommended the application be approved in accordance with the following details for the Decision Notice:
application details
Application No:	OPW22/0145
Street address:	26 Dayspring St Sunrise Beach Qld 4567
Real property description:	Lot 57 N 21851
Planning Scheme:	Noosa Plan 2020 (25 September 2020)
Decision details
Council decided to issue the following type of approval:
Development Permit for Approval for Operational Works - Vehicle Crossover
CURRENCY PERIOD of approval
The currency period for this development approval is stated in the conditions below.
assessment manager conditions
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
502746-03	5	Site Plan 1:200 Prepared by Brighton Homes As annotated by Council	12 July 2022
502746-04	5	Driveway Plan 1:200 Prepared by Brighton Homes As annotated by Council	12 July 2022
CURRENCY PERIOD
The Currency Period for this development approval lapses if the development has not substantially started by 15 July 2024, unless an application to extend the currency period is approved by Council.
SITE SPECIFIC CONDITIONS
The retained portion of the existing driveway in the Wollomia Way road reserve is to remain free from cars, trailers, campers, boats and the like from being stored on the driveway on a permanent or temporary basis.
The existing Melaleuca street tree marked for removal as per Brighton Homes’ plan 502746 Site Plan 1:200 and as annotated by Council, must be removed in accordance with Conditions 22 and 23. A single replacement street tree is to be planted at the applicant’s expense and must:
Meet AS2303:2018 Tree Stock of Landscape Use;
Meeting Specifying Trees – a guide to assessment of tree quality (NATPSEC);
Be a minimum of 45L;
Be located generally in accordance with engineering requirements for safe vehicle and pedestrian sight lines;
Be located from services and infrastructure at a minimum of:
6m from electricity poles and pillars;
4m from street lighting;
2m from stormwater catchment pits; and
2m from any adjoining driveways
Be maintained (watered) for a minimum of 12 months; and
Be species and planted according to the Noosa Plan 2020 – PSP2 – Landscaping Policy.
The final location and species of the replacement tree to be agreed on site with Council’s delegate at the pre-start meeting. A few suitable species include:
Banksia Integrifolia;
Callistemon Vaiminalis; or
Cupaniopsis Anacardiodes.
PRIOR TO COMMENCEMENT OF WORKS
Bonds
A compliance bond of $1000 (Streetscape Landscape) is to be submitted to Council prior to the pre-start meeting. The pre-start meeting will only be held once Council's Construction Engineering Officer has confirmation that the bond monies have been received by Council.
The bond will be refunded less any costs incurred by Council in ensuring compliance with these conditions or any additional inspections incurred for substandard work or work undertaken not in accordance with this permit.
Bonds must:
meet the requirements of council’s relevant Planning Scheme Policy for performance and uncompleted works.
be calculated using a schedule of works and relevant bond equation
include GST
have approval of the bond calculations and amount from Council prior to lodgement
be lodged with Council and accompanied by the Bond Administration Fee/s.
be requested for release by writing to Council, when relevant approval requirements have been met.
Engineering
All necessary approvals from external service providers (e.g. Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council.
A condition report including photographs of the frontage of the site must be completed and submitted to council at the prestart meeting / prior to any works commencing.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council prior to the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
Traffic Management during all aspects of the construct phase including:
A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction
Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased
Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures
Any changes to the details associated with the supervising Principal Contractor during construction, must be notified to council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works.
DURING CONSTRUCTION
Engineering
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Works within Road Reserve/Reinstatement
Safe vehicle and pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles.
Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council.
Site Access and Driveways
Driveway crossovers must be constructed in accordance with council’s Standard Drawings RS-049, RS-050 and any associated addendum.
The following must be complied with during the construction of the required crossover/driveway:
The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete.
The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties
Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway
Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path
The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
Slope and batters are a maximum grade of:
1 in 6 where in proximity to waterbodies
1 in 4 for grassed areas.
1 in 3 for planted areas
1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (e.g. by blocking or interfering with natural overland flows).
Removal of Existing Trees and Vegetation
Removal of existing trees and vegetation must be undertaken by a qualified person* and must include:
Stump grinding to below finished surface level
Rectification to the finished surface levels and materials
No damage to other vegetation for retention
Legal disposal of all removed vegetation and debris
Replanting in accordance with the approved plans
*(Refer to Advisory Note)
Fauna Management
A qualified person* must be engaged to manage fauna prior and during clearing to:
Ensure works are carried out in accordance with the Nature Conservation Act 1992.
Undertake pre-clearing inspections including fauna relocation and removal or blocking of all vacant hollows.
Ensuring clearing works avoids nesting times of animals and birds.
Co-ordinate staging and sequence of clearing with fauna protection.
Protect and recover fauna during clearing operations (not previously removed).
Manage the translocation of animals and recovery procedures in accordance with relevant legislation.
*(Refer to Advisory Note)
Erosion and Sediment Control
Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection Regulation 2019) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Sediment and erosion control measures must be in place prior to works commencing. If such measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such fines can be issued if sediments from the site are found to enter or have the potential to enter Council’s stormwater system, natural waterways, any downstream stormwater filtration system or adversely impacting on other properties. Council may request further controls to be installed should the implemented measures be found inefficient.
The erosion and sediment control measures must be designed, installed and maintained in accordance with the supervising engineer instructions and the current best practice standards * (Refer to Advisory Note).
The developer must ensure sediment does not leave the site or enter onto adjoining properties or Council’s drainage system due to surface runoff or on tyres of vehicles and/or machinery. It is essential to implement appropriate approved erosion and sediment control measures throughout the site during all phases of construction including vehicle shakedown pad/grid (or similar) at the access to the construction site. Where sediments or other contaminants are deposited on a road, they must be removed so as not to enter Council’s drainage system or waterways.
Prior to the completion of the development and commencement of use, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium to long-term. For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.
FOLLOWING CONSTRUCTION
On Maintenance
Maintenance periods* must be:
12 months for Streetscape Landscape.
*(Refer to Advisory Note)
Prior to requesting an On Maintenance inspection the following (prepared by respective qualified persons* and certifying compliance with approvals) must be submitted to Council:
Landscaping certification.
Specifying Trees: a guide to assessment of tree quality (NATSPEC) certification (addressing each specimen).
Off Maintenance
Prior to requesting an Off Maintenance inspection the following must be provided:
Written request of bond release.
Off Maintenance Inspection must be requested:
By contacting Council.*
Only after lodgement of all required certification and documentation.
Only after all works are confirmed in good order including:
Rectifying any damaged grassed areas.
Topdressing to grassed areas.
Remulching, fertilising and aeration of garden areas.
Replacement of plant material.
*(Refer to Advisory Note)
Prior to requesting an Off Maintenance inspection, the developer must provide a written request for the Off Maintenance inspection.
A re-inspection free in accordance with Council’s Fees and Charge Register will be charged where:
A Council inspection reveals works do not comply with approval requirements.
Submitted certification falsely states works comply with approval requirements.
Certification
A final inspection and approval of the new driveway and completed reinstatement works by Council’s Inspector is required. Please contact Council on 5329 6500 to arrange for the inspection.
referral agencies
Not applicable.
Advisory notes
ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
General Advisory Notes
Qualified Person, for the purpose of:
Supervising landscape works and preparing a landscape certification, is considered to be a landscape architect, landscape designer or horticulturist with a minimum of three years current experience in the field of landscape design.
Undertaking landscape construction and establishment works is considered to be a person with five years current experience in commercial landscape construction projects.
Undertaking rehabilitation construction and establishment works is considered to be a person with five years current experience in revegetation and regeneration.
Undertaking, supervising tree works and preparing arboriculture certification, is considered to be a person with a minimum three years current experience in tree protection, hazard identification/mitigation and Specifying Trees – a guide to assessment of tree quality (NATSPEC) assessment and either:
International Society of Arboriculture (ISA) certification; or
A Diploma of Arboriculture.
Managing Fauna protection is considered to be a certified Fauna Spotter Catcher.
Managing Fauna protection is considered to be an Ecologist or Environmental Scientist with a minimum of three years current experience in the field of fauna assessment and management.
Managing Fauna protection, preparing Fauna reporting and certification and calculating compensatory habitat, is considered to be an Ecologist or Environmental Scientist with a minimum of three years current experience in the field of fauna assessment and management.
Undertaking Fauna site works and calculating compensatory habitat is considered to be a Fauna Spotter Catcher with current certification under the Queensland Parks and Wildlife Service.
As this driveway is a private structure, the owner bears full responsibly for the standard of its construction, maintenance and any liabilities associated with its construction. It is recommended that professional advice be sought for the construction of the driveway to ensure that the driveway is constructed in accordance with standard drawings RS-049, RS-
Council reserves the right to call up any performance bond held or levy charges against the property, should emergency works be required to be undertaken by Council to make the site safe due to inactivity on the development site for extended periods of time.
Should any changes or modifications to the approved plans be required as a result of construction constraints, a “Request to change an existing approval” under the Planning Act 2016 must be made. Amended plans clearly indicating the changes must be lodged with this application along with the appropriate fees.
Prestart, On and Off Maintenance Inspections Request
Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5 business days notice of preferred inspection time.
If Council officers are required to undertake additional inspections of the same works, a reinspection fee will be applicable in accordance with Council’s Fees and Charges register applicable at the time.
A minimum maintenance period of 12 months will apply to all municipal works and thereafter until such time as the works are performing in accordance with the approved design unless noted otherwise.
Request for On Maintenance is the responsibility of the developer.  No credit will be given due to failure to request inspection.  Maintenance works are the responsibility of the developer and must include regular inspections, repairs, rectifications and establishment.  A single maintenance run immediately prior to inspection is not acceptable.
Environmental Advisory Notes
The Environmental Protection Act 1994 states that a person must not carry out any activity that causes, or is likely to cause, environmental harm unless the person takes all reasonable and practicable measures to prevent or minimise the harm. Environmental harm includes environmental nuisance. In this regard persons and entities, involved in the civil, earthworks, construction and landscaping phases of this development are to adhere to their ‘general environmental duty’ to minimise the risk of causing environmental harm.
Erosion and Sediment Control
Accepted best practice standards include International Erosion Control Association Australasia Best Practice Erosion and Sediment Control
As a general rule, a site is determined to have achieved effective short-term stabilisation if at the time of the plan sealing inspection:
Methods of stabilisation are:
appropriate for slopes and slope lengths; and
are consistent with best practice environmental management practices such as in the Manual for Erosion and Sediment Control or the IECA Manual; and
Stormwater runoff from the site is not currently, and is not likely to result in visible evidence of sedimentation or erosion, or lead to water contamination.
Landscaping
The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges Register where:
An inspection revealed that any landscape works do not comply with the conditions of the Decision Notice, Approved Plans and or Approved Documents
Certification is submitted to Council falsely stating that works comply with the approved plans, documents and or conditions of the Decision Notice.
Public amenity trees are defined as any tree located within public streets, parks or areas that will become publically owned as a result of this development.
property notes
Not applicable.
VARIATION approval details
Not applicable.
further development permits required
Not applicable.
submissions
Not applicable.
RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the Planning Act 2016 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval. If Council agrees or agrees in part with the representations, a negotiated decision notice will be issued. Only one negotiated decision notice may be given.
OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at www.noosa.qld.gov.au or at Council Offices.

[word/footer1.xml]
Page 4 of 11

[word/header1.xml]
3

[word/header2.xml]
DEVELOPMENT ASSESSMENT DELEGATED REPORT

[Attachment: image2.png (image text)]
 

13,000 EAVE

 

 

3,450 WALL

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DAYSPRING STREET

 

 

 

TREES TO BE REMOVED

‘pasta
L_sy cane Pion 10
‘COMMENCEMENT OF

 

Outlet

 

WOLLOMIA WAY
Log in to download the original file

Delegated Report - Code - Planning OPW22 0145.docx · 1.2 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.